CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Kent County Council
Policy and Resources Cabinet Committee, Wednesday 5 March 2025 at 10.00am

Contract Management Review Group update

Noted Executive 1 paper

Policy and Resources Cabinet Committee noted this item on Wednesday 5 March 2025. Below is the council's own wording, with the papers it was decided on.

Item251

Resolved

RESOLVED to consider and note the Contract Management Group update.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Policy and Resources Cabinet Committee, 5 pages

Summary

This report reflects on the work of the Contract Management Review Group (hereinafter referred to as CMRG or the Group).

The paper summarises the key outcomes and common themes emerging from the contract reviews that have been undertaken and assesses the impact that the Group has had in the time period since the last report to Committee on 10 July 2024. The paper also looks forward to the work programme of the CMRG for the coming six months and identifies opportunities to further improve how the Group is contributing to raising the standard of contract management across the Council.

Recommendation(s):

Policy and Resources Cabinet Committee is asked to consider and note this report.

1. Introduction

1.1The CMRG was first established in September 2016. Since its establishment, the Group has maintained a key role in identifying and promoting the best practice of contract management across the Council, while highlighting areas for further improvement.

1.2This paper reflects on the contract reviews that have been undertaken since the last update to the Committee, areas of focus identified during the Group’s reviews, and emerging themes. This paper outlines the future work programme for the CMRG, and opportunities for continuous improvement and learning.

2. Reflections on CMRG contract reviews since September 2024

2.1The workplan completed across 2024 reviewed contracts covering multiple directorates and a diverse range of services.

2.2Since the last update to Policy and Resources Cabinet Committee in July 2024, the CMRG has met a total of three times and reviewed four contracts identified as being of strategic importance. 2.3 The table below outlines the contracts that have been reviewed at the CMRG. It notes the point at which the contracts were reviewed and the key outcomes following discussion.

Date Contract/s Total Value Review Key Outcome/s Point 19.09.24 KCC £15,585,000 Mid life The contract management arrangements Cleaning (including were positively received by the Group. Services potential Further information on commercial Corporate extension) performance was requested; contract leads were advised to liaise with KCC finance to understand what additional financial information can be requested from the supplier and provide a clearer understanding of the auditing process of the cleans to help determine performance. The Group discussed and noted recommendations on reviewing the social value model. 5.11.24 People’s £3,761,295 Mid life The contract management arrangements Voice (including were discussed at length during the Group. potential Recommendations to re-visit and review KPI extension) wording, contract management oversight, review of contract specification to see if there are savings to be made by reducing activity delivered, and financial information were offered. The contract lead will be re- attending the CMRG later in 2025, prior to any proposed extension. 21.1.25 Safe £2,790,700 Prior to This prior to extension presentation was well Accommod (including Extension received by the Group, who felt the contract ation potential management arrangements were well Support extension) explained, and practices undertaken to drive Service cost savings were well received. Recommendations were noted on KPI’s to further drive supplier performance. 21.1.25 Kent £23,915,291 Prior to The presentation detailed the proposed Integrated Extension commissioning approach, which was well Domestic received by the Group, who noted its Abuse thorough and detailed manner. Service

2.4The CMRG assessed the above contractual arrangements’ level of maturity against different elements of contract management, using the NAO Good Practice Contract Management Framework, which is applied in proportion to the contract’s strategic importance.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Management Review Group updateReport 5 pages DownloadRead as text

At this meeting

Whole meeting
249Minutes of the meeting held on 15 January 2025Decided 250Risk Management: Chief Executive and Deputy Chief Executive DepartmentsOn the agenda
251Contract Management Review Group updateThis decision
252Commercial and Procurement Performance Report - Quarters 2 and 3, 2024 / 2025On the agenda 25325/00004 - Council Tax Collection Subsidies and IncentivesOn the agenda 25425/00033 - Extension of Domestic Abuse Act Framework and KIDAS contractAgreed 25525/00003 - Disposal of land at Stanhope Road, Ashford TN23 5RA.Agreed 25624/00107 - Disposal of land adjacent to Stourmouth Road, Preston CT3 1HPAgreed 25725/00026 - Disposal of surplus land at Broomhill Bank school (North), Puddledock Lane and Rowhill Road, Hextable BR8 7RPAgreed 25825/00013 - Freehold disposal of Former Aylesford CTS Workshops, Landscape Services Depot and Rear of Danepack located at Forstal Road, Maidstone (Herein referred to as Aylesford Depot)Agreed 25925/00027 - Formal Lease for an Electricity Sub Station within grounds of the former Walmer Science College, Deal - to serve The Beacon and the Southwood Centre, DealAgreed 26025/00024 - Granting of Formal Lease for a Solar Panel installation within the grounds of St Nicholas' School, Canterbury.Agreed 26125/00025 - Granting of Formal Lease for a Solar Panel installation within the grounds of Brunswick House Primary School, MaidstoneAgreed 26225/00028 - Construction of new office building at Henwood Highways Depot - Disposal of surplus office buildingAgreed 26324/00101 - Contact Centre ProcurementAgreed 264Work ProgrammeNoted 265Cyber Security UpdatePrivate

On this subject at Kent

Search all
  1. Contract Management Review Group updateThis decision
  2. Update from the Contract Management Review Group (CMRG)Decided
  3. 25/00043 - Old Rectory Business Centre Management ContractApproved
  4. 24/00083 - Old Rectory Business Centre Management ContractApproved
  5. Contract Management Review Group updateNoted
  6. Contract ManagementNoted

More from Kent Policy and Resources Cabinet Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the meeting held on 6 May 2026RESOLVED that the minutes of the meeting held on 6 May 2026 were a correct record and that they be signed by the Chai... Decided Open
2 Jul 2026 Local Outcomes FrameworkRESOLVED that the report be noted. Noted Open
2 Jul 2026 Budget Planning Process 2027-28 and Medium-Term Financial Plan (MTFP) UpdateRESOLVED that the report be noted. Noted Open
2 Jul 2026 26/00032 - Adoption of the KCC Winning for Kent: Procurement with Purpose Policy 2026-2028RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Approve the adoption and implementation of... Approved Open
2 Jul 2026 Work ProgrammeRESOLVED that the work programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies