Growth, Economic Development and Communities Cabinet Committee noted this item on Thursday 11 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the report.
1.1The Lower Thames Crossing (LTC) is a Nationally Significant Infrastructure Project (NSIP) being delivered by National Highways. The scheme’s Development Consent Order (DCO) was given approval by the Secretary of State for Transport on 25 March 2025. The LTC will provide an entirely new road crossing of the River Thames east of London, linking the M25 in Havering, the A13 in Thurrock and the A2 in Kent (east of Gravesend). The proposal includes 14.3 miles of new road and around 50 new bridges and viaducts. The crossing beneath the River Thames will comprise of two 2.6- mile tunnels making it the longest road tunnel in the UK.
1.2Currently the Dartford Crossing is the only way to cross the Thames east of London by road. This was designed to handle 135,000 vehicles a day, but the daily average now is 150,000 – with the busiest days seeing up to 180,000 vehicles using it. Almost 40% of the vehicles using the Dartford Crossing each day are freight vehicles or Heavy Goods Vehicles (HGVs) some 10,000 of which pass through Kent to and from the Channel ports each day. The LTC will alleviate capacity constraints at Dartford while adding resilience to the strategic road network in and around Kent, albeit when combined with other required improvements to the A2/M2 and A20/M20 corridors and connecting roads. 1.3 The total estimated cost of the project is expected to be around £10 billion. On the 16th June 2025 the UK Government announced £590 million to allow National Highways and their appointed contractors to progress with the detailed design and undertake pre-construction work. The UK Government is currently exploring different financing models to fund the remaining construction costs, and this includes opportunities for private sector investment.
1.4At the earliest, construction of the Lower Thames Crossing could start in 2026 and last a total of six years. As it stands the project is anticipated to have an opening year of 2032/2033. However, these timescales could change depending upon the final funding model.
1.5Increased crossing capacity and greater journey time reliability will mean that residents and businesses in Kent will have a much greater range of opportunities for work, education and leisure. The LTC will unlock growth opportunities that are currently suppressed by the unreliability of the Dartford Crossing, which has constrained productivity in the Lower Thames area.
1.6Various KCC teams are working closely with the LTC team including the Economy function to ensure that the scheme benefits the county as much as possible given its unique scale and the opportunities this represents.
1.7This paper focuses on the economic benefits that the LTC will bring about as a new strategic trade route between the ports of the south-east, the midlands and the north. The LTC has the potential to create jobs, upskill local people and open up new opportunities for businesses.
2. Boosting the Kent & Medway Economy: 2.1 In expressing support for the scheme as an interested party during the planning application stage, private sector representatives of the Kent & Medway Economic Partnership (KMEP) and the Kent & Medway Business Advisory Board emphasised that the LTC had the potential to:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Lower Thames Crossing- Economic ImpactReport | 6 pages | DownloadRead as text |
Follow Growth, Economic Development and Communities Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Nov 2025 | Election of ChairRESOLVED that [name removed] be elected as Chair of the Growth, Economic Development and Communities Cabinet Committee. | Decided | Open |
| 11 Nov 2025 | Minutes of the meeting held on 11 September 2025RESOLVED that the minutes of the meeting held of 11 September 2025 were a correct record and they be signed by the Ch... | Decided | Open |
| 11 Nov 2025 | KMEF- Ambition 2- Widen opportunities and unlock talentRESOLVED to note the report. | Noted | Open |
| 11 Nov 2025 | Regional Energy Strategic PlanRESOLVED to note the report. | Noted | Open |
| 11 Nov 2025 | Decisions taken between Cabinet Committee Meetings- 25/00084It was agreed that consideration would be given to Member involvement in the reinstated Visitor Economy and Inward In... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.