25/00089 - Highways Emergency Tree Works Contract

Agreed Executive 3 papers

Growth, Environment & Transport Cabinet Committee agreed this item on Tuesday 4 November 2025. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

RESOLVED to endorse the proposed decision, namely: That the Cabinet Member for (the Kent) Environment agree to: 1. ... view the full minutes text for item 42.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Environment & Transport Cabinet Committee, 7 pages

From: Peter Osborne Cabinet Member for Highways and Transport

Simon Jones, Corporate Director of Growth, Environment and Transport

To: Environment & Transport Cabinet Committee Meeting – 4 November 2025.

Subject: Procurement and award of contract/s for Highway Emergency Tree Works Contract

Key decision: Yes 25/00089

Classification: Unrestricted

Past Pathway of Paper: N/A

Future Pathway of Paper: Cabinet Member Decision

Electoral Division: All Districts.

Summary: The Highway Emergency Tree Works Contract is currently delivered by two Contractors, one serving the West of the County and the second the East. These Contracts expire on 31st March 2026. There are no further extension options, and a new contract is therefore required to be in place for 1st April 2026. A Key Decision is required to award the contract/s for this service as the value exceeds £1m.

Recommendation(s): The Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Highways and Transport on the proposed decision to give:

1. APPROVAL to procure and award a new Emergency Tree Works contract for up to five years with an opportunity to extend this for up to three further years,

2. DELEGATE authority to the Director of Highways and Transport to take relevant actions to facilitate the required procurement activity,

3. DELEGATE authority to the Corporate Director of Growth, Economy and Transport, in consultation with the Cabinet Member for Highways and Transport to take relevant actions including but not limited to awarding, finalising the terms of and entering into the relevant contracts or other legal agreements, as necessary, to implement the decision and

4. DELEGATE authority to the Corporate Director of Growth, Economy and Transport, in consultation with the Cabinet Member for Highways and Transport, to award extensions of the contract in accordance with the relevant clauses within the contract as shown at Appendix A. 1. Introduction

1.1The existing contract (SC21010) is currently operating under an 18-month extension period, which commenced in November 2024 and will conclude on the 31st of March 2026.

1.2While the contract includes an option to extend for a further 18 months, the projected spend during this period would exceed the originally advertised and approved contract value, rendering further extension commercially and procedurally unviable.

1.3There are therefore no further extension options, and a new contract is required to be in place for 1st April 2026.

1.4The current contract delivery model is for two lots, East and West. This has worked well for the duration of the contract and provided the necessary resilience for major storm events.

1.5The Council has a legal duty to keep roads and pavements clear of vegetation for safe passage of highway users. The service is principally concerned with the clearance of felled trees from the highway network, most notable in adverse weather conditions. To ensure the Council meets its statutory obligations the service will need to be re-commissioned.

1.6The requirement is for the provision of emergency response specialist tree surgery teams to attend at short notice on a 24/7 basis 365 days of the year. Emergency type response times will include 2-hour and 24-hour requirement. The service is used by all operational staff but also supports the highways out of hours emergency response service.

1.7There is no programmed works and work volumes are dictated by the weather and when emergency situations occur. This varies from year to year and is largely dependent on the prevailing weather and storm events.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/00089: Highways Emergency Tree Works ContractReport 7 pages DownloadRead as text
PDF
Proposed Record of DecisionAppendix A 2 pages Download
PDF
Highways Emergency Tree Works Contract Ref CN260458Appendix B 5 pages Download

At this meeting

Whole meeting

Who was there

15 of 17 attended
AB
Alister BradyCommittee Member, present
MB
Martin BriceCommittee Member, present
PC
Paul ChamberlainCommittee Member, present
WC
Wayne ChapmanCommittee Member, present
JD
James DefriendCommittee Member, present
BF
Ben FryerCommittee Member, present
JH
Jamie HendersonCommittee Member, present
MH
Mark HoodCommittee Member, present
SH
Sarah HudsonCommittee Member, present
IK
Isabella KempCommittee Member, apologies
RP
Richard PalmerCommittee Member, present
MP
Martin PaulCommittee Member, present

All 17 on the meeting page

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies