CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Kent County Council
Scrutiny Committee, Tuesday 25 November 2025 at 2.00pm

Revenue and Capital Budget Forecast Outturn Report - Quarter 2

Noted Scrutiny 2 papers

AI summaryKent County Council’s Scrutiny Committee noted the Quarter 2 budget forecast report and debate comments [D]. The report forecasts a £46.5m revenue overspend excluding Schools’ Delegated Budgets and a £35.4m capital underspend, with mitigation work under way [P2][P11][P18][P60].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarter 2 monitoring covered revenue, capital, savings and reserves [P1]
Money£46.5m revenue overspend [P11][P18]Capital forecast underspend is £35.4m [P60]
What happens nextNot stated
Who it affectsCouncil services and reserves [P11][P56]Adult social care and schools have the largest variances [P11]

What was decided

The Scrutiny Committee noted the Quarter 2 budget forecast report and the comments made during debate.

Why

The forecast revenue overspend required immediate attention, and steps were being taken to reduce it. Report P2

Revenue was forecast at £46.5m above budget, excluding Schools’ Delegated Budgets. The overall position worsened from £27.9m in Quarter 1 to £47.2m in Quarter 2. Report P11, P18

Adult Social Care & Health carried the largest revenue overspend at £50.9m. This included £20.9m of savings no longer expected and £30.0m of service related pressures. Report P11, P22

What happens next

Send a clear message to all staff that only essential spending should continue. Any non staffing spending treated as statutory must be justified by the relevant legislation. Report P12

Require budget managers to stay within budget and seek underspends. Review grant funded spending and recruitment, with a panel checking forecast increases from October to November. Report P12

Control adult social care recruitment through a vacancy panel, review fixed term and interim roles, increase scrutiny of key savings, and update practice guidance. Report P13, P14

The money

  • £46.5m Forecast revenue overspend, excluding Schools’ Delegated Budgets Report P18, P20
  • £50.9m Adult Social Care & Health forecast overspend Report P11, P20
  • £133.4m Forecast deficit on the central schools reserve Report P49, P57
  • £37.2m Schools’ Delegated Budgets forecast overspend Report P14, P21
  • £27.6m Savings not expected to be delivered in 2025-26 Report P14
  • £35.4m Forecast underspend against the capital budget Report P16, P60
  • £118.4m Total savings and additional income requirement for 2025-26 Report P14, P51
  • £1,531.9m Current working revenue budget for 2025-26 Report P11

Options considered

  • Chosen: Note the report and comments made during debate

Implications

  • Financial: The £46.5m revenue overspend must be funded from reserves, with a forecast £46.5m drawdown in 2025-26. Report P11, P56
  • Financial: Adult Social Care & Health includes £20.9m of savings no longer anticipated this year and £30.0m of other service related pressures. Report P11, P22
  • Financial: Of the £118.4m savings and income target, £27.6m is not expected in 2025-26. This comprises £9.2m planned for future years and £18.4m no longer deliverable, with £2.9m of alternative savings identified. Report P14
  • Financial: The capital underspend combines a +£26.2m real variance and a -£61.6m rephasing variance. Of the real variance, £20m comes from additional funding not yet in the budget. Report P16, P60
  • Financial: The Dedicated Schools Grant is forecast to overspend by £64.7m. The central schools reserve deficit is forecast at £133.4m, while maintained school balances show a £57.2m surplus. Individual school balances cannot offset the central deficit. Report P49
  • Risk: The Dedicated Schools Grant deficit is the council’s single biggest financial risk. The council no longer expects an in year breakeven position by 2027-28, with a residual accumulated overspend of around £125m forecast by March 2028. Report P49
  • Legal: Recruitment is to be authorised only for core statutory duties. Adult social care practice guidance is being updated to meet Care Act eligibility criteria. Report P13, P14
  • Staffing: A vacancy control panel will review recruitment. Fixed term and interim roles that are not critical to core duties will end. Report P13

Who and where

  • Adult social care service users Report P13, P22
  • Older people using residential or community based care Report P22
  • Children and young people in care Report P30
  • Children and young people with special educational needs and disabilities Report P49
  • Maintained schools Report P49
  • Adult social care contract providers Report P14
  • Council staff Report P12, P13
  • Passengers using the English National Concessionary Travel Scheme Report P33

Timeline

  • 2025-26: The working revenue budget is £1,531.9m. Report P11
  • end of September 2025-26: The revenue and capital forecast position was reported. Report P1
  • September 2025: Savings delivery was 81%, with £98m expected in 2025-26. Report P14
  • October to November: A panel will review any increase in forecasts. Report P12
  • 31st March 2026: The central schools reserve is forecast to have a £133.4m deficit. Report P49
  • 2026/27: Changed demand and unavoidable pressures are proposed for budget realignment. Report P33, P34
  • end of the 2027-28 year: The statutory override for managing school grant deficits comes to an end. Report P14
  • March 2028: A residual accumulated school grant overspend of around £125m is forecast. Report P49

Plain English for the jargon

  • ASCH: Adult Social Care & Health, the council directorate [P22]
  • Strategic Reset Programme: A programme that monitors key savings and works with service areas to replenish reserves [P11][P14]
  • BRAG: A monthly savings rating using blue, red, amber and green [P14]
  • Dedicated Schools Grant: A ring fenced grant payable to local authorities for school budgets [P49]
  • Safety Valve Programme: A Department for Education programme supporting recovery plans for councils with the highest school grant deficits [P14][P49]
  • High Needs Block: The schools grant block funding higher cost places and support for children and young people with special educational needs and disabilities [P49]
  • ENCTS: The English National Concessionary Travel Scheme, with free or discounted travel passes and rising passenger journeys [P33]
  • Capital variances: A real variance changes a project’s total cost, while a rephasing variance changes project timing [P11][P60]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22

Resolved

RESOLVED that the Committee note the report and the comments made during debate.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Scrutiny Committee, 65 pages

Summary

The attached report sets out the revenue and capital budget forecast monitoring position as at the end of September 2025-26, including progress against savings targets within the revenue budget, capital cash limit changes made between that Q1 and Q2 and monitoring updates for reserves, treasury management and prudential indicators.

The forecast revenue overspend reported needs immediate attention and steps are being taken to mitigate the level of the overspend. The report details the activities that have are being implemented to improve the situation and Cabinet are asked to endorse and support this approach.

Recommendation(s):

Cabinet is asked to:

a) NOTE the revenue and capital forecast outturn position for 2025-26 as detailed in the report, and accompanying appendices

b) NOTE the implementation of actions to mitigate the revenue overspend, both within Adult Social Care & Health specifically and across the authority

c) AGREE the revenue and capital budget adjustments detailed in the report

Contact details

Report Authors Relevant Director Cath Head John Betts Head of Finance Operations Interim Corporate Director Finance 03000 416 934 03000 410 066 [email protected] [email protected] Joe McKay Acting Chief Accountant 03000 419 601 [email protected] Joanna Lee Capital Finance Manager 03000 416 939 [email protected]

Page 1 Contents About this report .................................................................................................................................3 The revenue position .........................................................................................................................3 Urgent actions to mitigate the revenue overspend ............................................................................4 Savings and additional income ..........................................................................................................4 The capital position ............................................................................................................................5 Section 1 | Revenue by directorate ....................................................................................................6 Section 2 | Savings and additional income by directorate ...............................................................20 Section 3 | Reserves monitoring ......................................................................................................21 Section 4 | Capital by directorate .....................................................................................................23 Section 5 | Treasury Management Monitoring .................................................................................30 Treasury Management Indicators ....................................................................................................32 Appendix 1 | Key Service Statement ...............................................................................................35 Appendix 2 | Savings Statement ......................................................................................................43 Appendix 3 | Prudential Indicators ...................................................................................................61

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25-00095: Revenue and Capital Budget Forecast Outturn Report: Quarter 2, 19/11/2025 CabinetReport 65 pages DownloadRead as text
PDF
Revenue and Capital Budget Forecast Outturn Report: Quarter 2Report 2 pages Download

At this meeting

Whole meeting

Who was there

13 of 19 attended
RS
Richard Streatfeild, MBEChair, present
AB
Alister BradyVice-Chair, present
WC
Wayne ChapmanCommittee Member, present
JD
James DefriendCommittee Member, present
JE
Jeremy EustaceCommittee Member, present
AH
Antony HookCommittee Member, present
MH
Mark HoodCommittee Member, present
SH
Sarah HudsonCommittee Member, present
TM
Terry MoleCommittee Member, present
TS
Trevor ShonkCommittee Member, present
GS
Garry SturleyCommittee Member, present
DT
Dean TruderCommittee Member, present

All 19 on the meeting page

On this subject at Kent

Search all
  1. Revenue and Capital Budget Forecast Outturn Report - Quarter 2This decision
  2. 26/00055 - Revenue and Capital Budget Monitoring Report - Q1 2026-27Agreed
  3. Draft Revenue Budget 2026-27, Medium Term Financial Plan (MTFP) 2026-29, Draft Capital Programme 2026-2036, and draft Treasury Management StrategyAgreed
  4. 25/00077 - Revenue and Capital Budget Monitoring Report - Quarter 1 2025-26Agreed
  5. 25/00064 - Consolidated Active Travel Funding Grant (CATF -Tranche 6) - Capital & RevenueAgreed
  6. Revenue and Capital Budget Monitoring Report – November 2024-25Noted

More from Kent Scrutiny Committee

All decisions
MeetingDecisionOutcome
3 Aug 2026 Minutes of the meeting held on 11 June 2026RESOLVED that the minutes of the meeting held on 11 June 2026 were a correct record and they be signed by the Chair. Decided Open
3 Aug 2026 Work ProgrammeIt was agreed that LGR related matters would initially be considered by the relevant Cabinet Committee and could subs... Agreed Open
1 Jul 2026 Minutes of the meeting held on 13 May 2026RESOLVED that the minutes of the meeting held on 13 May 2026 were a correct record and they be signed by the Chair. Decided Open
1 Jul 2026 Work ProgrammeRESOLVED to note the . Noted Open