26/00011 - Cliff Collapse - Road of Remembrance, Folkestone
AgreedExecutive3 papers
AI summaryKent County Council's Growth, Environment and Transport Cabinet Committee endorsed plans to stabilise the cliff above the Road of Remembrance in Folkestone at a cost of around £5m, with a contribution from Folkestone and Hythe District Council, and works starting after May mobilisation.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet Committee endorsed the decision to proceed with cliff stabilisation works
Moneyaround £5m
What happens nextMobilise on site in MayWorks may take up to eleven or twelve months to complete
Who it affectsRoad users and cliff-top residents
What was decided
The Cabinet Member for Highways and Transport is recommended to approve progression of embankment stabilisation works using KCC capital funding from the 2026/27 Highways and Transport capital budget. Report 6.2
Accept a financial contribution from Folkestone and Hythe District Council towards the works, drawn from on-street parking monies collected by the district council. Report 6.2
Deliver the works via the existing Road Asset Renewal Contract with GW Highways, which has provision and financial capacity to accommodate the project. Report 5.2
Why
A major landslip of trees and soil from the cliff occurred on 27 January 2024, and the road has remained closed for over two years due to ongoing risk of further significant collapses. Report P1, 2.1, 3.1
Expert geological advice identifies a high likelihood of further cliff failures, including rotational slips and sudden toppling of the near-vertical overhanging crest, with risk to road users, properties at the top of the cliff, and the road itself. Report 3.6, 3.7, P21
KCC has a duty under section 41 of the Highways Act 1980 to maintain the highway, and legal advice indicates likely liability for any damage or injury caused by further collapse. Report 7.1
What happens next
Officers are reviewing design and costings, liaising with the supply chain and ecologists, and working on necessary legal agreements, with a current target to mobilise on site in May. Report 5.3
The Corporate Director of Growth, Environment and Transport will take any further decisions needed for the scheme to proceed, following consultation with the Cabinet Member for Highways and Transport. Report 11.1
Stabilisation works are estimated to take up to eleven or twelve months to complete once started. Report 5.3
The money
around £5m Estimated cost of the full Option 3 stabilisation design (974 stainless steel soil nails, erosion control mat, mesh facing, drainage, four-metre shotcrete crest) Report P32, 6.2
around £250k Potential saving from using galvanised nails and fittings instead of stainless steel, rejected as it would reduce design life by two-thirds or more Report P37
Options considered
Rejected: Do nothing (keep road closed indefinitely). Continued high risk of further significant collapses threatening road integrity, road users who ignore closure, and properties at top of cliff; would also make any later solution more extensive and costly Report P24, P25, P26, P27
Rejected: Temporary or interim measures such as concrete blocks or catch-fencing to allow partial or full reopening. Insufficient confidence of safety given unpredictability of collapse severity and mass; blocks and fencing only adequate for small landslips and rockfalls Report P28, P29, P30
Chosen: Full engineering solution to stabilise the cliff and safely reopen the road (Option 3). Safely stabilises the cliff, removes serious hazards, eliminates risk of damage to the road, and enables safe reopening Report P31, P32, P35, 5.1
Rejected: Option 3 with reduced design life using galvanised nails instead of stainless steel. Would not obtain required technical approval and would significantly reduce design life by two-thirds or more Report P36, P37
Implications
Financial: Estimated cost of around £5m; emergency costs of this scale cannot reasonably be absorbed by Highways and Transportation without significant reduction in preventative maintenance. Report 6.1, 6.2
Legal: KCC has a duty under section 41 of the Highways Act 1980 to maintain the highway; legal advice indicates likely court liability and a theoretical risk of corporate manslaughter prosecution if a further collapse causes damage or injury. Report 7.1
Equalities: An Equalities Impact Assessment concluded no protected groups are disproportionately affected by the works, but keeping the road closed would disproportionately affect disabled people due to the length of alternative routes. Report 8.1
Risk: High likelihood of continued and potentially larger-scale cliff failures including rotational slips, shallow translational slides, toppling failure of overhanging sections, ongoing erosion, and groundwater pressure build-up. Report 3.7, P21
Other: The Road of Remembrance is historically important and a vital link between the Leas and harbour areas of Folkestone, with significance for local regeneration and economic growth. Report 2.1, 10.2
Who and where
Road users, pedestrians and cyclists who would use the Road of Remembrance between The Leas and Folkestone harbour Report 1.2, 2.1, 5.3
Residents and property owners at the top of the cliff, where the crest is close to buildings Report P15, P26
Folkestone and Hythe District Council, contributing on-street parking monies towards the works Report 6.2, 12.2
GW Highways and their sub-contractor delivering the works through the Road Asset Renewal Contract Report 5.2
Timeline
27 January 2024: Major landslip of trees and soil from the cliff north of the Road of Remembrance; road closed on safety grounds Report P1, 3.1
12 February: Full Council approved the 2026/27 capital budget including funding for Category 1 significant unfunded highway risks including the Road of Remembrance collapse Report 6.2
10 March 2026: Growth, Environment and Transport Cabinet Committee meeting considering endorsement of the proposed decision Report P4, P56
May: Target to mobilise on site to start stabilisation works Report 5.3
up to eleven or twelve months: Estimated duration of the stabilisation works from start Report 5.3
Plain English for the jargon
Soil nails: Steel bars inserted into a slope or cliff face to reinforce it and prevent movement
Shotcrete: Sprayed concrete applied to a surface, used here to create a four-metre-high protective facing at the top of the cliff
Ground Penetration Radar (GPR): A non-invasive method of mapping underground features
Cone Penetration Tests (CPT): Tests that measure the strength of ground by pushing a cone-tipped probe into it
Road Asset Renewal Contract: KCC's existing contract (held with GW Highways) used to deliver the stabilisation works
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item76
Resolved
RESOLVED to endorse the proposed decision, namely: That the Cabinet Member for Highways and Transport agree to: (a) Give approval to progress the construction of the embankment stabilisation and associated works utilising KCC capital funding as identified in the 26/27 H&T capital budget. (b) Accept a contribution from Folkestone and Hythe District Council to contribute towards funding the works. (c) Deliver the works via the Road Asset Renewal Contract that has provision and financial capacity to accommodate these works. (d) Approval for any other further decisions required to allow the scheme to proceed through to construction to be taken by the Corporate Director of Growth, Environment & Transport under the Officer Scheme of Delegations following prior consultation with the Cabinet Member for Highways and Transport.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 7 pages
Summary
On 27 January 2024, a major landslip of trees and soil occurred from a cliff north of the Road of Remembrance, blocking the road. The road remains closed and there is a risk of further significant collapses with the potential to damage the road itself.
The report describes the unique complexities and challenges involved with this collapse, and explains how the authority proposes to stabilise the cliff to protect this historic road and enable it to be safely re-opened for public use. As part of that, it is necessary to seek a key decision to progress the delivery of necessary engineering works.
Recommendation(s):
The Growth, Environment and Transport Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Highways and Transport in relation to the proposed decision as detailed in the attached Proposed Record of Decision document (Appendix A).
1. Introduction 1.1 The Road of Remembrance is an historically important road linking the Leas and harbour areas of Folkestone. It has been closed for over two years to protect road users. During that time, officers have carried out site and other investigations, in order to understand geological, stability, legal, risks and other issues, and to carry out a detailed options appraisal given the ongoing risk to the road itself.
1.2The proposed engineering works are necessary to protect the road from further damage and to safely re-open this important road, and to reduce the risk of harm to residents and damage to properties at the top of the cliff and those who may chose to ignore formal closure of the road below.
2. Key Considerations
2.1The Road of Remembrance has been closed for a prolonged period, and will remain so unless action is taken to stabilise the cliff above. It is an historically important road, central to the character of Folkestone and a vital link between the Leas and harbour areas.
2.2The cliff is very unstable and there is a high risk of further significant collapses which may cause structural damage to the road itself.
2.3There are potential risks to injury of persons in the event of further significant collapses.
Background
3.1After the collapse occurred, we immediately closed the road on safety grounds to protect the public from further landslips, before removing trees and soil. The road itself remains closed since it would not be safe to re-open it given the risk of further collapses of the cliff above.
3.2Whilst the road itself did not appear to need repair at that time, we were concerned about the risk of the road being damaged and taken out of service if further collapses of the cliff above were to occur, especially since the road itself is on top of a further cliff below. As such, we worked as quickly as possible to get to the point where we could stabilise the cliff above so far as that is possible without substantive engineering works.
3.3A lot of technical and complex work has been carried out on site to understand cliff stability, any future risk to the road itself and what work would be necessary to protect the road and safely re-open it. Ground investigation works to assess the condition of the cliff have included:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.