26/00002 - Extension for Kent County Council's insurance arrangements

Agreed Executive 3 papers

AI summaryKent County Council's Policy and Resources Cabinet Committee endorsed a two-year extension to the council's insurance programme, running to 31st December 2028, with an estimated value of about £12m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedEndorsed for the Deputy Leader to decide
MoneyAbout £12m extension valueRoughly £6m annual premium, discounted
What happens nextDeputy Leader to make Key DecisionThen delegated to Corporate Director of Finance
Who it affectsCouncil-wide insurance coverAll schools and services funded via Kent Insurance Fund

What was decided

The committee endorsed extending the current insurance arrangements for two years, to 31st December 2028, using PCR 2015 regulation 72. Report 1.2, P10, 6.1

Authority to negotiate, enter and finalise the contract extension was delegated to the Corporate Director of Finance, in consultation with the Deputy Leader. Report P29

Why

A full tender is unlikely to attract competitive prices because of uncertainty caused by Local Government Reorganisation, with implementation expected by April 2028. Report 1.2, P10, 11.1, 11.3

Insurers are expected to charge higher premiums or decline to bid for a short-term arrangement, and the council's broker recommends the extension approach. Report P17, P18, 11.2

Without insurance cover the council would face significant financial loss, so continuity is needed for statutory duties and income-generating activity. Report 1.1, P10

What happens next

The Deputy Leader of Kent County Council will take the Key Decision on the extension. Report P2, P35, P36

The Corporate Director of Finance will negotiate terms, sign contract variations and complete legal agreements to put the extension in place. Report P29

The money

  • approximately £6m Total insurance premium for 2026, funded from the Kent Insurance Fund Report 3.1, 5.1
  • approximately £12m Indicative value of the two-year extension, subject to discounted premiums Report 5.1
  • approximately £25m Value of the current 5-year Long Term Agreement, against which the 50% PCR 2015 regulation 72 cap is assessed Report 6.1
  • £500k Current self-insurance excess across the main policies Report 3.2

Options considered

  • Rejected: Run a full competitive tender for a new insurance programme from 2027. Unlikely to attract competitive bids or competitive pricing because of LGR uncertainty and the likely short contract length Report P10, P17, 11.2, 11.3
  • Chosen: Agree a 2-year extension to the existing 5-year Long Term Agreement under PCR 2015 regulation 72. Recommended by the council's broker; keeps cover in place past expected LGR implementation in April 2028; meets the 50% value test for the regulation Report 1.2, P17, P18, 6.1, 11.4

Implications

  • Financial: Premium savings from the extension are ringfenced within the Kent Insurance Fund and do not affect the council's corporate position or Medium Term Financial Plan. Report 5.1
  • Legal: Extension is taken under PCR 2015 regulation 72, which permits amendment for unforeseen circumstances up to 50% of the original contract value; LGR was not foreseeable when the 2022 agreement was made. Report 6.1
  • Equalities: An Equalities Impact Assessment found no adverse impacts. Report 7.1, P38
  • Risk: Without insurance cover the council would be exposed to significant financial loss, including for claims incurred but not yet reported. Report P10, P9

Who and where

  • Kent County Council services and schools funded through the Kent Insurance Fund Report 1.1, 3.1
  • Risk Management Partners and other insurers in the current Long Term Agreement Report 3.1, 3.3
  • The Deputy Leader and Corporate Director of Finance, who will implement the decision Report P29

Timeline

  • 1st January 2022: Current 5-year insurance Long Term Agreement began Report 6.1
  • 2026: Annual premium of approximately £6m in place Report 3.1, 5.1
  • 31st December 2026: Current insurance programme due to end Report 1.2, P10
  • April 2028: Anticipated Local Government Reorganisation implementation date Report 1.2, 11.1
  • 31st December 2028: End date of the proposed two-year extension Report 1.2, P16

Plain English for the jargon

  • LGR: Local Government Reorganisation: structural changes to local authorities in Kent, expected to be implemented by April 2028.
  • Long Term Agreement: The current 5-year insurance contract Kent County Council holds with a panel of insurers, mainly Risk Management Partners.
  • PCR 2015 regulation 72: A public procurement rule allowing a contract to be modified for unforeseen circumstances, provided the change does not exceed 50% of the original contract value.
  • Kent Insurance Fund: The internal fund, financed by corporate contributions and a school recharge programme, that pays the council's insurance premiums and self-insured losses.
  • Self-insurance excess: The first part of any loss the council retains itself, currently £500k across the main policies, used to control premium costs.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item53

Resolved

RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Extend the Council’s current insurance arrangements for a further two years, through to 31st December 2028. (b) Delegate authority to the Corporate Director of Finance, in consultation with the Deputy Leader of Kent County Council to, take relevant actions, including but not limited to negotiating, entering into and finalising the terms of relevant contracts, contract variations or other legal agreements, as required, to implement the decision.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Policy and Resources Cabinet Committee, 5 pages

Summary

This report seeks endorsement and/or comments on the Key Decision to be taken in relation to the extension for the Council’s insurance programme.

Recommendation(s): The Policy and Resources Cabinet Committee is asked to CONSIDER and ENDORSE or MAKE RECOMMENDATIONS to the Deputy Leader of Kent County Council in relation to the proposed decision as detailed in the attached Proposed Record of Decision document (Appendix A).

1. Introduction

1.1The Council’s insurance programme is extensive and designed to protect its financial position in respect of losses it may suffer when undertaking the diverse nature of activities required to meet statutory duties and general business functions and income generating operations.

1.2The current programme is held under a 5-year Long Term Agreement. This agreement will end on 31st December 2026, and a new programme is due to be tendered for 2027 onwards. Due to the impending changes arising from Local Government Reorganisation (LGR), it is anticipated that a tender would not attract competitive prices and a 2-year extension should be sought. This extension would not alter the nature of the contract and would provide the Council with continued insurance cover through to 31st December 2028 and therefore past the anticipated LGR implementation date (April 2028).

1.3This report outlines the availability of an extension and seeks endorsement for the proposed decision to be taken by the Deputy Leader of Kent County Council.

2. Key Considerations

2.1The main objectives of the Council’s insurance programme are to:

• Provide financial certainty in relation to the Council’s maximum exposure to individual high value claims and overall cost of claims in any one year. • Provide financial certainty for claims that have been incurred but may not be reported for many years in the future. • Comply with the terms and conditions of contracts / agreements entered into by the Council.

It should be noted that in the absence of an appropriate insurance programme, the Council will be a risk of significant financial loss. The Council’s current programme ends on 31st December 2026. In considering future arrangements, an assessment was undertaken to either go out to full tender or agree a 2-year extension. Following the evaluation, the 2-year extension is the proposal being taken forward, as tendering at this point in time would be unlikely to attract competitive pricing due to the uncertainties associated with the Local Government Reorganisation (LGR).

Background

3.1The Council’s current 5-year Long Term Agreement is shared across multiple insurers. The main policies are held with Risk Management Partners (RMP). The agreement requires RMP to provide the Council’s insurance programme via insurers within their portfolio. The total premium for 2026 is approximately £6m. This cost is met from the Kent Insurance Fund which is financed from corporate contributions and a school recharge programme.

3.2The cost of premiums is controlled by the Council retaining the first part of any loss through variable levels of self-insurance. This is currently £500k across the main policies. There will be an opportunity to consider excess levels as part of the extension process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
26/00002: Extension for Kent County Council's insurance arrangementsReport 5 pages DownloadRead as text
PDF
Proposed Record of DecisionAppendix A 2 pages Download
PDF
EQIAAppendix E 4 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 26/00002 - Extension for Kent County Council's insurance arrangementsThis decision
  2. 24/00064 - Contract extension for the receipt and processing of organic waste in south west Kent (including Maidstone green waste) - (GW/2004/01)Decided
  3. 24/00036 - KCHFT (Kent Community Health NHS Foundation Trust) (twelve-month) Partnership ExtensionAgreed
  4. 23/00031 - Extension of Contracts with Locate in Kent and Visit KentAgreed
  5. 22/00102 - Contract Extensions for the Provision of Post-Mortem Facilities for Mid Kent & Medway, North West Kent, and East KentAgreed
  6. SE/22/645 Re-cladding of existing sports hall, demolition of swimming pool building and ancillary building, and erection of single storey replacement sports and changing room facilities extension at Broomhill Bank School (Northern Site), Rowhill Road, Swanley, Kent BR8 7RP (KCC/SE/0036/2022)Approved

More from Kent Policy and Resources Cabinet Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the meeting held on 6 May 2026RESOLVED that the minutes of the meeting held on 6 May 2026 were a correct record and that they be signed by the Chai... Decided Open
2 Jul 2026 Local Outcomes FrameworkRESOLVED that the report be noted. Noted Open
2 Jul 2026 Budget Planning Process 2027-28 and Medium-Term Financial Plan (MTFP) UpdateRESOLVED that the report be noted. Noted Open
2 Jul 2026 26/00032 - Adoption of the KCC Winning for Kent: Procurement with Purpose Policy 2026-2028RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Approve the adoption and implementation of... Approved Open
2 Jul 2026 Work ProgrammeRESOLVED that the work programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies