Kent County Council

Update on Kent and Medway LGR Implementation Preparation

Noted Executive 1 paper

AI summaryKent's LGR Cabinet Committee noted continued joint working by all 14 councils in Kent and Medway ahead of a ministerial decision on reorganisation expected by 16 July 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted joint preparation by all 14 councils
Money£99.4m to £139.1mestimated five year transition costs, model dependent
What happens next16 July 2026expected date of ministerial decision
Who it affectsAll 14 councils in Kent and Medwaycounty, district and borough authorities

What was decided

The Committee noted the continued collaborative working between all 14 councils in Kent and Medway, and the commitment to continue working closely together in anticipation of a ministerial decision.

Why

Five business cases for reorganisation were submitted to government on 28 November 2025, backed by different combinations of the 14 councils, after the then Minister invited proposals in February 2025. Report 1.1, 1.3

A statutory seven week consultation opened on 5 February 2026 and closes at 23:59 on 26 March 2026, with early indications of a high response rate relative to other areas. Report 3.1, 3.5

What happens next

Work continues on the Enhanced Discovery Phase, covering 11 Priority Activity Groups, alongside promotion of the consultation, liaison with civil servants, and a Memorandum of Understanding on cost apportionment. Report 4.2, 6.4, 7.1

A Programme Director is to be recruited before the ministerial decision, and Kent County Council is asked to act as lead procurement authority for a new Strategic Business Partner. Report 6.6, 6.7

The money

  • £99.4m and £139.1m estimated range of transition costs over five years depending on which model is chosen Report 6.1
  • £11.9m estimated costs before vesting day, partly in 2026-27 and the remainder in 2027-28, to be met by existing legacy councils Report 6.3
  • £514,410 MHCLG funding received in 2025, placed within the KCC Strategic Partnerships Team budget Report 6.5
  • £319,550 unspent balance of the 2025 MHCLG funding carried forward to the next phase Report 6.5
  • £63m additional national funding announced on 16 February 2026 for the next phase of reorganisation Report 6.6
  • £4-4.5m expected share for Kent and Medway of the new national funding, based on previous allocations Report 6.6

Options considered

  • Supported by Kent County Council: Business Case 1A: a single unitary council covering Kent and Medway with three area assemblies. KCC's preferred model Report P4, 1.3
  • Supported by five district and borough councils: Business Case 3A: three unitary councils covering north, west and east Kent Report P5, P6, 1.3
  • Supported by three district councils: Business Case 4B: four unitary councils within existing boundaries Report P7, P8, 1.3
  • Supported by Medway, Ashford and Canterbury councils: Business Case 4D: four unitary councils with boundary changes Report P9, P10, 1.3
  • Supported by Dartford and Gravesham councils: Business Case 5A: five unitary councils with boundary changes Report P11, P12, 1.3

Implications

  • Financial: Transition costs of £99.4m to £139.1m will fall over five years, with £11.9m of costs before vesting day to be met by existing councils under an apportionment set out in a forthcoming Memorandum of Understanding. Report 6.1, 6.3, 6.4
  • Staffing: The Enhanced Discovery Phase draws on existing staff across the 14 councils, with each Priority Activity Group led by a Chief Executive and a Project Officer from a different authority; a new Programme Director is to be recruited. Report 4.4, 4.5, 6.7
  • Risk: Chief Executives will run collective 'what if' scenario planning and agree joint responses so that Kent and Medway are prepared for different outcomes before ministers decide. Report 4.7
  • Legal: Final decisions on reorganisation rest with ministers, who may implement any of the submitted proposals with or without modification; formal decision making remains the responsibility of each sovereign council. Report 1.5, 5.1

Who and where

  • All 14 councils in Kent and Medway Report 1.2, 1.3
  • Residents, businesses, town and parish councils and the voluntary sector in Kent and Medway Report 3.2
  • Council staff, particularly in back office functions, given the data and information consolidation underway Report 4.3, 4.4

Timeline

  • 5 February 2026: HM Government launched the statutory seven week consultation on reorganisation Report 3.1
  • 26 March 2026: Statutory consultation closes at 23:59 Report 3.5
  • 16 July 2026: Ministerial decision on reorganisation expected Report 1.5
  • 2026/27: Costs before vesting day begin to be incurred; no additional KCC resource expected this year Report 6.3, 6.8
  • 2027/28: Remainder of pre vesting day costs incurred, with potential budget pressure if no further government funding Report 6.3, 6.8
  • 2028/29: Disaggregation and aggregation costs begin after vesting day and the transition to new unitary councils Report 6.2

Plain English for the jargon

  • LGR: Local government reorganisation, the restructuring of councils
  • MHCLG: Ministry of Housing, Communities and Local Government
  • SCO: Structural Changes Order, the legal instrument that creates new councils
  • Vesting day: The date on which new unitary councils come into legal existence
  • Shadow authority: A new council existing in the period before vesting day alongside legacy councils
  • Pre vesting day costs: Costs of preparing new councils before they legally exist, met by existing legacy councils
  • Apportionment: Method for sharing pre implementation costs between the 14 councils, based on taxbase and population
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24

Resolved

RESOLVED that the Committee noted the continued collaborative working between all 14 councils in Kent and Medway, and the commitment to continue working closely together in anticipation of a ministerial decision.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Devolution and Local Government Re-organisation Cabinet Committee, 12 pages

Background

1.1In February 2025 the then Minister for Local Government invited Councils in Kent and Medway to submit proposals for local government reorganisation (LGR). After submitting a joint interim proposal in March 2025, Leaders were given a deadline of 28 November 2025 to submit final business cases on reorganisation.

1.2Unlike other areas of the country, all 14 Councils in Kent & Medway were able to work together throughout the process collaboratively and collectively, utilising a single Strategic Business Partner, options appraisal, evidence base, financial analysis, communications, and programme governance, ensuring the work was as efficient and as joined up as possible, as directed by HM Government.

1.3Leaders in Kent and Medway ultimately submitted 5 business cases on 28 November 2025 as follows:

Business Case 1A A proposal for a single unitary council covering Kent and Medway to include three area assemblies covering the north, east and west of the county. Business Case 1A is supported by Kent County Council.

Business Case 3A A 3 unitary option consisting of Dartford, Gravesham, Medway and Swale in the North Kent; Sevenoaks, Tonbridge & Malling, Maidstone Tunbridge Wells in West Kent, Ashford, Canterbury, Thanet, Dover, Folkestone & Hythe in East Kent.

Business Case 3A is supported by Folkestone & Hythe District Council, Maidstone Borough Council, Sevenoaks District Council, Tonbridge & Malling Borough Council and Tunbridge Wells Borough Council

Business Case 4B A 4 unitary option consisting of Dartford, Gravesham and Medway in North Kent; Sevenoaks, Tonbridge & Malling, Maidstone and Tunbridge Wells in West Kent; Swale, Ashford and Folkestone & Hythe in Mid Kent and Canterbury, Thanet and Dover in East Kent.

Business Case 4B is supported by Dover District Council, Swale Borough Council and Thanet District Council

Business Case 4D A 4 unitary option with boundary changes consisting of most of Medway, Gravesham, Dartford, Swale, and small parts of Tonbridge & Malling and Maidstone in North Kent. Canterbury, Thanet, Dover, eastern Swale and part of Folkestone & Hythe in East Kent, Tunbridge Wells, Tonbridge & Malling and Sevenoaks in West Kent, and Maidstone, Ashford, southern Swale, parts of Tonbridge & Malling and part of Folkestone & Hythe in Mid Kent.

Business Case 4D is supported by Medway Council, Ashford Borough Council and Canterbury City Council

Business Case 5A A 5 unitary option with boundary changes consisting of Gravesham, Dartford and Swanley and parts of Medway in North Kent, Tonbridge & Malling, Maidstone, Tunbridge Wells and the remainder of Sevenoaks in West Kent, Ashford, Folkestone & Hythe and Dover in South Kent, Faversham, Canterbury and Thanet in East Kent, and the remainder of Medway and Swale in Mid Kent.

Business Case 5A is supported by Dartford Borough Council and Gravesham Borough Council.

1.4A map of each of the business case geographies can be found in Appendix 1 and the full business cases can be viewed on the Kent Council Leaders website.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on Kent and Medway LGR Implementation PreparationReport 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Update on Kent and Medway LGR Implementation PreparationThis decision
  2. 26/00028 Procurement of a Strategic Partner for Kent and Medway LGR ProgrammeDecided
  3. Kent & Medway Domestic Abuse StrategyNoted
  4. Annual Report of the Kent and Medway Police and Crime PanelApproved
  5. Kent and Medway Community Services Transformation and Neighbourhood HealthNoted
  6. Proposed Integration between the Kent Community Health NHS Foundation Trust and Medway Community HealthcareDecided

More from Kent Devolution and Local Government Re-organisation Cabinet Committee

All decisions
MeetingDecisionOutcome
14 May 2026 Minutes of the meeting held on 23.3.2026RESOLVED that the minutes of the meeting held on 23 March 2026 be approved and signed as a correct record. Approved Open
14 May 2026 Update on Service Complexity Assessments (KCC internal preparation for LGR)RESOLVED that the Committee note the progress and next steps in delivering the Service Complexity Assessment process. Noted Open
14 May 2026 26/00028 Procurement of a Strategic Partner for Kent and Medway LGR ProgrammeRESOLVED that, the Committee endorse the proposed approach and support the recommendations to the Leader as set out i... Decided Open
14 May 2026 Work ProgrammeRESOLVED to note the work programme. Noted Open
23 Mar 2026 Minutes of the meeting held on 3.11.2025RESOLVED that the minutes of the meeting held on 3 November 2025 be approved and signed as a correct record. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies