Policy and Resources Cabinet Committee, Wednesday 6 May 2026 at 10.00am

26/00027 - Infrastructure Condition Survey Programme

Agreed Executive 3 papers

AI summaryKent County Council's Policy and Resources Cabinet Committee endorsed plans to restart a condition survey programme for its corporate and school property estate from Q3 2026, with contract award powers delegated to the Director of Infrastructure.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSurvey of education and corporate estate, contracts by Director of Infrastructure
MoneyNot stated
What happens nextProgramme starts Q3 2026Multiple consultants, reassessed every 3 years
Who it affectsCorporate and maintained school estatesSplit roughly 1/3 corporate, 2/3 education

What was decided

The Committee endorsed establishing a condition survey programme to assess the current state of the Council's education and corporate property estate and inform future decisions. Report 2.1

Authority was endorsed to be delegated to the Director of Infrastructure to award contracts and take other legal actions needed to deliver the programme within approved budgets. Report 12.1

The programme will be reviewed every 3 years or sooner if Local Government Reorganisation changes how the estate is managed. Report 7.2

Why

The last condition surveys were completed about 5 years ago, so existing data no longer provides a reliable basis for decisions about repairs, capital spend or school funding returns to the Department for Education. Report 4.1, 7.6

Around 44 per cent of the estimated spend needed to keep the corporate estate in good condition has been funded over the last five years, leaving a shortfall of about £46 million and growing backlog maintenance. Report 3.3, 3.4, 3.5

Up to date condition data is needed to manage the estate ahead of Local Government Reorganisation, when assets are likely to transfer to new councils, and to meet the Council's Warm Safe and Dry maintenance standard. Report 3.1, 5.2, 5.3, 11.1

What happens next

Officers will commission multiple contractors through Procurement Act 2023 and Public Contract Regulations compliant frameworks, starting in Q3 2026, with a clear specification so results are comparable. Report 4.2, 4.4, 4.6

The specification will integrate with the Council's new asset management system so contractors can input data directly, reducing double handling and upload errors. Report 2.6, 4.5

The Director of Infrastructure, in consultation with the Deputy Leader, will award contracts within approved financial limits, and key outcomes and risks will be reported through member briefings and future committee papers. Report 12.1, 12.2

The money

  • £5,441,564.13 Modernisation of Assets outturn 2021/22 Report P12
  • £11,375,268.92 Modernisation of Assets outturn 2022/23 Report P12
  • £3,338,256.99 Modernisation of Assets outturn 2023/24 Report P12
  • £5,757,653.39 Modernisation of Assets outturn 2024/25 Report P12
  • c£10.9m Modernisation of Assets forecast 2025/26, subject to final accounts Report P12
  • c£36,812,740.39 Total Modernisation of Assets spend 2021/22 to 2025/26 forecast Report P12
  • c.£165m Total 10 year corporate condition spend requirement based on 2021/22 information Report 3.3
  • c.£16.5m pa Estimated annual spend needed to return corporate estate to good and serviceable condition Report 3.3
  • c£197m 2021/22 £165m projection inflated by BCIS to Q1 2026 prices Report 3.3
  • c.44% Proportion of the required condition spend actually spent over the last five years Report 3.4
  • c.£46m Estimated shortfall in condition spending over the last five years Report 3.4
  • £750k Annual revenue budget for condition surveys in education Report 7.1
  • £400k Annual revenue budget for condition surveys in corporate estate Report 7.1

Options considered

  • Rejected: Do nothing or delay surveys until Local Government Reorganisation is confirmed. Would increase risk of unplanned building failure, reactive capital spending, service disruption and non compliance with Department for Education requirements Report 6.1
  • Rejected: Ad hoc commissioning or single supplier tender. Would risk inconsistent data, extra admin burden, and a single supplier lacks capacity for the size and geographic spread of the estate Report 6.2
  • Chosen: Procure via multiple consultants through Procurement Act 2023 and Public Contract Regulations compliant frameworks. Gives a compliant route to market, consistent specification and data comparability, value for money, and ability to deliver at pace Report 4.6, 4.9

Implications

  • Financial: Annual revenue cost is covered within existing budgets, but the programme supports more targeted capital spending and reduces reliance on costly reactive and emergency works. Report 7.1, 7.4, 7.5
  • Legal: Contracts will be awarded through a Procurement Act 2023 and Public Contract Regulations compliant route, in line with the Council's spending policy, with legal support from Legal Services. Report 8.1
  • Equalities: An Equalities Impact Assessment found no direct equalities implications, with the assessment to be updated as the project progresses. Report 9.1
  • Risk: Lack of up to date condition data increases the risk of unplanned building closures, health and safety issues, and poor targeting of capital budgets over the next two years before Local Government Reorganisation. Report 5.2, 6.1, 11.2
  • Other: Up to date condition data is needed for the Department for Education funding returns and to inform any future asset transfers under Local Government Reorganisation. Report 5.3, 7.6, 11.3

Who and where

  • Kent County Council's corporate property estate and its users Report 2.1, 11.1
  • Maintained schools across Kent Report 2.1, 4.2, 11.2
  • Department for Education, as recipient of condition data returns Report 7.6, 11.3
  • Future unitary councils taking on assets under Local Government Reorganisation Report 5.3
  • Survey contractors appointed through framework agreements Report 4.6

Timeline

  • 2021/22 to 2025/26: Period covered by the Modernisation of Assets spend figures Report P12, 3.2
  • Q1 2026 prices: Date to which the £165m 2021/22 backlog estimate has been inflated by BCIS Report 3.3
  • Q3 2026: Planned start of the new condition survey programme Report 4.2
  • 2026-05-06: Date of the Policy and Resources Cabinet Committee meeting endorsing the proposed decision Report P61
  • July 2026: Anticipated timing of the Secretary of State's decision on Local Government Reorganisation at the time of the report Report 5.1
  • April 2028: Anticipated date by which the Council in its current form is expected to continue to exist Report 5.2
  • Every 3 years: Frequency at which the condition survey programme will be revisited Report 7.2

Plain English for the jargon

  • BCIS: Building Cost Information Service, a construction cost index used to update price estimates over time.
  • Warm Safe and Dry: Kent County Council's adopted approach of investing only in safety critical and compliance related works to keep buildings operational, rather than full backlog maintenance.
  • MOA: Modernisation of Assets, the Council's adopted capital budget for periodic enhancement of the corporate estate.
  • DFE: Department for Education, which requires condition data returns from councils responsible for maintained schools.
  • PCR: Public Contract Regulations, the procurement rules that compliant tender routes must follow.
  • PA23: Procurement Act 2023, the new procurement regime referenced for compliant routes to market.
  • LGR: Local Government Reorganisation, the planned restructuring of councils in Kent.
  • EqIA: Equalities Impact Assessment, a formal check on the equalities effects of a decision.
  • DPIA: Data Protection Implication Assessment, a screen for data protection risks.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item63

Resolved

RESOLVED that the Cabinet Committee endorses the proposed decision to: 1) The establishment of a condition survey programme to ascertain the current condition status of property assets within the Council’s education and corporate estate and inform future decision taking; and 2) Delegate authority to the Director of Infrastructure, to take necessary actions, including but not limited to, entering into contracts and other legal agreements as required to deliver the programme in line with approved budgets.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Policy and Resources Cabinet Committee, 9 pages

Background

2.1Due to the volume of surveys required the Council commissions surveys via suitable qualified contractors. In addition to the corporate estate the Council is responsible for large numbers of schools across the County which are also managed by Infrastructure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
26/00027: Infrastructure Condition Survey ProgrammeReport 9 pages DownloadRead as text
PDF
Proposed Record of DecisionAppendix A 3 pages Download
PDF
EQIAAppendix B 4 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 26/00027 - Infrastructure Condition Survey ProgrammeThis decision
  2. Proposal 18/504729/COUNTY (KCC/MA/0457/2018) - Section 73 application to vary Conditions 2 (approved plans), 3 (external materials) and 7 (access and parking) of Permission MA/16/507143 at The Lenham School , Ham Lane, Lenham; KCC Infrastructure DivisionApproved
  3. Proposal TW/17/3344 (KCC/TW/0271/2017) - Section 73 application to vary Condition 15 of Permission TW/12/1442 relating to traffic calming measures for the new Benenden Primary School at Land south of Rolvenden Road, Benenden; KCC Property and Infrastructure SupportDecided
  4. Proposal TW/12/1442 R14 - Code of Construction Practice pursuant to Condition 14 of Permission TW/12/1442 for the new Benenden Primary School at Land south of Rolvenden Road, Benenden; KCC Property and Infrastructure SupportApproved
  5. Proposal SW/14/1543/R3 and R4 - Details pursuant to Condition 3 (external materials) and 4 (external lighting) at Tunstall CE Primary School, Tunstall Road, Tunstall; KCC Property and Infrastructure ServicesApproved

More from Kent Policy and Resources Cabinet Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the meeting held on 6 May 2026RESOLVED that the minutes of the meeting held on 6 May 2026 were a correct record and that they be signed by the Chai... Decided Open
2 Jul 2026 Local Outcomes FrameworkRESOLVED that the report be noted. Noted Open
2 Jul 2026 Budget Planning Process 2027-28 and Medium-Term Financial Plan (MTFP) UpdateRESOLVED that the report be noted. Noted Open
2 Jul 2026 26/00032 - Adoption of the KCC Winning for Kent: Procurement with Purpose Policy 2026-2028RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Approve the adoption and implementation of... Approved Open
2 Jul 2026 Work ProgrammeRESOLVED that the work programme be noted. Noted Open