What was decided
The Committee endorsed establishing a condition survey programme to assess the current state of the Council's education and corporate property estate and inform future decisions. Report 2.1
Authority was endorsed to be delegated to the Director of Infrastructure to award contracts and take other legal actions needed to deliver the programme within approved budgets. Report 12.1
The programme will be reviewed every 3 years or sooner if Local Government Reorganisation changes how the estate is managed. Report 7.2
Why
The last condition surveys were completed about 5 years ago, so existing data no longer provides a reliable basis for decisions about repairs, capital spend or school funding returns to the Department for Education. Report 4.1, 7.6
Around 44 per cent of the estimated spend needed to keep the corporate estate in good condition has been funded over the last five years, leaving a shortfall of about £46 million and growing backlog maintenance. Report 3.3, 3.4, 3.5
Up to date condition data is needed to manage the estate ahead of Local Government Reorganisation, when assets are likely to transfer to new councils, and to meet the Council's Warm Safe and Dry maintenance standard. Report 3.1, 5.2, 5.3, 11.1
What happens next
Officers will commission multiple contractors through Procurement Act 2023 and Public Contract Regulations compliant frameworks, starting in Q3 2026, with a clear specification so results are comparable. Report 4.2, 4.4, 4.6
The specification will integrate with the Council's new asset management system so contractors can input data directly, reducing double handling and upload errors. Report 2.6, 4.5
The Director of Infrastructure, in consultation with the Deputy Leader, will award contracts within approved financial limits, and key outcomes and risks will be reported through member briefings and future committee papers. Report 12.1, 12.2
The money
- £5,441,564.13 Modernisation of Assets outturn 2021/22 Report P12
- £11,375,268.92 Modernisation of Assets outturn 2022/23 Report P12
- £3,338,256.99 Modernisation of Assets outturn 2023/24 Report P12
- £5,757,653.39 Modernisation of Assets outturn 2024/25 Report P12
- c£10.9m Modernisation of Assets forecast 2025/26, subject to final accounts Report P12
- c£36,812,740.39 Total Modernisation of Assets spend 2021/22 to 2025/26 forecast Report P12
- c.£165m Total 10 year corporate condition spend requirement based on 2021/22 information Report 3.3
- c.£16.5m pa Estimated annual spend needed to return corporate estate to good and serviceable condition Report 3.3
- c£197m 2021/22 £165m projection inflated by BCIS to Q1 2026 prices Report 3.3
- c.44% Proportion of the required condition spend actually spent over the last five years Report 3.4
- c.£46m Estimated shortfall in condition spending over the last five years Report 3.4
- £750k Annual revenue budget for condition surveys in education Report 7.1
- £400k Annual revenue budget for condition surveys in corporate estate Report 7.1
Options considered
- Rejected: Do nothing or delay surveys until Local Government Reorganisation is confirmed. Would increase risk of unplanned building failure, reactive capital spending, service disruption and non compliance with Department for Education requirements Report 6.1
- Rejected: Ad hoc commissioning or single supplier tender. Would risk inconsistent data, extra admin burden, and a single supplier lacks capacity for the size and geographic spread of the estate Report 6.2
- Chosen: Procure via multiple consultants through Procurement Act 2023 and Public Contract Regulations compliant frameworks. Gives a compliant route to market, consistent specification and data comparability, value for money, and ability to deliver at pace Report 4.6, 4.9
Implications
- Financial: Annual revenue cost is covered within existing budgets, but the programme supports more targeted capital spending and reduces reliance on costly reactive and emergency works. Report 7.1, 7.4, 7.5
- Legal: Contracts will be awarded through a Procurement Act 2023 and Public Contract Regulations compliant route, in line with the Council's spending policy, with legal support from Legal Services. Report 8.1
- Equalities: An Equalities Impact Assessment found no direct equalities implications, with the assessment to be updated as the project progresses. Report 9.1
- Risk: Lack of up to date condition data increases the risk of unplanned building closures, health and safety issues, and poor targeting of capital budgets over the next two years before Local Government Reorganisation. Report 5.2, 6.1, 11.2
- Other: Up to date condition data is needed for the Department for Education funding returns and to inform any future asset transfers under Local Government Reorganisation. Report 5.3, 7.6, 11.3
Who and where
- Kent County Council's corporate property estate and its users Report 2.1, 11.1
- Maintained schools across Kent Report 2.1, 4.2, 11.2
- Department for Education, as recipient of condition data returns Report 7.6, 11.3
- Future unitary councils taking on assets under Local Government Reorganisation Report 5.3
- Survey contractors appointed through framework agreements Report 4.6
Timeline
- 2021/22 to 2025/26: Period covered by the Modernisation of Assets spend figures Report P12, 3.2
- Q1 2026 prices: Date to which the £165m 2021/22 backlog estimate has been inflated by BCIS Report 3.3
- Q3 2026: Planned start of the new condition survey programme Report 4.2
- 2026-05-06: Date of the Policy and Resources Cabinet Committee meeting endorsing the proposed decision Report P61
- July 2026: Anticipated timing of the Secretary of State's decision on Local Government Reorganisation at the time of the report Report 5.1
- April 2028: Anticipated date by which the Council in its current form is expected to continue to exist Report 5.2
- Every 3 years: Frequency at which the condition survey programme will be revisited Report 7.2
Plain English for the jargon
- BCIS: Building Cost Information Service, a construction cost index used to update price estimates over time.
- Warm Safe and Dry: Kent County Council's adopted approach of investing only in safety critical and compliance related works to keep buildings operational, rather than full backlog maintenance.
- MOA: Modernisation of Assets, the Council's adopted capital budget for periodic enhancement of the corporate estate.
- DFE: Department for Education, which requires condition data returns from councils responsible for maintained schools.
- PCR: Public Contract Regulations, the procurement rules that compliant tender routes must follow.
- PA23: Procurement Act 2023, the new procurement regime referenced for compliant routes to market.
- LGR: Local Government Reorganisation, the planned restructuring of councils in Kent.
- EqIA: Equalities Impact Assessment, a formal check on the equalities effects of a decision.
- DPIA: Data Protection Implication Assessment, a screen for data protection risks.