the Panel support the recommendations to Cabinet as set out below: 1) Cabinet recommends to Council the amendments to capital schemes and resources for the 2015-2020 Capital Programme as detailed in the report. 2) Cabinet recommends to Council that new capital bids are to be funded from available capital resources and included in the capital programme 2016-2020 as detailed in the report.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
Open Would any decisions proposed : Any Mandatory especially (a) Be entirely within Cabinet’s powers to decide NO affected (b) Need to be recommendations to Council YES Wards None (c) Be partly for recommendations to Council NO and partly within Cabinets powers – Lead Member: Councillor Nick Other Cabinet Members consulted: Daubney Other Members consulted: E-mail:cllr.nick.daubney@west- norfolk.gov.uk Lead Officer: Lorraine Gore Other Officers consulted: Management Team, E-mail: lorraine.gore@west- Service Managers norfolk.gov.uk Direct Dial: Financial Policy/Personnel Statutory Equal Risk Implications Implications Implications Opportunities Management YES YES (incl S.17) Implications Implications NO NO YES
Date of meeting: 2 February 2016
CAPITAL PROGRAMME AND RESOURCES 2015-2020
Summary This report:
revises the 2015/2016 projections for spending on the capital programme sets out an estimate of capital resources that will be available for 2015-2020 details new capital bids that are recommended to be included in the capital programme for the period 2016-2020 outlines provisional figures for capital expenditure for the period 2015-2020
Recommendations It is recommended that:
1) Cabinet recommends to Council the amendments to capital schemes and resources for the 2015-2020 capital programme as detailed in the report.
2) Cabinet recommends to Council that new capital bids are to be funded from available capital resources and included in the capital programme 2016-2020 as detailed in the report.
Reason for Decision To report amendments, rephasing and resources to the 2015-2020 Capital Programme 1. Introduction
1.1This report presents the capital programme for the period 2015 to 2020. The capital programme forms part of the Council’s longer term Financial Plan, and is updated as part of the overall budget and council tax setting process.
1.2The current economic conditions continue to create a challenging environment for achieving capital receipts to support the funding of the Council’s capital programme. At the same time the Council aims to deliver a number of major projects within limited resources.
1.3The Council is faced with a situation where capital resources to fund the capital programme continue to be limited.
1.4This report sets out a programme for 2015/2020 that can be delivered if predicted land sales come about. Certain capital funds come from grants, VAT shelter receipts and use of reserves but a large part of funds are to come from land sales. These sums included in 2015/2020 are anticipated receipts from identified sites, phases I and 2 of the Housing Joint Venture on the NORA site and the Major Housing Development. The continuation of the Housing Joint Venture to develop phase 3 of the site are not included in the programme 2015-2020 at this stage.
1.5The capital programme 2015-2020 includes a number of major projects, including the Major Housing Development which will deliver 447 new homes in King’s Lynn. The delivery of new homes through this project provides essential funding to support the revenue budget, both through new homes bonus and increases to the council tax base.
1.6Reports being considered by Panel and Cabinet in January 2016 present additional major projects for consideration. Further major projects are being developed and will be subject to separate reports to future Panel and Cabinet meetings. The capital programme 2015/2020 will need to be amended accordingly if these major projects are approved.
1.7Detailed arrangements with the New Anglia LEP for the delivery of the infrastructure works on the NORA Enterprise Zone to facilitate growth of new businesses will be subject to a separate report to Cabinet. These works will be funded from the business rates generated and be administered by the Council. The capital programme will need to be amended accordingly.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Resources and Performance Panel at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
Cabinet Report: Staff Pay AwardThat the Panel supported the recommendation to Cabinet as set out below: 1. That an annual pay award of 1% be impleme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.