Resolved
The update was noted.
Regeneration and Development Panel noted this item on Wednesday 24 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
The update was noted.
Quentin Brogdale
Resident Engineer Norfolk County Council
24 February 2016 Norfolk County Council Community and Environmental Services Department Highways and Transport Group • Highway Maintenance • Network Management • Capital Schemes • Passenger Transport • Developer Services • Travel Systems Surfacing Programme Planned works 2015-16:
• A10 Ryston • Downham Market – Railway Road Traffic Signal Upgrades Recent schemes completed: • Gaywood Road/Tennyson Avenue • London Road/Hospital Walk
Planned works: • John Kennedy Road/Austin Street • Gaywood Road/Loke Road Projects Recent schemes led by BCKLWN with support from NCC: • King’s Lynn Transport Interchange • Saturday Market Place
Planned scheme: • Lynnsport Access Road West Area Office • 14 Technical Staff • 136 Parishes
• 4 Construction Staff • 2500 km of highway
• 3 Support Staff • 151,627 Hectares
• Streetworks Department • Area Population 221 300
• Countryside Team • Maintenance budget of £4.3 m • 23 Roadworker Gangs Works Carried out by the depot • Routine Maintenance
• Structural Maintenance
• Improvement Schemes
• Winter Services
• Highway and Community Ranger Work
• 24 hr Emergency Response What do we do? • Maintain the highway in accordance with NCC’s Transport Asset Management Plan • Scheduled Highway Inspections and Defect Identification • Identify & Prioritise Structural Maintenance Schemes (footway refurbishment, new drainage, surfacing, & road strengthening schemes) • Public Interface for Highways Group • Identify/Order/Check/Approve/Pay • Design of Minor Maintenance Schemes • Audit and Estate Road Inspections • Surface Dressing Supervision • Winter Service Decisions and Operation Identifying Maintenance Works
• Scheduled Highway Inspections
• First line response for Traffic Management Requests
• Borough, Town & Parish Council liaison
• Respond to Customer Service Requests Works carried out with term contractor Tarmac • Surface Patching
• Rural Highway Verge Grass cutting
• Weed Spraying
• Scheduled Road Drain Cleansing
• Surface Dressing
• Inspection and Maintenance of Safety Barriers
• Design & Delivery of some highway schemes Winter Services Winter Services • 2014/15: 70 Gritting actions on main routes – approx. 14,000t salt
• An average gritting route takes three hours to complete. We have 53 routes across the County and each time we grit we treat over 1910 miles of the County's 5965 mile network.
• Each normal gritting run costs £48,500, cost per mile = £23
• Highways England treats a further 143 miles of trunk roads – A11, A12 and A47. Norwich City Council is responsible for roads in the Norwich area with NCC acting as agent
• Long-term PFI arrangement with Salt Union ends 2020. This has guaranteed salt supplies since 1995 and avoided pollution problems by using domes Winter Services • We receive detailed weather forecasts each day predicting the timing and the possible formation of ice
• County Controller reviews forecast daily to decide if treatment is required Shouts Last night:
• P1&P2 10g @ 19:00 all zones except coastal north @ 20:00 (Crews hold if rain) • P1 & P2 10g @ 03:30 AM all zones except City
Tonight:
• PM – P1 & P2 10g @ 18:00 all County Zones, P1 & P2 7.5g @ 19:00 AM – P1 & P2 10g @ 03:00 all County Zones, No Action in the City. Highway Ranger Initiative • Greater community input
• More responsive to local priorities and streetscene needs
• Scheduled visits, notified in advanced
• Rangers more empowered to spot and fix
• More flexible working methods
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways WorksReport | 440 KB | DownloadRead as text |
Follow Regeneration and Development Panel at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Sep 2026 | RD26The minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 30 Sep 2026 | RD32The Panel’s Work Programme and the Forward Decisions List were noted. | Noted | Open |
| 30 Sep 2026 | RD34That under Section 100(A)(4) of the Local Government Act, 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 30 Sep 2026 | RD35That the Regeneration and Development Panel support the recommendations to Cabinet as included in the agenda. | Decided | Open |
| 22 Jul 2026 | RD14The minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.