Cabinet, Tuesday 1 March 2016 at 5.30pm

CREMATORIUM PROJECT UPDATE

Approved Executive 1 paper

Cabinet approved this item on Tuesday 1 March 2016. Below is the council's own wording, with the papers it was decided on.

ItemCAB141

Resolved

1 ) That the outturn figure as shown is section 5.1 of the report be approved. 2) That the works outlined in section 4 of the report in relation to both the bat mitigation and the cost of replacing the roof be approved. Reason for Decision To ensure that the Crematorium roof is good for another 35 years and to reduce the impact the resident bats have on the service provision. 1 ) That the outturn figure as shown is section 5.1 of the report be approved. 2) That the works outlined in section 4 of the report in relation to both the bat mitigation and the cost of replacing the roof be approved.
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Cabinet

Summary

The following report updates members on progress on the Crematorium project which included

Recommendation 1 – Approve the outturn figure as shown is section 5.1 of this report.

2 – To Approve the works outlined in section 4 of this report in relation to both the bat mitigation and the cost of replacing the roof

Reason for decision

To ensure that the Crematorium roof is good for another 35 years and to reduce the impact the resident bats have on the service provision.

Background

1.1On the 9th April 2013 Cabinet authorised officers to procure:-

i. a new cremator hall,

ii. three new cremators each with single stream inline abatement equipment,

iii. the stripping out of the old cremators, iv. the conversion of the old cremator hall into office space, meeting rooms and a staff changing room with showering facilities and,

v. the introduction of cost effective energy efficient/environmentally friendly options of heating and cooling the building.

1.2In September 2014 Members were updated on the progress made on:-

i. The Phase 1 enabling works (new car park and footpaths) which were completed and on budget.

ii. The Phase 2 works (new cremator hall and associated works) being carried out by EN Suiter & Sons Ltd (ENS) who had been appointed as contractors for this phase.

iii. The new cremators which were being built offsite by Facultatieve Technologies (FT).

iv. Arrangement for some of the admin posts that were to be transferred to King’s Court to allow for the necessary changes within the existing building to progress.

2 Update on Progress

2.1The new cremation equipment, which was built offsite was installed by FT became operational on 2nd April 2015. The old cremators were then removed to allow the final phase of work (Office refurbishment) to go ahead.

2.2All Admin posts returned to the new office space at Mintlyn on 20 July 2015.

2.3During the project officers were asked to see if improvements could be made to the Air Cooling system in the chapel. The Improved air cooling system for the chapel is now completed and ready for this summer.

2.4Practical completion of the Phase 2 works was achieved on 22nd June 2015, with most of the snagging items resolved at the time of this report.

2.5As part of the works all the remaining asbestos ceilings within the arears worked were removed. The last two small rooms with asbestos ceilings (bearers rest room and the public toilets) will also have the asbestos removed within the next 2 months. Once these works are complete with the exception of the tiles on the old part of the building will be asbestos free.

3 Bat Mitigation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CREMATORIUM PROJECT UPDATEReport 121 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
GA
Gordon AdamOfficer, expected
CB
Chris BamfieldOfficer, expected
KB
Kate BlakemoreOfficer, expected
RB
Councillor Richard BluntCommittee Member, present
ND
Councillor Nicholas DaubneyChair, apologies
DG
Debbie GatesOfficer, expected
LG
Lorraine GoreOfficer, expected
GH
Geoff HallOfficer, expected
RH
Ray HardingOfficer, expected
LH
Councillor Lord HowardCommittee Member, present
AL
Councillor Adrian LawrenceCommittee Member, present
BL
Councillor Brian LongCommittee Member, present

All 17 on the meeting page

More from King's Lynn and West Norfolk Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 ApologiesAn apology for absence was received from Councillor Moriarty. Decided Open
17 Nov 2026 MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... Agreed Open
17 Nov 2026 Urgent businessNone. Decided Open
17 Nov 2026 Declarations of interestNone. Decided Open
17 Nov 2026 Chair's correspondenceNone. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies