Resolved
RECOMMENDED : That the signing of contracts and start of works for NORA Phase 3 be authorised. Reason for Decision To allow the development on Nar Valley Park (NORA) to be completed
Cabinet decided this item on Wednesday 7 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RECOMMENDED : That the signing of contracts and start of works for NORA Phase 3 be authorised. Reason for Decision To allow the development on Nar Valley Park (NORA) to be completed
This report updates Members on progress made on the NORA Housing project and requests Members to agree to give delegated authority to the Chief Executive and the Chief financial officer in consultation with the Portfolio Holder for Regeneration, to authorise the signing of contracts to enable the start of works for Phase 3.
To authorise the signing of contracts and start of works for Phase 3.
To allow the development on Nar Valley Park (NORA) to be completed.
1.1The Borough Council of King’s Lynn and West Norfolk has led the redevelopment of the Nar Ouse Regeneration Area (NORA) since its inception in 1998. NORA aims to deliver the comprehensive regeneration of an area of around 53 hectares of underused and derelict land extending from Boal Street to the A47 adjacent to South Lynn. The Council has worked in partnership with the East of England Development Agency (EEDA), English Partnerships (now the Homes and Communities Agency), Norfolk County Council and developers Morston Assets to deliver the NORA Millennium Community on the southern site since 2002. Throughout the programme, community stakeholders have been actively engaged in the development of detailed plans through the NORA Consultative Group.
1.2An agreement with Norfolk County Council (NCC) to create a contractual Joint Venture to deliver the first phase of residential units on the Council’s land at NORA was approved by Cabinet on 3rd April 2010 and signed with the NCC on 8 October 2012. This approach gave access to NCC capital funding and housing related specialist expertise and staffing capacity.
1.3Following a tendering process, contract negotiation took place with Morgan Sindall. Once the full price for the scheme was calculated together with their prelims, it became apparent that they were not the lowest tender. As a result contract negotiations then took place with Carter Builders whose tender proved to be the best value on offer under the procurement. Carters started on site on February 2013.
2. How the Project has Progressed
2.1It was always known that due to the previous uses and the location of the site that this project would be difficult to deliver and during the first two phases the Council has had to deal with the following major issues.
(i) Condition of existing pumped foul sewer (ii) Ground level and surcharging requirements (iii) Ground water issues (iv) Residual contamination (v) Deep excavations to allow surface water drainage and sewer connections.
2.2All these issues have related to ground conditions and as all site servicing has been completed as part of the phase 1 and phase 2 contracts further risk in the ground for phase 3 is greatly reduced.
3. Works Carried out in Advance of this Phases
3.1Due to the nature of the project and to gain best value, certain works have been carried out prior to the commencement of phases 2 and 3. These costs are added to the JV Account and allocated to the relevant phase during the development stage. All outstanding sums within the JV account are subject to interest, the cost of which is shared equally by the partners. These costs include:-
(i) Master Planning costs associated with Phase 3 (ii) Planning Fees (iii) Services Design (iv) Installing roads and installing services in road / footpaths (as part of road building phase) 4. Trigger Point to Allow Phase 3 to Start
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NORA JOINT VENTURE: PHASE 3Report | 188 KB | DownloadRead as text |
Follow Cabinet at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | ApologiesAn apology for absence was received from Councillor Moriarty. | Decided | Open |
| 17 Nov 2026 | MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... | Agreed | Open |
| 17 Nov 2026 | Urgent businessNone. | Decided | Open |
| 17 Nov 2026 | Declarations of interestNone. | Decided | Open |
| 17 Nov 2026 | Chair's correspondenceNone. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.