Resolved
The Committee considered the contents of the Corporate Risk Register and confirmed agreement with Management Team’s assessment of the risks to the Corporate Objectives.
Audit Committee agreed this item on Tuesday 30 May 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee considered the contents of the Corporate Risk Register and confirmed agreement with Management Team’s assessment of the risks to the Corporate Objectives.
Not applicable
Members are requested to consider the contents of the Corporate Risk Register and confirm agreement with Management Team’s assessment of the risks to the Corporate Objectives.
In order to ensure the Council meets its statutory obligations to ensure that it has 'effective arrangements in place for the management of risk'.
REPORT DETAIL
1. Introduction 1.1 The Risk Management Policy and Risk Management Strategy were presented to the Audit and Risk Committee in February 2016 and approved by Cabinet on 1st March 2016.
1.2The Terms of Reference for the Audit and Risk Committee include responsibility for monitoring the management of risk by Management Team. To this end, the Committee receives reports on a half-yearly basis on the position of the Corporate Risk Register, with the last one, as at October 2016, being presented in November 2016.
1.3Each risk on the register is scored in terms of Impact and Likelihood, according to criteria defined within the Corporate Risk Strategy. The definitions are attached for reference in Appendix 2. 1.4 The Risk Register is reviewed by the Executive Directors on a 6-monthly basis. Any existing entries on the register are considered for changes to the nature of the risk, progress to be reported and any adjustments to the risk scores. Risks that are no longer relevant are removed and new risks considered in the context of current circumstances are added. The risk reference numbers are not reallocated when risks are removed from the register, to enable the history to be maintained.
1.5A summary of the changes to the Risk Register since the last monitoring report are detailed in section 2 below. Details of the ‘Very High’ risks are given in Appendix 1 together with a list of the ‘High’ risks.
1.6The full Risk Register, as agreed by Management Team, has been provided to the Audit Committee in hard copy, for reference.
2. Changes to the Register
2.1The Risk Management Policy states that to ‘ensure it is effective, risk management needs to be aligned with corporate aims, objectives and priorities’. As such the format of the risk register is ordered to reflect the Priorities as contained in the Corporate Business Plan. This makes the link between the Priorities and the management of associated risks clearer.
2.2Apart from small changes made from a fresh review of the content and updates on progress for various entries, the main changes since October 2016 are listed below.
2.3Risks to be removed:
Two risks have been removed from the register, from Priorities 1 and 2.
1.14– Land Charges
The risk was originally added as an adverse judgement on a land charges case may have resulted in the Council being liable to reimburse an element of past Land Changes fees. The Service Manager advises that no further claims are expected and Management Team has determined that this entry may therefore been removed.
2.6– Major Planning Applications
The risk was originally added to the register when changes were proposed by the Government to the way that Major Planning Applications were to be dealt with. Management Team have determined that the new Minister does not appear minded to progress the possible option and so this risk may be removed from the register.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Register Monitoring ReportReport | 86 KB | DownloadRead as text |
Follow Audit Committee at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2026 | Appointment of Vice - Chair for Municipal Year 2026/2027Councillor Bearshaw was appointed Vice – Chair for the Municipal Year 2026/2027. | Decided | Open |
| 14 Sep 2026 | MinutesThe minutes from the meeting held on the 15 th June 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 14 Sep 2026 | Work Programme and Forward Decision ListThe Audit Committee noted the Work Programme and the Forward Decisions List. | Noted | Open |
| 15 Jun 2026 | Appointment of Vice - Chair for the Municipal Year 2026/2027Councillor A Jamieson was appointed Vice – Chair for the Municipal Year 2026/2027. | Decided | Open |
| 15 Jun 2026 | MinutesThe minutes from he meeting held on the 23 rd March 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.