RESOLVED :That the Council agrees to make up to £125K available from Reserves towards initial design work for the West Winch relief road. Reason for Decision To support the development of 3 – 3500 houses provided for in the Local Plan allocation.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
That Cabinet agrees to make up to £125K available from Reserves towards initial design work for the West Winch relief road.
Reason for decision
To support the development of 3 – 3500 houses provided for in the Local Plan allocation.
Background
1.1The Core Strategy adopted in 2011 and the Site Allocations and Development Management Policies Plan adopted in 2016 make allocations for a large housing area at West Winch / North Runcton of some 3-3500 houses. There is a considerable amount of associated infrastructure which is needed to ensure the development takes place in a way that it mitigates the impacts locally and those in the wider catchment. 1.2 The two plans above contain very detailed explanations of what is required to give an acceptable development, but this is not specific enough to ensure a fully deliverable Section 106 agreement (or set of agreements). The Borough Council has commissioned work on an Infrastructure Delivery Plan (IDP) to ensure the most effective way of providing that infrastructure.
1.3The results of the IDP work will not be fully available until July, but we do know that the landowners and potential developers previously expressed reservations about the infrastructure bill at the Local Plan Examination in 2015 / 16. The Borough Council made amendments to the allocation and included additional developable land to support viability and deliverability. The strategic site is also zero rated for Community Infrastructure Levy (CIL) in the light of a high level viability assessment. Taking this all into account we consider that whilst the site is viable, careful attention needs to be paid to the infrastructure needed and the phasing of it. Hence we commissioned the IDP work to ensure this. Whilst the work is led by the Borough Council it actively seeks the involvement of the landowners and developers.
1.4One of the key elements of the Local Plan allocation is the provision of a West Winch relief road to serve the Growth Area and ensure traffic from the new development has a minimal impact on the existing A10 as it passes through the village of West Winch. Specific access points will draw traffic away from the A10. This road will also have the effect of diverting existing traffic away from the village. This aspect of the Growth Area proposal is widely supported, and the local communities have a view that the relief road should be provided before any residential development takes place.
1.5Norfolk County Council as the strategic Highway Authority has a genuine involvement in the provision of an effective road network capable of accommodating the proposed growth. They also have the expertise to provide a design, and have been involved in the plan making process since the Growth Area was first proposed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.