Resolved
The Panel supported the recommendations to Cabinet as set out below. It is recommended that the Action Plan be approved.
Regeneration and Development Panel approved this item on Tuesday 29 January 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
The Panel supported the recommendations to Cabinet as set out below. It is recommended that the Action Plan be approved.
Borough Council of King’s Lynn & West Norfolk
SELF-BUILD & CUSTOM HOUSE BUILDING ACTION PLAN
November 2018 This marks the first document where the Borough Council has set out both its responsibilities and ambitions for self-build and custom house building in the Borough.
Self-build and custom house building has recently received increasing Government attention in the face of meeting the need for housing in the UK.
This action plan sets the background as to why self-build and custom house building has gained increasing focus from Government, which has translated into national legislation, policy, regulations and guidance. This document marks the first corporate action plan that comprehensively covers this issue.
It explains emerging local policies, strategies and development in the Borough, as well as the latest evidence the Council has regarding the local demand for self and custom build housing.
The Council recognises that self and custom house building developed in the Borough offers an important potential route to home ownership and contributes towards housing delivery. This action plan marks the first step in the Council in:
‘Positively influencing or helping to secure development opportunities where it can support individuals or organisations in our local communities to deliver high quality self-build or custom house building to meet demand in the Borough.’
1|Page CONTENTS
1.0INTRODUCTION Page 1
2.0BACKGROUND Page 2
3.0WHAT IS SELF-BUILD & CUSTOM HOUSE BUILDING? Page 6
4.0WHAT ARE THE COUNCIL’S RESPONSIBILITIES FOR Page 8 SELF-BUILD AND CUSTOM HOUSE BUILDING?
5.0WHAT HAS THE COUNCIL DONE TO SECURE Page 11 SELF-BUILD AND CUSTOM HOUSE BUILDING TO DATE? AND WHAT IS PLANNED FOR THE FUTURE?
6.0LOCAL SELF-BUILD AND CUSTOM HOUSE BUILDING Page 16 DEMAND IN WEST NORFOLK
7.0THE COUNCIL’S SELF-BUILD AND CUSTOM HOUSE Page 17 BUILDING ACTION PLAN
Page 23 8.0 MONITORING & REVIEW
Page 24 9.0 LIST OF ACTIONS
2|Page 1.0 INTRODUCTION
The Purpose and Role of Borough Council of King's Lynn & West Norfolk Self-Build & Custom House Building Action Plan
1.1The purpose of this action plan is to set out the Council’s own responsibilities and wider ambitions in respect to self-build and custom house building in the Borough.
1.2The delivery of self and custom house building in the Borough is not the sole responsibility of the Council, it in fact relies heavily on those wishing to and having the means to build houses themselves, organisations who would like to facilitate or deliver self-build plots or build custom built houses and interested landowners and developers promoting sites for such products. Given this context, the Council aims to: ‘positively influence or help secure development opportunities where we can support individuals or organisations in our local communities to deliver high quality self-build or custom house building to meet demand in the Borough’.
1.3This document sets out the Council’s proposed actions to directly meet its own responsibilities to help deliver quality self-build and custom house building in the Borough to meet local demand. It also sets out the Council’s wider ambitions, where we want to work with customers and partners to influence and help deliver such high-quality housing products.
1.4This action plan will need to be reviewed and updated as and when necessary. This is the Council’s first comprehensive action plan focused on this issue. The Council also recognise that this sector in many respects is in its infancy in the UK, and with increasing experience in the Borough, it is important that lessons are learnt and reflected in future action plans.
3|Page 2.0 BACKGROUND
Self-Build & Custom House-Building Gaining Increasing Focus from Government
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CSB Action plan FINAL :Report | 373 KB | DownloadRead as text |
PDF |
Custom Build Action PlanReport | 197 KB | Download |
Follow Regeneration and Development Panel at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Sep 2026 | RD26The minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 30 Sep 2026 | RD32The Panel’s Work Programme and the Forward Decisions List were noted. | Noted | Open |
| 30 Sep 2026 | RD34That under Section 100(A)(4) of the Local Government Act, 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 30 Sep 2026 | RD35That the Regeneration and Development Panel support the recommendations to Cabinet as included in the agenda. | Decided | Open |
| 22 Jul 2026 | RD14The minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.