Resolved
Members reviewed the progress against the audit plan and noted the update of the fraud work.
Audit Committee noted this item on Monday 3 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Members reviewed the progress against the audit plan and noted the update of the fraud work.
POLICY REVIEW AND DEVELOPMENT PANEL REPORT
REPORT TO: Audit Committee DATE: 3rd June 2019 TITLE: Internal Audit Full Year Progress Report 2018-19 TYPE OF REPORT: Update PORTFOLIO(S): Cllr Long, Finance REPORT AUTHOR: Kathy Woodward, Internal Audit Manager OPEN/EXEMPT Open WILL BE SUBJECT No TO A FUTURE CABINET REPORT:
REPORT SUMMARY/COVER PAGE
PURPOSE OF REPORT/SUMMARY: To provide Members with an update on progress against the Internal Audit Strategic Plan 2018-19 that was endorsed by the Audit Committee at the meeting on 12th February 2018. The report also provides an update on the fraud work for the first half of the year.
KEY ISSUES: Section 5 of the Accounts and Audit Regulations 2015 state that ‘A relevant authority must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance.’
The work of the Internal Audit team throughout the year is directed towards compliance with this requirement as well as aiming to add value to the Council’s services by identifying opportunities to improve efficiency and effectiveness.
The Audit Committee Terms of Reference require it to monitor the delivery of the internal audit activity.
OPTIONS CONSIDERED: Not applicable
RECOMMENDATIONS: Members are asked to review the progress against the audit plan and to note the update of the fraud work.
REASONS FOR RECOMMENDATIONS: Audit Committee members are required to monitor the delivery of the Internal Audit Plan as part of the Committee’s Terms of Reference, which is legislated in section 5 of the Accounts and Audit Regulations 2015. REPORT DETAIL
1. Introduction
1.1The Strategic Audit Plan 2018-19, endorsed by the Audit Committee on 12th February 2018, sets out the work Internal Audit expect to carry out during the year. This work complies with the requirements of the Accounts and Audit Regulations 2015:
Section 3 – A relevant authority must ensure that it has a sound system of internal control which: a) Facilitates the effective exercise of its functions and the achievement of its aims and objectives b) Ensures that the financial and operational management of the authority is effective
Section 5 - A relevant authority must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance.’
1.2Performance Standard 2060 of the Public Sector Internal Audit Standards (PSIAS) requires the Audit Manager to report to the Audit Committee on the internal audit activity and performance relative to this plan.
1.3The Terms of Reference for the Audit Committee require the Committee to monitor delivery of the internal audit activity to ensure that the resources and work are sufficient to fulfil the requirements of the Accounts and Audit Regulations.
2. Monitoring Report 2.1 On completion of each audit a formal report is issued to the relevant line managers, the Executive Director and Portfolio Holder. Copies are sent to the Chief Executive, Deputy Chief Executive (s151 Officer), and the external auditors, Ernst and Young. A copy is also placed on InSite in the restricted area for members of the Audit Committee to view. Each report contains an action plan, with target dates, that has been agreed with the managers to address any observations and recommendations raised by the Internal Auditor. This forms the basis of the follow-up audit, which is carried out approximately six months later to assess progress in implementing the agreed actions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Full Year Progress Report 2018/2019Report | 162 KB | DownloadRead as text |
Follow Audit Committee at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2026 | Appointment of Vice - Chair for Municipal Year 2026/2027Councillor Bearshaw was appointed Vice – Chair for the Municipal Year 2026/2027. | Decided | Open |
| 14 Sep 2026 | MinutesThe minutes from the meeting held on the 15 th June 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 14 Sep 2026 | Work Programme and Forward Decision ListThe Audit Committee noted the Work Programme and the Forward Decisions List. | Noted | Open |
| 15 Jun 2026 | Appointment of Vice - Chair for the Municipal Year 2026/2027Councillor A Jamieson was appointed Vice – Chair for the Municipal Year 2026/2027. | Decided | Open |
| 15 Jun 2026 | MinutesThe minutes from he meeting held on the 23 rd March 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.