RESOLVED : That the application of the Vacant Building Credit in line with the CIL regulations in order to offer increased clarity for applicants and decision makers be adopted. Reason for Decision To adopt a clear and transparent approach to applying the Vacant Building Credit and avoid uncertainty when dealing with planning applications.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
1.1Vacant Building Credit (VBC) was first introduced in a ministerial statement in November 2014. The measure is included in the National Planning Policy Framework, February 2019 which states ‘To support the re-use of brownfield land, where vacant buildings are being reused or redeveloped, any affordable housing contribution due should be reduced by a proportionate amount’ 1.2 NPPG provides guidance on how VBC should be calculated and when it should be applied. This suggests that authorities consider “whether the building has been made vacant for the sole purposes of re- development” and “whether the building is covered by an extant or recently expired planning permission for the same or substantially the same development”.
1.3Since the credit was introduced, we have taken the approach of applying the credit to any brownfield proposal with vacant building(s), provided they have not been abandoned. We have relied on information provided to us in the planning application, usually the Design & Access Statement and requested further evidence where necessary.
1.4Neither NPPF nor NPPG define how long a building should be vacant for in order to qualify for VBC or clarify what constitutes a building for the purposes of the vacant building credit. To date it has been down to the officer to decide whether or not the building is vacant and whether the credit should be applied. This has led to a high level of subjectivity as to what constitutes a vacant building.
1.5However, the CIL regulations apply a credit for in-use buildings and define an in-use building as
“contains a part that has been in lawful use for a continuous period of at least six months within the period of three years ending on the day planning permission first permits the chargeable development”.
1.6The CIL regulations also clarify that “building” does not include
(i) a building into which people do not normally go; (ii) a building into which people go only intermittently for the purpose of maintaining or inspecting machinery; or (iii) a building for which planning permission was granted for a limited period;
1.7Therefore, it follows that a vacant building can be defined as a building (not including the above exemptions) that is not in-use, this would lead to a vacant building being defined as
“a building that has not been in use for a continuous period of at least six months within the past 3 years.”
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.