Resolved
The update was noted. At 6.42pm the Panel had a five minute comfort break. The Panel reconvened at 6.47pm and the Democratic Services Officer conducted a roll call.
Corporate Performance Panel noted this item on Wednesday 31 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
The update was noted. At 6.42pm the Panel had a five minute comfort break. The Panel reconvened at 6.47pm and the Democratic Services Officer conducted a roll call.
Major Housing Project
Dale Gagen Assistant Director – Companies & Housing Delivery Background on The Major Housing Project 1. When was the Major Housing project conceived
2. Why was the Project was started
3. How was the Project developed
4. What was the procurement route
5. How does the contract work
6. Who is the Developer
7. How is risk managed Current Delivery
Site Property Completion Notes Contractor Numbers Date NORA Phase 1 2015 JV with NCC Carters NORA Phase 2 2017 JV with NCC Carters NORA Phase 3 2019 JV with NCC Lovell
Orchard Place 2019 Major Housing Contract Lovell
Dewside 2020 Major Housing Contract Lovell
Cowper Place 2021 Major Housing Contract Lovell
NORA Phase 4 Ongoing Major Housing Contract - Piling Lovell Starts April 2021 Parkway 379 units over 12 phases
A development of 379 new homes together with associated roads and infrastructure, and a new vehicular bridge over the sand line rail line providing pedestrian, cycle and vehicular links from the Hardwick Industrial Estate Parkway – funding the scheme Fund Claim
Project Cost £88,771,000 Business Rates Pool - 035 £200,000
Income Business Rates Pool - 034 £1,878,000 Open Market Sales £44,890,000 Private Rental Sector £22,071,000 Affordable Units £6,330,000 Homes England - £3,035,000 Grants £10,113,000 Accelerated Land Receipts £5,937,000 Construction Programm Surplus £570,000 e Towns Investment Plan £5,000,000 Parkway – partners
Lovell Partnerships House and road build Fielden & Maswon Architects Scheme design Mott MacDonald Ecology Bridge design Air quality / noise surveys / traffic modelling Ground conditions Norfolk County Council Bridge and road build Royal Haskoning DHV Estate Road engineering Estate drainage and sewers design IDB Stantec modelling Parkway – planning Committee 31st March 2021 232 public comments and petition The site measures approximately 19.5 hectares Multi Use Games Area and play areas Homes will have air source heat pumps and, where house type and plot orientation allow, will be fitted with solar panels. All garages will include electric charging 3 points
Tenure 1bed 2bed 3bed 4bed 1bed 2bed Total house house house house flat flat
Affordable 11 9 8 2 0 9 39 Rent
Open 0 56 88 45 0 0 189 Market
Private Rent 0 33 47 4 26 24 134 (PRS)
Shared 0 8 9 0 0 0 17 Ownership
Total 11 106 152 51 26 33 379 Parkway Development – Ecology
Ecology supporting statements undertaken by Mott MacDonald including:- • Reptile Report • Bat Report • Breeding Bird Report • Great Crested Newt Report • Reptile Fencing Methodology • Noise – impact from railway & industrial estate • Traffic & air quality assessment • Water Vole Report & Licence Application Parkway Bridge Project Road bridge over rail line linking Parkway development with Fairstead & Hardwick
Fairstead Estate
Location of proposed rail bridge Parkway Development - Bridge
• NCC to design and deliver bridge and infrastructure works in partnership with BCKL&WN • Spans Network Rail line from Kings Lynn to Leziate sand pits (Sibelco UK) • Provides traffic route from Parkway development south to Hardwick industrial area • Provides emergency access & footway/cycle link north to Fairstead housing • Five spans a total of 150m long excluding approach ramps • 6.0m carriageway • 3.0m combined footway/cycleway • 2.0m footway Salters Road Milestone GFA Date Start Date January 2019 78 units, Freebridge Project Completion Date 31st December 2022 Homes England Accelerated Completion of the Construction Programme funding - 30th June 2021 Development Works £2,000,000 Start on site of housing 30th April 2021 Lovell Partnerships development
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Projects under Portfolio Holder for Project DeliveryReport | 3.3 MB | DownloadRead as text |
Follow Corporate Performance Panel at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Appointment of Vice - Chair for the MeetingCouncillor Spikings was appointed Vice – Chair for the meeting. | Decided | Open |
| 10 Nov 2026 | MinutesThe minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 10 Nov 2026 | Cabinet Report - Corporate Performance Monitoring Quarter 2The Panel supported the recommendations to Cabinet. Cabinet Resolves to: 1. To review the Performance Management Repo... | Decided | Open |
| 10 Nov 2026 | Cabinet Report – Council Tax Support Scheme for Working Age People for 2027/2028The Panel supported the recommendations to Cabinet then Council. Recommendation to Full Council: That the draft Counc... | Agreed | Open |
| 10 Nov 2026 | Cabinet Report - Council Tax Discounts, Levies and Premiums for Empty Properties and Second Homes for 2027/2028The Panel supported the recommendations to Cabinet then Council. Recommendation to Full Council: The following discou... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.