To improve the council’s streetlighting (some of which have columns in need of replacement), achieve wider energy savings and help reduce the Borough Council’s carbon footprint to net zero. To improve the council’s streetlighting (some of which have columns in need of replacement), achieve wider energy savings and help reduce the Borough Council’s carbon footprint to net zero.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
1.1In 2018 we started Re:fit Phase 1, in which Ameresco were selected to deliver energy efficiency and emissions reduction projects. Ameresco produced an investment grade proposal (IGP) for our last remaining project; improving the streetlighting portfolio.
1.2Streetlighting was slipped from Phase 1 following an assessment of all of the Council streetlighting stock, which identified significant additional work required to identify what was required to allow all columns to be fitted with the new LED heads.
1.3Ameresco will install high efficiency LED lighting, by replacing units on a one for one basis. Streetlighting columns are also included within the replacement scope. From our 684 streetlights, 126 columns need replacement due to having serious defects or having defects whilst being situated in a high-risk area.
1.4Council approved £2,000,000 of capital funding on 29 November 2018 to progress the projects. This approval was granted assuming the identified schemes remained at or improved the agreed payback. Payback for the streetlighting project was identified at 17.30 years and for the total Re:fit project, at 10.50 years.
1.5Following the streetlighting IGP, the payback period of 22.95 years was identified, which is outside of the above agreed payback terms.
Options considered
2.1Option 1: Approve the Streetlighting works Go ahead with the project despite the longer payback period to improve streetlighting and achieve further energy savings for the borough council. This is in line with the council’s climate change policy and agenda and will replace columns with serious defects.
2.2Option 2: Decline the Streetlighting works This is an option; however, this goes against the council’s climate change policy and agenda and will leave 126 columns standing that need replacement.
3. Policy Implications
3.1This project will follow the aims set out in the Borough Council’s Climate Change Policy to reduce its carbon footprint to net zero. This work will also tie in with the draft Climate Change Strategy and Action Plan. It follows best practice in reducing the energy required for street lighting.
Financial implications
4.1The total spend on Re:fit Phase 1 to date is £1,404,399. The streetlighting estimate of £598,258 will bring total spend to £2,002,659 which is £2,659 above the approved budget. If approved, this additional cost can be met by a transfer from the streetlight reserve.
5. Personnel Implications
5.1The council will use our project manager, Mayra Torres from Local Partnerships to act for us. The project will be delivered by Ameresco. Ameresco were appointed following the initial Re:fit procurement process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.