Borough Council of King's Lynn and West Norfolk
Cabinet, Monday 11 April 2022 at 2.00pm

GUILDHALL CREATIVE HUB OPTIONS INCLUDING GOVERNANCE

Agreed Executive 7 papers

Cabinet agreed this item on Monday 11 April 2022. Below is the council's own wording, with the papers it was decided on.

ItemCAB130

Resolved

RECOMMENDED: The Council endorses the Vision Manifesto (appendix 1) and the Business Plan (appendix 2) for the Centre for submission to the Towns Fund and NHLF. That following consideration of the options for securing funding for the Guildhall and Creative Hub set out in section 4, the council agrees to amend the capital programme as set out in section 7.3 in the report, to underwrite the match funding required in order to secure the Towns Fund allocation. In the event the NLHF Stage 1 or 2 applications are not successful, a further report be brought back to Cabinet and relevant Panels to confirm the final project scope and extent of funding required as detailed in section 7.3 of the report That following a consideration of the options for a governance and operating model that a new separate entity is formed. That on consideration of options (appendix 3), that this entity is a newly formed for purpose Charitable Incorporated Organisation (CIO). That the process of forming a new Independent CIO with a wholly owned trading subsidiary is commenced and matters relating to this including: · Finalising the constitution and Governing Document the way the CIO will run · Selecting the Chair and two initial trustees before an application to the Charities Commission is made as detailed in section 5 of the report. · Choosing a name are delegated to the Monitoring Officer and Chief Executive in consultation with the Portfolio Holder for Business, Culture and Heritage and the newly formed task group. The financial implications of the decisions as set out in section 7 of this report are endorsed and reflected in the Council’s Financial Plan from 2025 onwards Delegate authority to the Assistant Director for Property & Projects in consultation with the Portfolio Holder for Commercial Property to negotiate and conclude the leases with existing tenants. Reason for Decision To provide the match funding evidence for the ‘Guildhall and Creative Hub’ to secure the £4.8m Towns Fund allocation. A timely decision about how a future enterprise will be governed and the model under which it will operate is an important part of planning the ‘Guildhall and Creative Hub’ project and the associated funding submissions. The decision will demonstrate to funding bodies that the council is giving careful consideration and certainty at this stage to the future sustainability of the investment being sought and the key documents that will define the relationship between the council and the entity that will run the Guildhall and Creative Hub. The project directly supports and will deliver against the Council’s commitment and ambitions for culture as set out in the Council’s Cultural Prospectus and Town Investment Plan (2021).
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Cabinet

King’s Lynn St George’s Guildhall Complex – a manifesto Who Are we?

The Borough Council of King’s Lynn and West Norfolk; National Trust; Norfolk Museums Service, and Norfolk Arts Service are working in partnership to deliver a conservation and regeneration project centred around King’s Lynn’s Grade 1 Listed St George’s Guildhall complex.

These partners are working together to deliver a transformative cultural project for King’s Lynn and exploring appropriate governance models to deliver a sustainable future for the complex. The partners are working hand-in-hand with the Town Deal Board to deliver a pivotal part of the £25 million vision for the town. The St George’s Guildhall project will promote the town’s heritage and connection to Shakespeare, boost skills, and support new businesses and creative practice.

What are we doing?

We are working in partnership.

We are protecting and celebrating the heritage of these unique buildings:

• Protecting the historic fabric of listed buildings, notably the Grade 1 Listed St George’s Guildhall Theatre • Safeguarding the future of the oldest working theatre in the UK, an historic space which has hosted all phases of drama since the 15th century, a place where Shakespeare’s Touring Company has performed, as well as Shakespeare’s comedian and King’s Lynn born Robert Armin • Refurbishing the historic theatre to create an accessible, welcoming, and attractive space that is fit for purpose and open to a wide range of audiences • Creating inspiring spaces at the heart of the local community, and a beacon for visitors to King’s Lynn • Interpreting the rich story of the complex and the lives of people associated with it; telling the story of English theatre from the Guild period to the present day in an interactive working theatre environment • Engaging and involving all sections of our local communities and wider audiences in the rich story of these historic buildings, through broad and inclusive programmes of formal and informal learning including youth engagement.

We are supporting enterprise and economic productivity in King’s Lynn:

• Creating a financially sustainable operating model for the St George’s Guildhall Complex • Bringing measurable social and economic benefits to King’s Lynn and West Norfolk • Delivering a viable and sustainable plan for the St George’s Guildhall Complex bringing commercial and cultural initiatives together under one ‘roof’, under the direction of a pioneering partnership • Establishing co-ordinated site management • Supporting the creative arts sector by collaborating with other organisations • Delivering an environmentally responsible project, and a reduction in energy use for the complex • Supporting skills and enterprise development and routes into employment

Page 1 of 3 Signed off by Project Board 18th October 2021 We are creating a hub for arts and culture:

• Creating a sense of identity and place, drawing on the unique significance of the Guildhall Theatre • Creating a nationally significant centre for culture and the arts, which serves its local community • Creating an accessible and flexible space able to house a changing programme of events and activity; hosting professional and community theatre, dance or musical groups, or a venue for films, talks, comedy and poetry • Modernising and effectively using buildings to provide spaces for interpretation, exhibitions, formal & informal learning, retail, and catering and use by the local community • Providing a welcoming point of entry and improved street presence

Why are we doing it?

For heritage: To bring life back into the historic complex, giving it a sustainable future

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20211810 KLGuildhall Vision Manifesto, 24/03/2022 Cabinet Sifting Papers, 30/03/2022 Joint Panel MeetingReport 70 KB DownloadRead as text
PDF
App 4 Guildhall creative hub finance assessment, 24/03/2022 Cabinet Sifting Papers, 30/03/2022 Joint Panel MeetingAppendix 384 KB Download
PDF
Operating Model Options, 24/03/2022 Cabinet Sifting Papers, 30/03/2022 Joint Panel MeetingAppendix 3 113 KB Download
PDF
Guildhall management agreement, 24/03/2022 Cabinet Sifting Papers, 30/03/2022 Joint Panel MeetingAppendix 6 526 KB Download
PDF
FEI KLGHCH Business Plan FINAL VERSION, 24/03/2022 Cabinet Sifting Papers, 30/03/2022 Joint Panel MeetingReport 10 MB Download
PDF
Financial Risk Analysis Appendix 4 (a) by Project Finance Accountant, 24/03/2022 Cabinet Sifting Papers, 30/03/2022 Joint Panel MeetingAppendix 377 KB Download
PDF
GUILDHALL CREATIVE HUB OPTIONS INCLUDING GOVERNANCEReport 630 KB Download

At this meeting

Whole meeting

Who was there

6 of 20 attended
AB
Alexa BakerOfficer, expected
KB
Kate BlakemoreOfficer, expected
RB
Councillor Richard BluntCommittee Member, present
JC
Jemma CurtisCouncil Staff, expected
SD
Councillor Stuart DarkChair, present
AD
Councillor Angie DickinsonCommittee Member, apologies
MD
Michelle DreweryOfficer, expected
DG
Debbie GatesOfficer, expected
LG
Lorraine GoreOfficer, expected
GH
Geoff HallOfficer, expected
CH
Carl HollandCouncil Staff, expected
AI
Aaron IrelandCouncil Staff, expected

All 20 on the meeting page

On this subject at King's Lynn and West Norfolk

Search all
  1. GUILDHALL CREATIVE HUB OPTIONS INCLUDING GOVERNANCEThis decision
  2. Guildhall and creative hubAgreed
  3. King's lynn town deal guildhall & creative hub business caseApproved
  4. Cabinet Report - St George's Guildhall and Creative Hub - Project Underwriting, Future Governance and Operating Model ArrangementsDecided
  5. Cabinet Report - St George's Guildhall and Creative Hub - Project Underwriting, Future Governance and Operating Model ArrangementsAgreed

More from King's Lynn and West Norfolk Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 ApologiesAn apology for absence was received from Councillor Moriarty. Decided Open
17 Nov 2026 MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... Agreed Open
17 Nov 2026 Urgent businessNone. Decided Open
17 Nov 2026 Declarations of interestNone. Decided Open
17 Nov 2026 Chair's correspondenceNone. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies