The Panel received a further report addressing the outstanding issues as set out below (prior to Christmas 2022): · Collection dates/reporting weekends/bank holidays · USP’s – rolled out elsewhere – why not rolled out here/ · Changing rounds without consulting officers and Councillors.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
Waste and Related Services Contract (Serco) Performance Management Report
Barry Brandford, Waste & Recycling Manager Background The Contract involves three councils (Breckland DC, North Norfolk DC and Borough Council of King’s Lynn and West Norfolk). Serco were previously the service provider for Breckland DC Services under this contract started in North Norfolk in April 2020 and for King’s Lynn & West Norfolk and Breckland in April 2021
Covid19 impacted the mobilisation of the contract. • Food waste could not be collected to prioritise Green and Black Bins • Waste and Recycling amounts increased • Staff availability reduced • Not all systems and training could be fully deployed • Data management and reporting delayed Contract Performance Standards The contract in King’s Lynn and West Norfolk’s area collects each week • 37,500 Black Bins • 37,000 Green Bins • 14,400 Brown Bins
The Contract has performance management framework This has two parts relating to • Contract Wide Standards • Locally Derived Performance
The contract is self monitoring and Serco are responsible for collecting performance data and reporting it to the council. Contract Wide Standards Dec Jan Feb Mar April Failure to gain ISO9001, ISO14001, ISO45001 or agreed equivalent accreditation within the relevant timescale and continuously maintain 0 0 0 0 0 these accreditations thereafter Failure to notify the Supervising and Authorised Officers of RIDDOR 0 0 0 0 0 reportable incident Unavailability of Contract Managers during the specified hours 0 0 0 0 0 Unavailability of Contract Manager(s) or Supervisory Staff to contact 0 0 0 0 0 during urgent situations arising out of normal office hours Failure to manage and maintain suitable and secure IT systems and paperless MIS and provide an auditable trail of the Services provided, and store and update at least, but not limited to, the information listed in 0 0 0 0 0 Authorities' Requirements paragraphs 6.5.8 throughout the Contract Period. Contract Wide Standards Unavailability or inaccessibility of the IT system and/or Dec Jan Feb Mar April MIS: Number of hours every Quarter 0 0 0 0 0
Number of hours per Contract Year 0 0 0 0 0
Failure to respond to information requests from the Supervising / Authorised 0 0 0 0 0 Officers within the specified timescale within 3 working days
Failure to follow the Daily reporting procedures, associated timescales and/or 0 0 0 0 0 provide the required information Performance Reporting Standards Provision of Self Monitoring Reports Dec Jan Feb Mar April
Failure to provide accurate Monthly Report 0 0 0 0 0
Failure to provide accurate Quarterly Report 0 0
Failure to provide accurate Annual Report 0 Contract Wide Standards Provision of Customer Care Centre & Performance Dec Jan Feb Mar April
Failure to provide a fully functional Customer Care Centre (CCC) in accordance 0 0 0 0 0 with the Authorities' Requirements
Failure to achieve the CCC performance standards 0 0 0 0 0
Failure to address complaints / referrals in accordance with the Authorities' 0 0 0 0 0 Requirements Contract Wide Standards Method Statements, Staff & Vehicles Dec Jan Feb Mar April
Failure to update Method Statements at least annually and for each Service change agreed with the Supervising Officer and submit the updates for his/her 0 Approval in accordance with the Authorities' Requirements. Failure to ensure that all Staff, including supervisory Staff, are at all times properly attired and presentable in appropriately identifiable, functional, protective and smart clothing approved by the Supervising Officer, wear appropriate PPE and are issued 0 0 0 0 0 with identity cards which have a photograph of the individual together with their name and Staff number (if applicable) indicated thereon
Failure to keep Plant employed in the performance of the Services in good and serviceable repair in accordance with the maintenance arrangements in the Annual 0 0 0 0 0 Maintenance Plan. Contract Wide Standards Ancillary Matters Dec Jan Feb Mar April
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Performance Panel at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.