Planning Committee, Monday 3 July 2023 at 9.30am

Decisions on Applications

Refused Planning 6 papers

Planning Committee refused this item on Monday 3 July 2023. Below is the council's own wording, with the papers it was decided on.

ItemPC21:a

Resolved

That the application be determined, as set out at (i) – (ix) below, where appropriate, to the conditions and reasons or grounds of refusal, set out in the schedules signed by the Chair. (i) 23/00265/CU Walpole: 10 Folgate Lane, Walpole St Andrew: Change of use of bungalow from a dwelling (C3) to a children’s home (C2) for up to two children: [name removed] here to view a recording of this item on You Tube The case officer presented the report and explained that the application had been referred from the 5 June Planning Committee meeting to enable the applicant to obtain his OFSTED registration. The agent had confirmed that part of the registration process required the applicant to provide a copy of the planning permission granted, a certificate of lawfulness, a copy of a planning application or evidence that planning permission was not required. Whilst he could start the registration process, it would not be possible to complete the registration until he had the decision relating to the planning application. The Committee was therefore asked to determine the application as submitted. The application site was located within the development boundary of Walpole St Andrew, which was classified as a Rural Village within Policy CS02 of the Core Strategy 2011. The site was located along Folgate Lane, at the end of a row of single storey dwellings, before the lane led out into open countryside. On site was an existing dwelling of prefabricated construction. The proposal sought the change of use of the existing dwelling (C3) to a children’s home (C2) for up to two children. The proposed number of children was reduced during the course of the application from ‘up to three’ and an amended description advertised. The application had been referred to the Committee originally by the Assistant Director of Environment & Planning due to the scale of objections. The Parish Council also objected to the proposal. The application was deferred from the 5 June Planning Committee meeting. The Committee noted the key issues for consideration, when determining the application, as set out in the report. In accordance with the adopted public speaking protocol, Kym Marlow (objecting) and Heather Smith (objecting on behalf of the Parish Council) addressed the Committee in relation to the application. In response to a question from Councillor Ring about whether it was known if there was asbestos in the building, the Planning Control Manager explained that this would be covered by separate legislation. The Executive Director, in response to a request by Councillor Blunt, read out point 2 of the Ministerial Statement and explained that it would be up to the Committee to decide whether the application met the terms of the Statement. Councillor Blunt stated that the Committee should have more information before making ... view the full minutes text for item PC21:a
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Planning Committee

Recommendation

APPROVE

THE APPLICATION

This application is for the installation of a Battery Energy Storage System (BESS) to the east of Walpole Bank opposite from the Walpole Substation on an irregular shaped parcel of 1.8ha of agricultural land.

Principal access to the site would be off Walpole Bank via an access already approved for a further BESS adjacent to the road under application ref: 22/00438/FM. The proposal would be undertaken either consecutively or after the development of the site to the west which has already been granted Planning Permission. An emergency access is also proposed connecting to Folgate Lane to the east.

There is a land drain close to the southern boundary and an overhead power line suspended between pylons bisects the northern portion of the site.

The BESS would store excess electricity at times of low demand and then release it back into the grid when required at peak times. It would be rated at up to 100MW and would therefore be capable of serving the needs of over 280,000 homes for one hour if required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
22.02265.FM :aReport 295 KB DownloadRead as text
PDF
22.02265.FM Map 1 :aPlan 227 KB Download
PDF
22.02265.FM Map 2 :aPlan 472 KB Download
PDF
23.00265.CU :aReport 215 KB Download
PDF
23.00265.CU Map 2 :aPlan 271 KB Download
PDF
Decisions on ApplicationsDecisions 234 KB Download

At this meeting

Whole meeting

Who was there

17 of 33 attended
BA
Councillor Bal AnotaCommittee Member, present
JA
James ArrandaleCouncil Staff, expected
AB
Alexa BakerCouncil Staff, expected
RB
Councillor Richard BluntCommittee Member, present
FB
Councillor Francis BoneCommittee Member, present
TB
Tracy BrookerCouncil Staff, expected
AB
Councillor Anthony BubbCommittee Member, present
CC
Councillor Chris CroftsCommittee Member, present
MD
Councillor Michael de WhalleyCommittee Member, present
TD
Councillor Tom de WintonCommittee Member, present
PD
Councillor Pallavi DevulapalliCommittee Member, present
MD
Michelle DreweryCouncil Staff, expected

All 33 on the meeting page

On this subject at King's Lynn and West Norfolk

Search all
  1. Decisions on ApplicationsThis decision
  2. Decisions on ApplicationsRefused
  3. Decisions on ApplicationsRefused
  4. Decisions on ApplicationsRefused
  5. Decisions on ApplicationsRefused
  6. Decisions on ApplicationsRefused

More from King's Lynn and West Norfolk Planning Committee

All decisions
MeetingDecisionOutcome
5 Oct 2026 PC47That the applications be determined as set out at (i) – (ii) below, where appropriate to the conditions and reasons o... Refused Open
5 Oct 2026 PC48That the report be amended and re-circulated. Decided Open
7 Sep 2026 PC37That the applications be determined as set out at ( i ) – (iv) below, where appropriate to the conditions and reasons... Refused Open
7 Sep 2026 PC38(1) That the report be noted. (2) That a breakdown of enforcement cases showing their start dates be circulated so Me... Noted Open
7 Sep 2026 PC39That the reports be noted. Noted Open