The Board asked officers to liaise with Norfolk County Council so that updates and a timetable could be made available to Councillors so that they could answer resident queries relating to the scheme. 3G Pitch The previous planning application for this had been withdrawn and work was ongoing to move the scheme forward. The Board discussed if the 3G Pitch should be considered as a Major Project and agreed that it should be removed from the list of current projects. 1. Officers to provide an update ... view the full minutes text for item 8.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
NORA EZ Development of Spec Units - Phase 1 Project P-21.03a Highlight Report NORA EZ Project Development of Project Mark Fuller/Jason Project Matthew Report covers December 23 & Name: Spec Units - Manager: Richardson Sponsor: Henry period of: January 24 Phase 1 Lead RG Carter Capital Code: C5002 Client Dept: - Designer: Cost Aecom Consultant: Project Code: P-21.03a End User (if applicable: - Contractor on RG Carter Site:
Management Summary 1. Overall 2.1 Risks 2.2. Issues 3. Financials 4. Timelines 5. Resources Status This Report A A A A R G
Last Report A A A A R G
Project Definition Project Stage: Phase 1 – RIBA 5 (awaiting utility connections and commissioning to allow handover) Objectives: Development of 4 units on the Nar Ouse Business Park offering a mix of light industrial and office spaces as per planning permission. Scope: The project will deliver modern speculative units for the Enterprise Zone portfolio as below: 2no semi-detached offices, offering up to 8 office suites (Plot A1) 2no light industrial semi detached units (Plot A2) Tenant fit out (Plot A1)
1. Overall Status (high-level summary) Overall status is Amber as timelines and issues are being managed, despite the points noted. Delays to handover due to infrastructure delivery and installation of utilities Financial early warning for costs associated with delayed handover Tenant fit out Plot A1 works essentially complete pending tenant sign off and snagging
1.1Decisions required by the Officer Major Projects Board No decisions required at this time
1.2Achievements during this period Tenant fit out Plot A1 works essentially complete pending tenant sign off and snagging Remaining works on hold pending infrastructure contract and service connections
2. Risks and Issues
2.1Key Risks [all red and increasing amber] A risk is something that may happen Risk Risk Title Description RAG Risk Mitigation Dated Comments ID Status Category (2/6) Continued delay Regular co-ordination Phase 1 Programme / 01.02.24 Utility connections 2/6 to handover of A meetings between Utilities Financial delayed - completion 15.04.24 Phase 1 units due Utility Consultant / NCC to utility team to progress connection infrastructure contract delays. and utility install 01.02.24 Fit out essentially Fit out contract complete pending tenant sign off and handover to Plot A1 Actively managing and and snagging - occupation meet incoming 6/6 Tenant A Programme engaged with incoming cannot take place until units tenants Fit Out tenant. formally handed over April / May requirements and 2024. Meeting scheduled with time constraints. incoming tenant 26.02.24.
2.2Key Issues [all red and increasing amber] An issue is something that has happened Issue Issue Description RAG Issue Type Resolution Plan Dated Comments ID Title Status (1/1) 01.02.24 Outstanding issues Delay in AWS sign Active engagement being closed off – AWS in Phase 1 off impacting Programme / and dialogue with 1/1 A receipt of all information and Utilities infrastructure financial AWS to secure responses – awaiting AWS delivery and utilities approvals response. 01.02.24 RGC concluded their investigations – BCKLWN appointed third party to RGC undertook During period of undertake independent review internal investigation Attenuati heavy rainfall which wasn’t conclusive - 1/2 A Programme – independent third on tanks attenuation tanks in requires further investigations by party engineer car park area lifted geotechnical engineer and appointed. programme of ground water monitoring looking to action asap. Note: further detail on Project Risks and Issues can be found in the Risks and Issues Log.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Member Major Projects Board at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.