CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Borough Council of King's Lynn and West Norfolk
Cabinet, Tuesday 4 February 2025 at 6.00pm

CAPITAL PROGRAMME AND RESOURCES 2024-2029

Approved Executive 6 papers

Cabinet approved this item on Tuesday 4 February 2025. Below is the council's own wording, with the papers it was decided on.

ItemCAB126

Resolved

RECOMMENDED : 1) That the amendments to capital schemes and resources for the 2024-2029 capital programme as detailed in the report be approved. 2) That new capital bids as set out in section 5, table 6 of the report, are to be funded from available capital resources and included in the capital programme 2024-2029 as detailed (subject to pending approval from SLT) of the report be approved. Reason for Decision To report amendments, rephasing and resources to the 2024-2029 Capital Programme. Cabinet chose not to exclude the press and public to discuss in detail the exempt elements as further detailed consideration of those would be made at a later date.
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Cabinet

REPORT TO CABINET

Partly Exempt Would any decisions proposed : Any Mandatory especially (a) Be entirely within Cabinet’s powers to decide NO affected (b) Need to be recommendations to Council YES Wards None (c) Be partly for recommendations to Council NO and partly within Cabinets powers – Lead Member: Portfolio Holder for Other Cabinet Members consulted: Finance Other Members consulted: E-mail:cllr.chris.morley@west- norfolk.gov.uk Lead Officer: Michelle Drewery Other Officers consulted: Management Team, E-mail: michelle.drewery@west- Service Managers norfolk.gov.uk Direct Dial: 01553 616432 Financial Policy/Personnel Statutory Equal Risk Implications Implications Implications Opportunities Management YES YES (incl S.17) Implications Implications NO NO YES If not for publication, the paragraph of Schedule 12A of the 1972 Local Government Act considered to justify that is 16-20.

Date of meeting: 4 February 2025

CAPITAL PROGRAMME AND RESOURCES 2024-2029

Summary This report:  revises the 2024/2025 projections for spending on the capital programme  sets out an estimate of capital resources that will be available for 2024-2029  details new capital bids that are recommended to be included in the capital programme for the period 2024-2029  outlines provisional figures for capital expenditure for the period 2024-2029

Recommendations It is recommended that: 1) Cabinet recommends to Council the amendments to capital schemes and resources for the 2024-2029 capital programme as detailed in the report. 2) Cabinet recommends to Council that new capital bids as set out in section 5 table 6, are to be funded from available capital resources and included in the capital programme 2024-2029 as detailed (subject to pending approval from SLT)

Reason for Decision To report amendments, rephasing and resources to the 2024-2029 Capital Programme. 1. Introduction

1.1This report presents the capital programme for the period 2024 to 2029. The capital programme forms part of the Council’s longer-term Financial Strategy and is updated as part of the overall budget and council tax setting process.

1.2The Council faces circumstances where capital resources to fund the capital programme continue to be limited. There are competing demands for use of these resources, including investment in projects which will deliver revenue savings.

1.3This report sets out a programme for 2024-2029 that can be delivered subject to the outcomes from revised forecasts reflecting continuing changes in costs and capital receipt levels. Certain capital funds come from grants and use of reserves, a large part of funds is to come from anticipated receipts from the Major Housing Development.

1.4The capital programme 2024-2029 includes a number of major housing projects, summarised in the table below. The delivery of new homes through this project provides essential funding to support the revenue budget, both through new homes bonus and increases to the council tax base.

Table 1 – Units to be delivered under Major Housing Schemes. Units in Current Capital Programme 2024-2029 Major Housing Lynnsport 1 96 Florence Fields 226 Salters Road 78 South End Road, Hunstanton 32 432

1.5The Council has set out to deliver as ambitious a capital programme as possible to meet its corporate priorities and to deliver new income streams and savings to support the revenue budget and will continue to aim to do so even in these difficult times.

2. Supporting Delivery of the Financial Strategy

2.1The Financial Strategy for 2024-2029 sets out the council’s latest proposed budget over the term of the plan. The Council has previously conducted a deep review of its earmarked reserves and capital programme to identify any savings. These reviews will continue in future years to identify any opportunities that may arise to help to meet savings targets and/or support the General Fund Reserve. Any revisions will be reported and updated accordingly.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TIERS CURRENT YEARAppendix 1 221 KB Download
PDF
OLD VIEW CURRENT YEARAppendix 2 227 KB Download
PDF
TIERS ALL YEARAppendix 3 233 KB Download
PDF
OLD VIEW ALL YEARAppendix 4 251 KB Download
PDF
TIERS FINANCE METHODAppendix 5 443 KB Download
PDF
CAPITAL PROGRAMME AND RESOURCES 2024-2029Report 891 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 22 attended
BA
Councillor Bal AnotaCommittee Member, apologies
JA
James ArrandaleCouncil Staff, expected
AB
Alexa BakerOfficer, expected
AB
Councillor Alistair BealesChair, present
KB
Kate BlakemoreOfficer, expected
EB
Emma BriersSecretary, expected
SC
Councillor Sandra CollopPresent Under standing Order 34, in attendance
JC
Jemma CurtisCouncil Staff, expected
MD
Councillor Michael de WhalleyCommittee Member, present
MD
Michelle DreweryOfficer, expected
OJ
Oliver JudgesCouncil Staff, expected
AK
Andy KingCouncil Staff, expected

All 22 on the meeting page

On this subject at King's Lynn and West Norfolk

Search all
  1. CAPITAL PROGRAMME AND RESOURCES 2024-2029This decision
  2. Capital programmeApproved
  3. Cabinet Report - Capital Programme and Resources 2025 - 2030Approved
  4. Cabinet Report- Capital Programme and Resources 2024-2029Approved
  5. Capital programme 2023-2028Approved
  6. Cabinet Report - Capital Programme and Resources 2023-2028Decided

More from King's Lynn and West Norfolk Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 ApologiesAn apology for absence was received from Councillor Moriarty. Decided Open
17 Nov 2026 MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... Agreed Open
17 Nov 2026 Urgent businessNone. Decided Open
17 Nov 2026 Declarations of interestNone. Decided Open
17 Nov 2026 Chair's correspondenceNone. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies