That the progress on the transfer of Alive West Norfolk back to the council be noted. Reason for Decision To provide assurance to the Shareholder Committee that the project is progressing on schedule and there are no significant risks to the transfer taking place on 1 April 2025. That the progress on the transfer of Alive West Norfolk back to the council be noted. Reason for Decision To provide assurance to the Shareholder Committee that the project is progressing on schedule and there are no significant risks to the transfer taking place on 1 April 2025.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
Any especially Mandatory/ Be entirely within Shareholder Committee powers to decide affected YES/NO Wards Discretionary / Need to be recommendations to Council YES/NO
Operational Is it a Key Decision YES/NO
Lead Member: Cllr Simon Ring Other Cabinet Members consulted: N/A E-mail: [email protected] Other Members consulted: N/A Lead Officer: Charlotte Marriott Other Officers consulted: N/A E-mail: charlotte.marriott@west- norfolk.gov.uk Direct Dial: Financial Policy/ Statutory Equality Impact Risk Environmental Implications Personnel Implications Assessment Management Considerations YES/NO Implications YES/NO YES/NO Implications YES/NO YES/NO If YES: Pre- YES/NO screening/ Full Assessment If not for publication, the paragraph(s) of Schedule 12A of the 1972 Local Government Act considered to justify that is (are) paragraph(s)
Date of meeting: 18 February 2025
Summary In July 2024, Cabinet resolved to transfer Alive West Norfolk (AWN) from a wholly owned Local Authority Company to an in-house function of the council. Following this decision Officers began the work required to ensure an efficient and effective transfer of services was realised by 1 April 2025.
Appendix A provides the Shareholder Committee with a high-level summary of the project work that has taken place to date.
Recommendation That the Shareholder Committee note the progress on the transfer of Alive West Norfolk back to the council.
Reason for Decision To provide assurance to the Shareholder Committee that the project is progressing on schedule and there are no significant risks to the transfer taking place on 1 April 2025. Shareholder Committee Report – 18 February 2025 – Appendix A
Project Highlight Report Project Manager Charlotte Marriott Shareholder Committee meeting 13 February 2025 Time 14.00-17.00 date
1. Purpose
1.1To update the Shareholder Committee on the progress that has been made towards transferring AWN from a wholly owned Local Authority Company to an in-house function of the council, following the decision made by Cabinet in July 2024.
1.2This report provides a high-level summary of the project activity that has taken place since the Cabinet decision in July 2024.
2. Overall Status – High-level Summary
2.1Following the decision, work began quickly to identify key project workstreams, Lead Officers and project governance arrangements. This included the creation of the Project Working Group and Project Board, along with relevant Terms of Reference for each. A detailed project plan was generated which details key actions, deadlines and responsible Officers for each.
2.2The key project workstreams are: 2.2.1 Structure and position 2.2.2 Finance 2.2.3 Personnel 2.2.4 Property 2.2.5 ICT 2.2.6 Legal and Governance 2.2.7 AWN
2.2The Exit Management Plan (EMP), as per Schedule 6 of the Management Agreement, was drafted. The EMP sets out the agreement between the council and AWN on how the transfer of services will happen. It outlines key processes and actions required to ensure the transfer is successful and includes information on the following areas: 2.2.1 Termination of the Management Agreement 2.2.2 Key workstreams 2.2.3 Reporting (to the AWN Board) 2.2.4 Key milestones 2.2.5 Staff transfer arrangements (including TUPE) 2.2.6 Finance (including fees and charges process for 2025-26) 2.2.7 Data and information security 2.2.8 Assets, leases and contracts 2.2.9 Communication and stakeholder engagement 2.2.10 Risk management and contingency planning 2.2.11 Post-transfer period
2.3Key workstream update, as of 7 February 2025: Workstream RAG rating Personnel – Structure Legal and Finance including Property ICT AWN and Position Governance staff comms G G G G G G G Shareholder Committee Report – 18 February 2025 – Appendix A
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Shareholder Committee at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.