ItemPC114:
Resolved
That the recommendation contained within the report be approved subject to: 1. To complete all S106 agreements (Framework Part A, Part B and Site Specific 106) and issue the decision by 5.15pm on 4 th April 2025. If this timescale is not met, the application be referred back to Planning Committee on 7 th April 2025. 2. In the exceptional circumstance where the individual landowner specified in the report and shown on the attached plan, is not able to enter into the Framework Part B and Site Specific S106 within the required timescale, to issue the permission and impose an additional condition which restricts development commencing on any part of the application site until the legal agreements have been entered into in relation to that land so that all the necessary land within the application site is bound.