Riverfront and Custom House R&D Update Jemma Curtis and Abigail Rawlings Background, scope at start of RIBA 3 • Rejuvenation of the Custom House, to provide a flexible accessible space for hospitality, meetings and exhibitions etc • Remediation of the Devils Alley site with a flexible public realm space to draw footfall to this end of the riverfront including dry side facilities. • Enhancements to public realm and utilities in King’s Staithe Square, to facilitate events and flexible use. • Development of a cultural events programme to supplement the major town centre events to draw regular footfall to the Riverfront and create a new town quarter. Work to date • Planning application for Devil’s Alley scheme submitted • Designs for Custom House to RIBA 3, 3 rounds of pre application consultation. Riverfront- change in project scope • Planning process for the public realm at Devil’s Alley highlighted some areas that needed further design review. • KLTDB funding timeframe did not allow for design review. • Town Board agreed to pause the Devil’s Alley element of the project. Dryside facilities not affected by pause. Riverfront- Devil’s Alley next steps • Pause project & transfer to LTPFT for expanded scope. • Explore further connection to South Quay and Southgates regeneration areas. • Work with local communities and residents to design the public realm space. • £2M funding reallocated to St George’s Guildhall & Creative Hub. Project Adjustment Request to be submitted May 2025. Next steps Dryside facilities Custom House • Pre Application feedback from Statuary Bodies considered that internal and external building modifications could not be justified in archaeological terms.
• New design team progressing plans for core accessibility improvements (lift, toilets) to support building use with minimal loss of historic fabric.
• New Business Plan and Economic Case work to confirm building uses, preferred option agreed. Programme • April / May: Procurement of team / mobilisation
• May: Commence Dryside Stage 4 (6-8 weeks), Commence CH Stage 3 and submission to Planning (4-6 weeks)
• July: Custom House Stage 4 development (6-8 weeks)
• August: Dryside Stage 4 tender release
• September: Custom House Stage 4 tender release
• September: Dryside tender returns
• October: Custom House tender returns
• November: Dryside Stage 5 construction (Nov ‘25-Apr ‘26 completion)
• December: Custom House Stage 5 construction (Dec ‘25-Oct‘26 completion)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
R&D Riverfront Update May 2025 :Report | 578 KB | DownloadRead as text |
PDF |
Riverfront and Custom House Update and Highlight ReportReport | 825 KB | Download |
Follow Regeneration and Development Panel at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Sep 2026 | RD26The minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 30 Sep 2026 | RD32The Panel’s Work Programme and the Forward Decisions List were noted. | Noted | Open |
| 30 Sep 2026 | RD34That under Section 100(A)(4) of the Local Government Act, 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 30 Sep 2026 | RD35That the Regeneration and Development Panel support the recommendations to Cabinet as included in the agenda. | Decided | Open |
| 22 Jul 2026 | RD14The minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.