Resolved
The minutes from the previous meeting were agreed as a correct record.
Member Major Projects Board agreed this item on Monday 12 May 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The minutes from the previous meeting were agreed as a correct record.
BOROUGH COUNCIL OF KING’S LYNN & WEST NORFOLK
MEMBER MAJOR PROJECTS BOARD
Minutes from the Meeting of the Member Major Projects Board held on Monday, 11th November, 2024 at 9.30 am in the Council Chamber, Town Hall, Saturday Market Place, King's Lynn PE30 5DQ
PRESENT: Councillor A Beales (Chair) Councillors R Blunt, B Long, J Moriarty, C Morley, S Ring and A Ware
Due to technical difficulties and further to consultation with the Monitoring Officer, the Chair proposed, and the Board agreed to continue with the meeting. The Member Major Projects Board commenced at 10:10am and was not streamed live on YouTube or recorded.
The Board held two minutes silence at 11:00am for Remembrance Day.
1 APOLOGIES
There were no apologies for absence.
2 MINUTES
RESOLVED: The minutes from the previous meeting were agreed as a correct record.
3 DECLARATION OF INTEREST
Councillor Ware declared she was a Board Member for West Norfolk Housing Company and West Norfolk Properties Limited.
4 URGENT BUSINESS UNDER STANDING ORDER 7
There was no urgent business under Standing Order 7.
5 MEMBERS PRESENT PURSUANT TO STANDING ORDER 34
Councillor de Whalley was present under Standing Order 34.
6 CHAIR'S CORRESPONDENCE
There was none.
7 STANDING ITEM: ACTION LOG
The Board had no comments or questions on the Action Log. 2
8 STANDING ITEM: PROJECT HIGHLIGHTS REPORT INCLUDING THE OVERVIEW REPORT
The Executive Director presented the Highlight Reports, starting with the overview report. He highlighted to the Board from the overview report that the NORA Enterprise Zone was rated red due to the overspend due to the delays. He outlined there were 7 projects rated amber and 6 rated green. He brought to the Board’s attention 3 projects where the ratings had moved to amber.
He explained to the Board the Southgates STARS project had been delayed with Active Travel England assessing the business case on behalf of the Dept for Transport. He added there was a site visit on the 5th June 2024 which Active Travel England had provided improvements to the scheme.
Under Standing Order 34, Councillor de Whalley questioned if the phosphor Gypsum removal had impacted the delay.
Councillor Morley commented generally on the capital expenditure across the capital programme, of which approximately one third of forecasted spend had been spent which was significantly lower than expected at the start of the financial year.
Councillor Long commented he felt the Southgates STARS project should have been rated at red.
NORA EZ Infrastructure
The Executive Director introduced the project and highlighted the financial report was red based on Norfolk County Council overspend due to the continued delays in completing the project.
Th Assistant Director of Property and Projects provided further detail to the Board and explained a substantial amount of work had been completed however there were delays relating to Anglian Water signing off the design of the highway works and how they related to the drainage, and other delays with UK Power Networks in respect of electricity supplies. He advised the work north of the development was paused and will resume once negotiations in respect of the overspend had been resolved.
The Assistant Director of Property and Projects responded to Councillor de Whalley’s earlier question in respect of contamination and explained there were overall contamination issues. Within the Contaminated Land Method Statement there had been agreed ways in which to deal with contamination on site, for example, Phosphor Gypsum previously was allowed to be used as part of the fill material beneath road infrastructure however the Environment Agency had 3
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 340 KB | DownloadRead as text |
Follow Member Major Projects Board at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Nov 2026 | MinutesThe minutes from the previous meeting were agreed as a correct record. | Agreed | Open |
| 4 Nov 2026 | Exclusion of Press and PublicThat under Section 100(A)(4) of the Local Government Act, 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 9 Oct 2026 | MinutesThe minutes from the previous meeting were agreed as a correct record. | Agreed | Open |
| 9 Oct 2026 | Standing Item: Action LogIt was agreed that the balance between maintaining effective oversight and avoiding an overly congested agenda would ... | Agreed | Open |
| 9 Oct 2026 | Standing Item: Project Highlight Reports including the Overview ReportIt was agreed that the most appropriate route for future reporting and oversight would be considered following the up... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.