Resolved
The Panel thanked the Principal Project Officer for the presentation and noted the update.
Corporate Performance Panel noted this item on Wednesday 3 September 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Panel thanked the Principal Project Officer for the presentation and noted the update.
Corporate Performance Panel Major Housing Review Lookback from 2015 to Today
James Grant Clarifications and Exclusions • High level oversight of programme and its management
• Not specific, in depth performance review of individual projects – this is covered by the authorities formal “Post Project Review” process, presented to Member Major Projects Board
• Does not include Nora 1, 2 and 3 – delivered under different relationships (162 Units)
• Salters Road included within completed projects as works largely completed – however some works are outstanding, so performance is projected.
• Future CPP or R&D meeting may scrutinise more specific items following this presentation where needed Key Aims • Boost housebuilding in West Norfolk (4-5 years) • Develop publicly-owned, previously undeveloped and challenging land • Stimulate local economy • Generate Council return • Improve local facilities • Leveraged Homes England's Accelerated Construction Programme (ACP) funding • Target: 1,000 properties delivered (2015-2027) • Build Market Leading – High Quality Housing Difficult places at difficult times • Poor Ground Conditions • Low Housing Values • Areas other developers where not interested
• Post 2008 Financial Crash • Throughout Covid • Housing Market Contraction Governance • Managed by Corporate Projects Team • Regeneration, Housing & Place • Project Team > James Grant > Duncan Hall > Kate Blakemore • Portfolio Holder – Cllr Beales • Quarterly Highlight Reports • Assurance provided by Officer and Members Major Project Boards
• Governance Under Review • Programme Board • Delegated Authority • Agile Decision Making (in accordance with contractual requirements) Who are Lovell Partnerships Ltd • Part of Morgan Sindall Group plc: A major UK construction and regeneration group. • Leading Partnership Housing Provider: Specialises in delivering housing through collaboration. • Comprehensive Services: Builds, refurbishes, regenerates, and maintains homes across the UK. • Focus Areas: Includes new‐build, affordable, build‐to‐rent, open market, refurbishment, later living, and strategic land. • Established Expertise: Over 50 years' experience in UK partnership housing. • Nationwide Presence: Regional offices across England, Scotland, and Wales. • Strong Partner Relationships: Works closely with local authorities, housing associations, etc, Lovel Partnership • Appointed Via Competitive Negotiation Process • Contractual Framework • Two‐tiered structure governs Council and Lovell partnership. • 1. Development Management Agreement (DMA): • Overarching document defining partnership structure and governance. • Crucial for pre‐construction phases and strategic framework. • 2. PPC2000 Contract: • Used for each individual project. • Cost‐plus basis with a profit‐share mechanism. • Incentivises Lovell to manage costs efficiently and maximize sales. Project Process DMA – Governs LPL / BCKLWN Relationship over all schemes PPC 2000 Contract or BCKLWN reviews and agrees DMA spend JCT Major Works
Quarterly Adjudication Post Project Pre Planning Post Planning Detailed Feasibility Design Adjudication Contract Review / Appraisal Appraisal Design (Commercial Profit Share Presentation)
Project Commencement PLANNING COONSET
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update and History of the Major Housing Projects and ProgrammeReport | 47 pages | DownloadRead as text |
Follow Corporate Performance Panel at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Appointment of Vice - Chair for the MeetingCouncillor Spikings was appointed Vice – Chair for the meeting. | Decided | Open |
| 10 Nov 2026 | MinutesThe minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 10 Nov 2026 | Cabinet Report - Corporate Performance Monitoring Quarter 2The Panel supported the recommendations to Cabinet. Cabinet Resolves to: 1. To review the Performance Management Repo... | Decided | Open |
| 10 Nov 2026 | Cabinet Report – Council Tax Support Scheme for Working Age People for 2027/2028The Panel supported the recommendations to Cabinet then Council. Recommendation to Full Council: That the draft Counc... | Agreed | Open |
| 10 Nov 2026 | Cabinet Report - Council Tax Discounts, Levies and Premiums for Empty Properties and Second Homes for 2027/2028The Panel supported the recommendations to Cabinet then Council. Recommendation to Full Council: The following discou... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.