Resolved
The minutes from the previous meeting were agreed as a correct record.
Member Major Projects Board agreed this item on Wednesday 8 October 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The minutes from the previous meeting were agreed as a correct record.
BOROUGH COUNCIL OF KING’S LYNN & WEST NORFOLK
MEMBER MAJOR PROJECTS BOARD
Minutes from the Meeting of the Member Major Projects Board held on Monday, 12th May, 2025 at 9.30 am in the Council Chamber, Town Hall, Saturday Market Place, King's Lynn PE30 5DQ
PRESENT: Councillor A Beales (Chair), R Blunt, A Kemp, B Long, C Morley, S Ring (Vice-Chair) and Ware
1 APOLOGIES
An apology of absence was received from Councillor J Moriarty.
2 MINUTES
Councillor Beales commented regarding Councillor Blunt’s previous query on whether it was the Borough Council or Norfolk County Council who would be the planning authority for the STARS scheme and confirmed that Officers have not yet confirmed this.
RESOLVED: The minutes from the previous meeting were agreed as a correct record.
3 DECLARATION OF INTEREST
There were no declarations of interest.
4 URGENT BUSINESS UNDER STANDING ORDER 7
There was no urgent business under Standing Order 7.
5 MEMBERS PRESENT PURSUANT TO STANDING ORDER 34
Councillor A Kemp and Councillor A Ware were present under Standing Order 34.
6 CHAIR'S CORRESPONDENCE
There was none.
7 STANDING ITEM: ACTION LOG
Councillor Morley asked if there was any progress on the lease of the Custom House. Councillor Ring advised he would raise this with the Interim Assistant Director for Property and Projects. 2
The Board had no further comments or questions on the Action Log
8 STANDING ITEM: PROJECT HIGHLIGHTS REPORT INCLUDING THE OVERVIEW REPORT
Click here to view the recording of the item on YouTube.
EZ NORA Infrastructure
The Assistant Director for Regeneration, Housing and Place highlighted to Board a significant overspend from Norfolk County Council. He added most of the work was completed however minor works were outstanding.
Councillor Ring sought clarification on the travel hub to be built as planned.
The Assistant Director for Regeneration, Housing and Place confirmed the final report had not yet been received however it was positive as there was concern this aspect of the project was jeopardized.
Councillor Ring questioned further if the active travel hub was to go ahead, would this fit the Neighbourhood Board time frames for spending.
The Assistant Director for Regeneration, Housing and Place confirmed it would fit the time frame and requirements of the Neighbourhood Board to be in contract by March 2026, not to have spent the money by this date. He added the timeline was tight and therefore a risk.
Councillor Long raised a concern of the access road being gated and questioned if there were any future plans for this to be opened to allow access for fire emergency vehicles to access Nar Ouse Way and the A47.
The Assistant Director for Regeneration, Housing and Place advised he was unable to confirm but would raise with Norfolk County Council.
Under Standing Order 34, Councillor Kemp commented discussions had been had regarding this matter and added this would be useful for fire emergency vehicles.
Parkway (Florence Fields)
The Assistant Director for Regeneration, Housing and Place advised there had been good progress however sales slower than anticipated. He advised arrangements were being reviewed and housing research had been conducted to identify prospective purchasers. 3
The Chair, Councillor Beales highlighted site progress was going well. The deputy mayor had recently undertaken a site visit who was particularly interested in the environmental aspects. The Chair confirmed that a site visit for members would be arranged and mentioned that the show home showed the modern construction methods in use, in clear and easy to understand detail. He referenced the projected 55% saving in energy costs. He brought to the Board’s attention work going on to enable information to be more accessible to members without compromising commercial sensitivity.
Councillor Ring commented the housing research reinforced the reason for building the developments and who the interested and prospective purchasers are.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 11 pages | DownloadRead as text |
Follow Member Major Projects Board at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Nov 2026 | MinutesThe minutes from the previous meeting were agreed as a correct record. | Agreed | Open |
| 4 Nov 2026 | Exclusion of Press and PublicThat under Section 100(A)(4) of the Local Government Act, 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 9 Oct 2026 | MinutesThe minutes from the previous meeting were agreed as a correct record. | Agreed | Open |
| 9 Oct 2026 | Standing Item: Action LogIt was agreed that the balance between maintaining effective oversight and avoiding an overly congested agenda would ... | Agreed | Open |
| 9 Oct 2026 | Standing Item: Project Highlight Reports including the Overview ReportIt was agreed that the most appropriate route for future reporting and oversight would be considered following the up... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.