Refused Planning 6 papers

AI summaryKing's Lynn and West Norfolk planners recommend approving five homes in Docking, including one affordable bungalow, subject to a legal agreement on affordable housing and a GIRAMS payment.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeRefusedSubject to completion of legal agreement within four months
MoneyS106 requiredAffordable housing and GIRAMS tariff; CIL also applies
What happens nextComplete s106 in 4 monthsOr delegated refusal if no reasonable progress
Who it affectsNot stated

What was decided

Officers recommend approving the application subject to a Section 106 agreement to secure one affordable rental dwelling and a GIRAMS payment, with delegated authority to the Assistant Director to complete the agreement or refuse if no reasonable progress is made within four months. Report P15, P16, P214, P269

The scheme was reduced from six to five dwellings during consideration, bringing the total using the private access to nine, the maximum allowed under Norfolk County Council highways policy. Report P11, P73

Why

The site adjoins the Docking development boundary and is treated as a windfall site that rounds off the settlement, consistent with Policy LP02 of the Local Plan and paragraph 83 of the NPPF. Report P26, P136, P137, P142

The Conservation Officer, Local Highway Authority, arboriculturist, ecologist and Strategic Housing raised no objection, and officers considered the foul drainage objection from Anglian Water was not supported by sufficient evidence to refuse the scheme. Report P72, P88, P96, P98, P101, P174, P177

Conditions and a Section 106 agreement address affordable housing, GIRAMS, drainage, landscape, trees, archaeology, highway safety, noise, air source heat pumps and biodiversity net gain. Report P214, P217, P218, P262, P270

What happens next

Draft and complete the Section 106 legal agreement within four months of the committee resolution, or the application is refused under delegated authority for failure to secure affordable housing. Report P15, P16, P269

Impose the twenty conditions set out in the recommendation, including a three-year time limit, plans compliance, archaeology, tree protection, landscaping, surface water drainage, acoustic fencing, air source heat pump details and highway works. Report P217, P218, P260, P267

The money

  • 1 x 3 bed 5 person bungalow On-site affordable rental unit required by Policy LP28 Report P97, P181, P182
  • 20% provision Affordable housing requirement on sites of five or more dwellings in Docking Report P181

Options considered

  • Chosen: Approve subject to Section 106 securing affordable housing and GIRAMS. Site adjoins development boundary, accords with Policy LP02 windfall criteria, affordable unit and conditions address key impacts Report P15, P211, P215
  • Chosen: Refuse if Section 106 not completed within four months. Failure to secure affordable housing in line with Policy LP28 Report P16, P269
  • Rejected: Refuse on Anglian Water grounds due to lack of capacity at Heacham Water Recycling Centre. Officers found the response lacked detailed evidence of specific harm; Section 106 Water Industry Act right to connect applies; small scale development Report P174, P176, P177, P178

Implications

  • Legal: A Section 106 agreement must be completed within four months to secure the affordable rental unit transferred to a registered provider at no public subsidy, and the GIRAMS payment; otherwise the application is refused under delegated authority. Report P15, P16, P97, P184, P214, P269
  • Equalities: The affordable unit is a three-bed, five-person bungalow meeting M4(2) accessibility standards and the Nationally Described Space Standard, addressing older residents' and accessible housing needs under Policy LP29 and LP30. Report P22, P28, P29, P97
  • Climate: Biodiversity net gain of 3.04 area and 1.65 hedgerow units is to be delivered through offsite Habitat Bank credits, secured by condition; air source heat pumps are specified, subject to a condition on sound levels. Report P99, P100, P199, P267
  • Financial: Community Infrastructure Levy will apply alongside the Section 106 contributions; one condition secures contributions towards off-site highway improvement works. Report P139, P255, P257
  • Risk: Conditions require an acoustic fence along the access, archaeological investigation, tree protection, unexpected contamination reporting, sustainable drainage and visibility splays to address identified impacts. Report P222, P232, P243, P251, P260, P262

Who and where

  • Residents of Docking, including neighbours on Sandy Lane and along the access drive Report P44, P107, P108
  • Anglian Water as sewerage undertaker for the area Report P45, P48, P51
  • Docking Parish Council, which objected Report P43, P44
  • The applicant, Vello Ltd, a local housebuilder Report P3, P27
  • Future occupants of the one affordable rental bungalow and four open market bungalows Report P21, P22, P97

Timeline

  • 21/05/01: Previous permission 2/01/0340/F granted for four terraced dwellings on nearby land Report P41
  • 3 December 2025: Original target determination date for 25/01391/FM Report P5
  • 31/12/2025: Anglian Water reiterated its objection due to Heacham WRC capacity Report P46
  • 02 February 2026: Planning Committee date; recommendation is to approve subject to s106 Report P5, P14, P217
  • Within 4 months of committee resolution: Deadline to complete Section 106 or face delegated refusal Report P15, P16, P269
  • 27 February 2026: Extension of time expiry for determination Report P5

Plain English for the jargon

  • Section 106 (s106): A legal agreement under the Town and Country Planning Act 1990 used by councils to secure planning obligations such as affordable housing from developers.
  • GIRAMS: Green Infrastructure and Recreational Impact Avoidance and Mitigation Strategy, a Norfolk-wide tariff addressing recreational pressure on protected habitats.
  • Sui generis: A planning use class for activities that do not fall within any defined use class, considered on their own merits.
  • M4(2): Building regulation standard for accessible and adaptable dwellings, part of Part M optional requirements.
  • Biodiversity Net Gain (BNG): Development must deliver a measurable net improvement in biodiversity, often through offsite habitat bank credits.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPC93:

Resolved

That the applications be determined, as set out at ( i ) – (XXXX) below, where appropriate to the conditions and reasons or grounds of refusal, set out in the schedules signed by the Chair. (i) 25/01552/FM Denver: Land to the east of Ryston Road: Change of use of agricultural land to sui generis for secure dog walking: Tiggys Paddock Click here to view a recording of this item on You Tube The case officer introduced the report and explained that the application was for the change of use of approximately 1.04ha agricultural land to a secure dog walking (sui generis) use at land to the east of Ryston End in Denver. The site was located to the east of Ryston Road. The application site comprised of an existing access from Ryston Road and 1.04ha of agricultural land. The wider setting of the site encompassed agricultural land bound by woodland to the west, protected under a Tree Preservation Order (reference TPO/00085/W1) and trees along the north, east and south boundaries. Furthermore, Denver Footpath 21 was located along the south of the application site. The application had been referred to the Committee for determination at the request of Councillor Hodson. The case officer advised that there was a correction to Condition 2, which had been outlined in the correspondence received after the publication of the agenda. The Committee noted the key issues for consideration when determining the application, as set out in the report. The Committee raised concerns about noise impact on neighbouring properties and the effectiveness of proposed fencing and landscaping. Officers clarified that while landscaping would provide visual screening, it would not significantly attenuate noise, and management plans would be required to address potential nuisance. Conditions had been included to require further details on boundary treatments and landscaping, particularly along the southern boundary adjacent to the public footpath. Members discussed the risk of dogs jumping fences and the interaction between dogs on the field and those on the adjacent footpath. Officers confirmed that a two-metre-high stock fence with timber posts and mesh would be installed, and further details would be agreed through planning conditions. The management plan would also address operational aspects, including the number of dogs allowed on site at any one time. Concerns were also raised about dog waste and the potential for the field to become unpleasant. Officers explained that the applicant would require users to pick up after their dogs, and a waste company would be contracted to manage any missed waste. The Democratic Services Officer then carried out a roll call on the recommendation to approve the application and, after having been put to the vote, was carried (13 votes for and 1 abstention). That the application be approved as recommended subject to the ... view the full minutes text for item PC93:
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Planning Committee

AGENDA ITEM NO. 9/1 (b)

Parish: Docking

Proposal: Full Planning Application: Erection of 5 no. single storey dwellings, garages, vehicular/pedestrian access, landscaping, and associated infrastructure; together with change of use of parts of site to residential curtilages (for existing dwellings) Location: Land E of Bennet Mews S And W of Sandy Lane Sandy Lane Docking Norfolk Applicant: Vello Ltd.

Case No: 25/01391/FM (Full Application - Major Development)

Case Officer: Jack Ibbotson Date for Determination: 3 December 2025 Extension of Time Expiry Date: 27 February 2026

Reason for Referral to Planning Committee – Sifting Panel Referral.

Neighbourhood Plan: No - Docking Neighbourhood Plan has not yet been made although has been considered below as an emerging plan.

Case Summary

Full Planning permission is sought for the erection of five single storey dwellings together with change of use of parts of the site to residential curtilages (for existing dwellings) at land adjacent to, but outside of the development boundary of Docking.

The development would see four open market dwellings and one affordable dwelling constructed.

The proposal has been amended since its original submission from 6 dwellings to 5 dwellings. This would now result in total of 9 dwellings using the existing private access which is the maximum allowed under NCC Highways policy.

Key Issues

Principle of Development Design, Impact upon Heritage and Landscape Access and Highway Safety Impact upon Neighbour Amenity Flood Risk and Drainage Affordable Housing

Planning Committee 02 February 2026 25/01391/FM Recommendation

A. APPROVE - subject to completion of a s106 to secure Affordable Housing. If the agreement is not completed within 4 months of the committee resolution, but reasonable progress has been made, delegated authority is granted to the Assistant Director/Planning Control Manger to continue negotiation and complete the agreement and issue the decision.

B. If in the opinion of the Assistant Director/Planning Control Manager no reasonable progress is made to complete the legal agreement within 4 months of the date of the committee resolution, the application is REFUSED on the failure to secure Affordable Housing in line with Policy LP28 of the Local Plan.

THE APPLICATION

The application site is a field located to the north of Docking. The site would be accessed via an existing private drive located on the western section of Sandy Lane within close proximity to the junction with Station Road. The site adjoins Docking development boundary on the west and northern boundaries and more recent residential development runs along the eastern site boundary. The southern boundary of the site and field is an established hedgerow including hedgerow trees separating it to further agricultural land to the south. Docking Conservation Area is also located to the north and west of the site. There are a number of attractive unlisted heritage assets within close proximity of the site.

Full planning permission is sought for the erection of five single storey dwellings, which is an amendment from the original six dwelling proposal. The amendment has seen the site area reduced slightly to approximately 1.1 hectares and now includes the provision of a bin storage area within an area owned by the applicant to the side of the front garden of Hawthorns, Sandy Lane, close to the public highway. This bin storage area is proposed to be used on bin collection days. In addition, parts of the site are proposed to be changed from agricultural to garden curtilage of neighbouring properties. This would see the gardens of houses along the north and part of the west boundary expanded.

The site lies on an east-west axis. Access would be gained from Sandy Lane to the west, with the private access drive running along the northern portion of the site boundary to the east with five dwellings along the southern half of the site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25.01391.FM :Report 235 KB DownloadRead as text
PDF
25.01391.FM MAP 1 :Plan 482 KB Download
PDF
25.01391.FM MAP 2 :Plan 493 KB Download
PDF
25.01552.FM :Report 240 KB Download
PDF
25.01552.FM MAP 2 :Plan 568 KB Download
PDF
Decision on applicationsDecisions 475 KB Download

At this meeting

Whole meeting

Who was there

13 of 30 attended
BA
Councillor Bal AnotaCommittee Member, present
HA
Henry AnthonyCouncil Staff, expected
JA
James ArrandaleCouncil Staff, expected
TB
Councillor Thomas BarclayCommittee Member, present
KB
Kate BlakemoreOfficer, expected
RB
Councillor Richard BluntCommittee Member, present
FB
Councillor Francis BoneChair, present
EB
Emma BriersSecretary, expected
AB
Councillor Anthony BubbCommittee Member, present
MC
Martin ChisholmOfficer, expected
MD
Councillor Michael de WhalleyCommittee Member, present
TD
Councillor Tom de WintonCommittee Member, apologies

All 30 on the meeting page

More from King's Lynn and West Norfolk Planning Committee

All decisions
MeetingDecisionOutcome
5 Oct 2026 PC47That the applications be determined as set out at (i) – (ii) below, where appropriate to the conditions and reasons o... Refused Open
5 Oct 2026 PC48That the report be amended and re-circulated. Decided Open
7 Sep 2026 PC37That the applications be determined as set out at ( i ) – (iv) below, where appropriate to the conditions and reasons... Refused Open
7 Sep 2026 PC38(1) That the report be noted. (2) That a breakdown of enforcement cases showing their start dates be circulated so Me... Noted Open
7 Sep 2026 PC39That the reports be noted. Noted Open