Guildhall Project Update R&D 31st March 2026. Guildhall Project Update R&D 31st March 2026.
Governance Framework for Delivery Phase. The Guildhall project is now firmly in the delivery phase which requires a clear and coordinated governance structure to provide strategic oversight, critical decision-making support on operational, assurance and key outputs as the project moves towards launch and beyond that into the critical post opening period.
Five Workstreams have been identified that will drive the demands of the project.
1 - Construction Delivery & Contractor Management – Lead: Robin Lewis 2 - Stakeholder Engagement – Lead: Tim FitzHigham 3 - Engagement, Activities & Social Value – Lead: Duncan Hall / Tim FitzHigham 4 - Fundraising – Lead: Tim FitzHigham 5 - Site Operations & Business plan – Lead: Siobhan Cleeve Guildhall Project Update R&D 31st March 2026.
Agenda
1 - Construction Delivery (Site Activities, Programme, Budget.) 2 - Stakeholder Engagement 3 - Engagement, Activities & Social Value 4 - Fundraising 5 - Site Operations & Business plan
Progress Photo’s – covering the site Dec 2025 – March 2026. Workstream 1 - Construction Delivery
– Site Activities, Programme, Budget, Health & Safety.
Site Activities • Contract Signed – Messenger Construction Ltd (MCL). • Start on Site 24th Nov 2025 – Handover 30th June 2028. • Scaffold erection, asbestos removal and WC, site wide demolition started. • Party wall awards and specific Scaffold licenses for various locations. • Monthly Construction Progress Meetings Dec-February. • Contractor payments, procurement of 2nd Tier packages. • Immersive media consultant appointment to compliment Interpretation design. • Guildhall Roof Repair package of work has started (Historic England Funded). • Crown Post Truss. • Substation procurement. Programme – Update March 2026.
Main Contract. • Start 24th Nov 2025 • Planned Handover 30th June 2028
Post Handover • Operational fit out • Interpretation & Immersive Experience fit out. • Launch to the Public Summer/ early Autumn 2028. Budget & Cost - Headlines.
• £30.5m Budget – March 2026 Forecast - £30.5m. On budget.
• Post Contract Value Engineering workshops continue. Contractor (Messenger), Project Team continue to target c£250k of savings.
• Spend to date as of 28th February 2026 is £3.8m.
• Actuals primarily relate to professional and consulting costs, including Architect, Project Management, Quantity Surveyor, Archaeologist, Scaffolding License costs, and the first 3-4 months of Main Contractor costs at £0.7m to date.
• Funding of £12.5m is secured, and £2.5m Pride in Place (formerly PfN) awaiting final approval from MHCLG. This leaves a current balance of £15.5m of funding as approved by Full Council (July 25) to meet the project requirements. Work is well underway to find further funds to reduce the Borough’s financial commitment. Workstream 2 - Stakeholder Engagement
• Partners consistently updated and kept informed (National Trust, Historic England, Charitable Incorporated Organisation (the Charity), Norfolk Museum Service, Norfolk County Council, King’s Lynn Neighbourhood Board). • Talks given to local stakeholder groups (West Norfolk Archaeological Society, True's Yard). • Information submitted to Parliamentary APPG. • Further international partner organisations identified and meetings held with them. • Continuing meetings with other nationally recognised Shakespeare organisations. • Messaging and communication to stakeholders is in a good place, for example, the Anglia Water leak issue in King Street was handled well and within 60 minutes of becoming an issue. ACTIVITIES Over 10,000 children engaged Volunteers Workstream 3 - Engagement, Activities & Social Value
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Guildhall CH Project update R&D March 26: Final version 23.03.2026 :Report | 2.8 MB | DownloadRead as text |
PDF |
Guildhall UpdateReport | 450 KB | Download |
Follow Regeneration and Development Panel at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Sep 2026 | RD26The minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 30 Sep 2026 | RD32The Panel’s Work Programme and the Forward Decisions List were noted. | Noted | Open |
| 30 Sep 2026 | RD34That under Section 100(A)(4) of the Local Government Act, 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 30 Sep 2026 | RD35That the Regeneration and Development Panel support the recommendations to Cabinet as included in the agenda. | Decided | Open |
| 22 Jul 2026 | RD14The minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.