CIL Spending Panel, Monday 18 May 2026 at 10.00am

CIL Spending Panel Report - Review

Agreed Committee 4 papers

AI summaryKing's Lynn and West Norfolk CIL Spending Panel unanimously recommends £2.84 million for Hunstanton Coastal Defences to Cabinet, with debate over whether to reclassify the West Lynn Ferry application as essential.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedUnanimous on Hunstanton coastal defences
Money£2,840,000 CIL requestedHunstanton coastal defences bid only
What happens nextCabinet considerationRFCC DGiA bid Q3 2026 if confirmed
Who it affectsHunstanton residents and businesses522 homes and 105 businesses protected

What was decided

The Panel unanimously agreed to recommend the full £2.84 million request for the Hunstanton Coastal Defence Capital Works Project to Cabinet.

Councillor de Whalley, as Portfolio Holder, supported the West Lynn Ferry Infrastructure Improvements application and called it essential, with risks of service suspension if not funded.

Under Standing Order 34b, Councillor Heneghan argued the West Lynn Ferry application should be changed to essential status, citing the risk of service suspension without funding.

Why

Hunstanton coastal defences are end of life and need a major rebuild; 522 residential properties and 105 businesses rely on them for protection from coastal erosion and flooding. Report P5, P7

The £2.84m would form part of the council's 10% partnership contribution to secure a Regional Flood and Coastal Committee Defence Grant in Aid covering up to 90% of the £43.2m project. Report P5, P10

The West Lynn Ferry is positioned as sustainable transport that supports local housing allocations, the King's Lynn Master Plan, and reduces pressure on the Southgates and Pullover roundabouts. Report P27

What happens next

Cabinet will consider the Hunstanton coastal defences recommendation; an Outline Business Case will be prepared for the RFCC Defence Grant in Aid application in Q3 2026, with capital works expected to start Q3 2027 for about 24 months. Report P18

The West Lynn Ferry application, currently classed as 'Desirable' by CIL officers, is subject to a feasibility study due in early Q2 2026, with construction anticipated to finish in summer 2027. Report P42, P44, P40

The money

  • £2,840,000 CIL requested for Hunstanton Coastal Defences Capital Works Project Report P4, P20
  • £800,000 CIL requested for West Lynn Ferry Infrastructure Improvements Report P24, P43
  • £706,500 CIL requested for Guildhall and Creative Hub Public Realm Project Report P46, P65
  • £366,000 CIL requested for Hunstanton Cliff Top public convenience refurbishment Report P69, P85
  • £300,000 CIL requested for King's Lynn South Fire Station training infrastructure Report P89, P110
  • £100,000 CIL requested for Resort Recycling Bins Programme in Hunstanton (reduced from £160k by finance) Report P114, P131
  • £100,000 CIL requested for Riverfront Regeneration Custom House Interpretation Report P135, P155
  • £80,000 CIL requested for Lynnsport Changing and Toilet Facilities Report P159, P177

Options considered

  • Chosen: Fund Hunstanton Coastal Defences at full £2.84m CIL request. Unanimous Panel recommendation to Cabinet; coastal defences classed as essential by CIL officers Report P21
  • Rejected: Fund West Lynn Ferry at £800,000 CIL request. Application is classified as Desirable by CIL officers; a member amendment to reclassify as Essential was raised under Standing Order 34b Report P44
  • Rejected: Reclassify West Lynn Ferry as essential infrastructure. Raised by Cllr Heneghan under Standing Order 34b due to service suspension risk; full outcome not recorded in supplied text

Implications

  • Financial: Council will need additional funding beyond the £2.84m CIL to meet its 10% partnership contribution for the £43.2m coastal defence scheme; RFCC Defence Grant in Aid will cover up to 90% if successful. Report P5, P10, P12
  • Financial: The West Lynn Ferry project has a £800,000 funding shortfall not covered by the CIL request, hoped to come from the Borough Council and Norfolk County Council. Report P32, P34, P37
  • Risk: Service suspension risk identified for the West Lynn Ferry if CIL funding is not secured, prompting the Standing Order 34b challenge to reclassify the project.
  • Risk: Hunstanton coastal defences are end of life; failure to fund the partnership contribution could prevent the council from securing RFCC Defence Grant in Aid and leave 522 homes and 105 businesses at risk. Report P5, P7
  • Equalities: Lynnsport changing rooms and Downham Leisure inclusive changing modernisation aim to meet Part M of the Building Regulations and the Equality Act 2010 for disabled and older users. Report P166, P175
  • Climate: LED pitch lighting at Lynnsport is expected to save over five tonnes of CO2e per year and more than £8,000 per year in energy and maintenance. Report P184

Who and where

  • 522 residential properties and 105 businesses in Hunstanton protected by the coastal defences Report P7
  • West Lynn and King's Lynn residents and commuters using the ferry Report P27
  • Visitors and residents using Guildhall, Lynnsport, Custom House and Hunstanton public realm Report P47, P162, P136, P204
  • Norfolk Fire and Rescue Service crews based at King's Lynn South Report P92
  • King's Lynn and West Norfolk residents served by the new fire training infrastructure Report P108

Timeline

  • Q3 2026: Hunstanton coastal defences: RFCC Defence Grant in Aid application and planning/MMO Marine licence submissions Report P18
  • Q3 2027: Hunstanton coastal defence construction phase expected to start, lasting around 24 months Report P18
  • Late Mid 2025 to Summer 2027: West Lynn Ferry: feasibility stage now, with anticipated construction completion by Summer 2027 Report P38, P40
  • September 2026 to End March 2027: Lynnsport LED pitch lighting: tender launch, award and completion of works Report P197
  • Late 2026 to Early 2027: Lynnsport Changing and Toilet Facilities refurbishment to be delivered on site over 6 to 8 weeks Report P173, P174
  • April 2027: Hunstanton Resort Recycling Bins and Street Furniture refurbishment programmes targeted for completion Report P128, P217
  • August 2027 to June 2028: Guildhall and Creative Hub Public Realm works scheduled to start and finish Report P60

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure
  • RFCC DGiA: Regional Flood and Coastal Committee Defence Grant in Aid, central government flood defence funding
  • MMO: Marine Management Organisation, the regulator for marine licensing in England
  • RIBA Stage 1/2: Royal Institute of British Architects feasibility and preliminary design stages
  • Standing Order 34b: Council procedure rule allowing a member to challenge a recommendation and propose an amendment
  • GIA: Grant in Aid funding from the Regional Flood and Coastal Committee
  • Town Deal: Government town centre regeneration funding programme
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19

Resolved

The Panel unanimously agreed to recommend the full £2.84 million request for the Hunstanton Coastal Defence Capital Works Project to Cabinet. Application 2 - West Lynn Ferry – Infrastructure Improvements Councillor de Whalley, as the Portfolio Holder supported the application and highlighted the ferry was essential infrastructure. He highlighted relevant parts of the Local Plan and outlined the West Lynn Ferry supported sustainable transport, local housing allocations, and the King's Lynn Master Plan, with risks of service suspension if not funded. Under Standing Order 34b, Councillor Heneghan argued the application should be changed to essential and expressed the concerns of suspension of the service if funding was not secured. ... view the full minutes text for item 19.
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to CIL Spending Panel

CIL Strategic Project Funding

Contents CIL Strategic Project Funding................................................................................................ 1 1. Hunstanton Coastal Defences Capital Works Project ........................................................ 2 £2,840,000 ........................................................................................................................ 2 2. West Lynn Ferry - Infrastructure Improvements................................................................. 6 £800,000 ........................................................................................................................... 6 3. The Guildhall and Creative Hub Public Realm Project. .................................................... 10 £706,500 ......................................................................................................................... 10 4. Redesign and refurbishment of Cliff Top public convenience facilities in Hunstanton....... 15 £366,000 ......................................................................................................................... 15 5. Technical Training Infrastructure – King’s Lynn South Fire Station .................................. 18 £300,000 ......................................................................................................................... 18 6. Resort Recycling Bins Programme.................................................................................. 22 £100,000 ......................................................................................................................... 22 7. Riverfront Regeneration - Custom House Interpretation .................................................. 26 £100,000 ......................................................................................................................... 26 8. Enhancement of Lynnsport Changing & Toilet Facilities, Including Accessible Provision . 32 £80,000 ........................................................................................................................... 32 9. LED Lighting Upgrades (Lynnsport Sports Pitches) ......................................................... 36 £60,000.00 ...................................................................................................................... 36 10. Refurbishment & painting of Street Furniture to Enhance Public Realm in Hunstanton . 39 £56,000 ........................................................................................................................... 39 11. Lynnsport Sports Barn and Kaset Toilets ....................................................................... 42 £48,000 ........................................................................................................................... 42 12. Inclusive Changing Room Modernisation at Alive Downham Leisure............................. 46 £32,000.00 ...................................................................................................................... 46 13. Replacement of Beach Safety Signage ......................................................................... 49 £21,000 ........................................................................................................................... 49

1 1. Hunstanton Coastal Defences Capital Works Project Amount of CIL Funding Required This is the amount of CIL requested, not the overall total of the project

£2,840,000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
03_Appendix 1_Project 22 Supporting DocsAppendix 701 KB Download
PDF
04_Appendix 2_CIL Spending StrategyAppendix 299 KB Download
PDF
05_Appendix 3_CIL Policy DocumentAppendix 194 KB Download
PDF
CIL Spending Panel Report: ReviewReport 440 KB DownloadRead as text

At this meeting

Whole meeting
12Notes of the previous meetingOn the agenda 18Chair's introductionOn the agenda
19CIL Spending Panel Report - ReviewThis decision

Who was there

11 of 11 attended
RB
Councillor Richard BluntCommittee Member, present
MD
Councillor Michael de WhalleyCommittee Member, present
TD
Councillor Tom de WintonPresent Under standing Order 34, present
MD
Michelle DreweryOfficer, present, as expected, virtual
AD
Amanda DriverOfficer, present
DH
Councillor Deborah HeneghanCommittee Member, present, as expected, virtual
HH
Honor HowellCouncil Staff, present, as expected, virtual
SL
Councillor Susanne LinternPresent Under standing Order 34, present
JM
Councillor Jim MoriartyChair, present
CM
Councillor Chris MorleyPresent Under standing Order 34, present
SS
Councillor Samantha SandellCommittee Member, present

On this subject at King's Lynn and West Norfolk

Search all
  1. CIL Spending Panel Report - ReviewThis decision
  2. Community infrastructure levy (cil) - funding policy and spending strategyApproved
  3. CIL Spending Panel Report- Applications and Officer RecommendationsAgreed
  4. CIL Spending Panel Report - Applications and officer recommendationsAgreed
  5. CIL Spending Panel Report - Applications and officer recommendationsAgreed
  6. Community infrastructure levy (cil) governance and spending document 2024 and annual infrastructure funding listAgreed

More from King's Lynn and West Norfolk CIL Spending Panel

All decisions
MeetingDecisionOutcome
22 Jun 2026 Review Funding applications and allocate funding to community projectsAGREED: The Panel unanimously approved the application for £19,983.73. 2 The Burnhams Tennis Club – Resurfacing proje... Agreed Open
9 Sep 2025 Local Infrastructure application form and validationAGREED: That the Panel was content with the proposed application form and validation criteria. Setting up an Officer ... Agreed Open
17 Feb 2025 CIL Spending Panel Report- Applications and Officer RecommendationsAGREED: That £29,850.40 be awarded. Sedgeford Parish Council – Sedgeford Village Hall Refurbishment - £7,700.00 reque... Agreed Open
16 Sep 2024 CIL Spending Panel Report - Applications and officer recommendationsAgreed : That Cabinet be recommended to approve the £67,023.18 28 Nordelph - river railings (£13,720 requested) Agree... Agreed Open
5 Mar 2024 CIL Spending Panel Report - Applications and officer recommendationsAGREED: The Panel agreed that the application be withdrawn. The Panel considered the applications received and determ... Agreed Open