AI summaryCabinet approved CIL funding for four infrastructure projects, cutting the Hunstanton Coastal Defences allocation by £53,557.02 to keep within the £4,252,442.98 funding envelope.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFunded four projects, reduced Hunstanton allocation
Money£4,252,442.98 availableShortfall of £53,557.02 addressed by Hunstanton cut
What happens nextSpending Panel to monitor deliveryDetailed design work still required
Who it affectsNot stated
What was decided
Cabinet approved Option 1, reducing the Hunstanton Coastal Defences Capital Works allocation from £2,840,000 to £2,786,442.98, a cut of £53,557.02. Report 4.6
The three remaining infrastructure projects receive their full recommended funding, keeping total spend within the £4,252,442.98 strategic CIL envelope. Report 4.5, 4.6, 5.1
The Regeneration and Development Panel had recommended Option 1 to Cabinet on 02.06.2026. Report 4.8
Why
The Spending Panel's recommendations exceeded the available CIL strategic funding by £53,557.02, so Cabinet had to choose how to close the gap. Report 4.2, 5.1
Reducing the Hunstanton allocation was judged low risk because detailed designs and external grant funding applications are still in progress. Report 4.6
The Council must ensure CIL spending complies with the Community Infrastructure Levy Regulations 2010 (as amended). Report 4.4, 9.1
What happens next
The four projects proceed with their confirmed CIL allocations as listed in Appendix 1. Report 4.6
Further work on detailed designs and external grant funding applications continues for the Hunstanton Coastal Defences project. Report 4.6
Spending on CIL will be monitored to ensure it is directed to improved infrastructure in the borough. Report 14.1
The money
£4,252,442.98 Total available 80% strategic CIL funding Report 4.5, 5.1
£53,557.02 Amount by which Spending Panel recommendations exceeded available funding Report 4.2, 5.1
£2,840,000 Original recommended allocation for Hunstanton Coastal Defences Report 4.6
£2,786,442.98 Revised allocation for Hunstanton Coastal Defences under Option 1 Report 4.6
£11,032.98 Balance that would have remained in the 80% CIL pot under Option 2 Report 4.7
Options considered
Chosen: Option 1: Reduce Hunstanton Coastal Defences allocation by £53,557.02, leaving other three projects fully funded. Low risk to the Hunstanton project at this stage; allows full funding of other projects including those reliant on match funding Report 4.6, 4.8
Rejected: Option 2: Top-slice all four projects proportionately (1.5% reduction) to capture the £53,557.02 shortfall. Risk to West Lynn Ferry and King's Lynn South Fire Station proposals, which rely on match funding from external sources Report 4.7
Implications
Financial: CIL receipts are ringfenced for qualifying infrastructure under the CIL Regulations 2010 (as amended); spending must stay within the £4,252,442.98 envelope. Report 4.4, 5.1, 9.1
Legal: All CIL expenditure and governance must conform to the relevant CIL regulations and local policies. Report 9.1
Equalities: Pre-screening Equality Impact Assessment completed; all projects expected to have a positive community impact and neutral impact on protected groups. Report 13.1, P37, P40
Climate: No specific climate change implications, though individual projects may have positive environmental impacts. Report 8.1
Risk: Monitoring of spending and delivery is important to ensure money is directed to improved infrastructure; the Hunstanton project carries limited risk from the reduction at this stage. Report 4.6, 14.1
Who and where
Residents and users of the four funded infrastructure projects in the borough, including Hunstanton, West Lynn, and King's Lynn South Report 4.6, 4.7
Project delivery teams for the Hunstanton Coastal Defences, West Lynn Ferry, and King's Lynn South Fire Station proposals Report 4.6, 4.7
Organisations providing match funding for the West Lynn Ferry and King's Lynn South Fire Station projects Report 4.7
Timeline
18.05.2026: Spending Panel meeting considered funding requests Report P33
02.06.2026: Regeneration and Development Panel recommended Option 1 to Cabinet Report 4.8, P33
23.07.2026: Cabinet approved Option 1 and the project list at Appendix 1
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge that local authorities can collect from developers on new building projects, ringfenced for infrastructure
Strategic allocation (80% pot): The portion of CIL receipts that the council can spend on strategic infrastructure priorities across the borough
Spending Panel: The council panel that reviews CIL funding requests and makes recommendations to Cabinet
R&D Panel: Regeneration and Development Panel, a council committee that also considered the CIL funding recommendations
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB27
Resolved
Cabinet considered the recommendations provided by the Spending Panel and allocated funding to Corporate Projects as set out in Option 1 and the attached project list at Appendix 1. REASON FOR DECISION: To ensure that CIL monies collected are being spent in accordance with CIL legislation and local policy on appropriate infrastructure projects and ensure spend is within the available funding envelope.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
REPORT TO CABINET DATE OF MEETING 23 July 2026 REPORT TITLE CIL Strategic Project Funding LEAD MEMBER Cllr James Moriarty LEAD OFFICER Amanda Driver, Senior CIL Officer CONSULTEES Officers, Hannah Wood-Handy, Stuart Ashworth, ELT, Spending Panel, R&D Panel WARDS AFFECTED All
KEY DECISION NO DECISION MAKER Cabinet IS THE REPORT OPEN OPEN OR EXEMPT
FINANCIAL IMPLICATIONS NO HR IMPLICATIONS NO POLICY IMPLICATIONS NO STATUTORY IMPLICATIONS NO RISK MANAGEMENT NO IMPLICATIONS ENVIRONMENTAL IMPLICATIONS NO EQUALITY IMPACT ASSESSMENT PRE-SCREEN COMPLETED COMPLETED
SUMMARY OF REPORT In line with the Community Infrastructure Levy (CIL) Spending Strategy and Policy approved by Cabinet in September 2025, 80% of the strategic CIL pot is to be allocated to corporate infrastructure projects aligned with Capital Programme tiers 1–3. For schemes requesting over £100,000, the CIL Spending Panel is required to make recommendations to Cabinet.
Following the Spending Panel meeting on 18 May 2026, five applications were put forward for Cabinet consideration. The total CIL funding available within the 80% allocation is £4,252,442.98, against which the Panel has recommended funding totalling £4,588,600.
However, since those recommendations were made, the request for funding for the Guildhall and Creative Hub Public Realm Project has been withdrawn, leaving four remaining projects. The total recommended funding is therefore £4,306,000 against the 80% allocation of £4,252,442.98, leaving a shortfall of £53,557.02.
Cabinet is therefore asked to consider the proposed allocations (set out in Appendix 1) and Options 1 and 2 below which are available to them, to ensure that spending is within the available funding envelope.
RECOMMENDATIONS Consider the recommendations provided by the Spending Panel and allocate CIL funding to Corporate Projects as set out in Option 1 and the attached project list at Appendix 1. REASON FOR DECISION To ensure that CIL monies collected are being spent in accordance with CIL legislation and local policy on appropriate infrastructure projects and ensure spend is within the available funding envelope.
CORPORATE STRATEGY How does this proposal support our Corporate Priorities Our priorities | Corporate Strategy 2023 - 2027 | Borough Council of King's Lynn & West Norfolk Promote growth All projects on the list will support this corporate priority and prosperity to directly, by increasing West Norfolk’s infrastructure benefit West Norfolk provision with safety & economic benefits. Protect our The Hunstanton Coastal Defences & Cliff Top Facilities Environment projects will support this priority. Efficient and Projects on the list will support this corporate priority, effective delivery of including the King’s Lynn South Fire Station & Cliff Top our services Facilities. Support our All projects on the list will support this corporate priority communities directly, by ensuring that communities have appropriate facilities & infrastructure available to them, particularly Hunstanton Coastal Defences & West Lynn Ferry.
REPORT DETAIL
1. Introduction
1.1The Borough Council of King’s Lynn & West Norfolk approved the introduction of the Community Infrastructure Levy (CIL) in December 2016 and began charging in February 2017. The levy is payable to the council by developers upon implementation of planning permissions. Within the borough, CIL is currently charged on residential and supermarket developments at a rate per square metre for schemes that deliver one or more new dwellings, or in excess of 100sqm of additional floorspace.
1.2CIL receipts must be spent in accordance with the Community Infrastructure Levy Regulations 2010 (as amended), specifically on ‘the provision, improvement, replacement, operation or maintenance of infrastructure to support the development of its area’.
1.3Following Cabinet approval of the CIL Spending Strategy and Policy in September 2025, all expenditure decisions are required to align with this agreed framework.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.