Refused Planning 6 papers

AI summaryBorough Council's Planning Committee approved an Active Travel Hub at the King's Lynn Enterprise Park: cycle hub, 236 car parking spaces, two new bus stops on Nar Ouse Way, in two phases.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeRefusedActive Travel Hub with 236 parking spaces and cycle hub building
MoneynullPart of £25 million Town Deal backed Active and Clean Connectivity project
What happens nextConditions to be metPlanning conditions on materials, landscaping, drainage, contamination
Who it affectsNot stated

What was decided

The Planning Committee approved application 25/01783/FM for the phased development of an Active Travel Hub on a 1.45 Ha site at the King's Lynn Enterprise Park, subject to conditions and reasons in the schedules signed by the Chair. Report P1, P3, P4

Phase 1 will deliver the cycle hub with WCs and changing facilities, 33 standard and 4 accessible parking bays, 3 standard and 3 accessible EV bays, a footpath link to Nar Ouse Way and two new bus stops, covering 0.76 Ha. Report P9, P10

Phase 2 will add an internal bus route, 201 standard parking bays, 12 motorcycle spaces, 11 accessible bays, 20 standard and 4 accessible EV bays, covering 0.69 Ha. Report P11, P12

Why

Officers considered the principle acceptable because the scheme supports active and sustainable travel, aligns with Local Plan policies on transport, design and King's Lynn regeneration, and is backed by the King's Lynn Transport Strategy 2025 to 2035 and the Local Cycling and Walking Infrastructure Plan. Report P19, P20, P118, P119, P121, P128

The Local Highway Authority, Environment Agency, Lead Local Flood Authority, Natural England, the Council's Ecology Officer and the Arboricultural Officer all raised no objection, subject to conditions. Report P42, P49, P50, P70, P72, P77

The Regeneration Team, Norfolk County Council Strategy Growth and Investment, Active Norfolk and the King's Lynn Civic Society (in principle) supported the scheme as a means to reduce congestion and encourage modal shift. Report P30, P32, P33, P35, P38, P87

What happens next

Detailed plans of roads, footways and cycleways, visibility splays, a Construction Traffic Management Plan and details of off-site highway works must be submitted and approved before development proceeds. Report P173

Conditions will require the development to be built in line with the agreed Flood Risk Assessment and Drainage Strategy, a construction phase surface water management plan, and a site specific bat sensitive lighting scheme. Report P54, P191

A Remediation Method Statement must be followed, a further ground gas risk assessment carried out, Biodiversity Net Gain delivered, and landscaping details enhanced post consent, all secured by condition. Report P67, P143, P193

The money

  • £20 million over 10 years Pride in Place Programme award for King's Lynn Report P15
  • £25 million Town Deal backed Active and Clean Connectivity project of which this scheme forms part Report P120
  • £60 million Earlier public infrastructure project that transformed the King's Lynn Enterprise Park Report P115

Options considered

  • Chosen: Approve the application. Officers judged it aligned with planning policy, no objections from key consultees, and the scheme supports active travel and regeneration aims. Report P1, P128, P174, P183
  • Rejected: Refuse the application. Not formally put as an option; the officer recommendation was approval and the Committee accepted it. Report P1

Implications

  • Climate: Supports modal shift from private car to walking, cycling and bus use, reducing emissions and contributing to the King's Lynn Air Quality Action Plan. Report P69, P123, P196
  • Other: Adds 236 car parking spaces, including 24 EV charging bays, on the edge of town with an informal park and ride link to existing bus services on Nar Ouse Way. Report P6, P13, P168
  • Risk: Site lies partly within Flood Zone 3 along its south west corner; a flood evacuation plan and sign up to the Environment Agency flood warning system are recommended. Report P62, P176, P179
  • Equalities: Includes 11 accessible parking bays, accessible EV bays, 6 cycle hoops for adapted cycles, 1 long cycle hoop and WC, shower and changing facilities within the hub. Report P5, P6
  • Legal: Third party objectors and the King's Lynn and West Norfolk Bicycle Users Group raised concerns over safety, design and use of public money; the Local Highway Authority did not share these concerns. Report P93, P94, P95, P96, P160

Who and where

  • Workers and visitors to the King's Lynn Enterprise Park, including the King's Lynn Innovation Centre and King's Lynn Health Hub Report P117, P149
  • Residents of King's Lynn and surrounding villages who may walk, cycle or use the Excel bus service into town Report P35, P159
  • King's Lynn town centre businesses and visitors, as the hub is intended to reduce car trips into the centre Report P13, P19
  • Cllrs, officers and consultees, with the King's Lynn and West Norfolk Bicycle Users Group and King's Lynn Area Consultative Committee registering objections or holding objections Report P90, P94

Timeline

  • 2002: Outline planning permission granted for the wider Nar Ouse Regeneration Area Report P24
  • 1 June 2026: Application deferred at Planning Committee for further review by the Regeneration and Development Panel and further operational detail
  • 22nd July 2026: Application due to be considered by the Regeneration and Development Panel, with the outcome to be reported in late correspondence
  • 27 July 2026: Planning Committee resolved to determine the applications in accordance with the schedules signed by the Chair

Plain English for the jargon

  • KLEP: King's Lynn Enterprise Park, a 48.5 hectare brownfield site to the south of King's Lynn town centre
  • NORA: Nar Ouse Regeneration Area, the wider enterprise zone around the application site
  • LCWIP: Local Cycling and Walking Infrastructure Plan for King's Lynn
  • AQAP: Air Quality Action Plan, a statutory plan covering King's Lynn
  • BNG: Biodiversity Net Gain, a requirement to deliver measurable gains for nature
  • LLFA: Lead Local Flood Authority at Norfolk County Council
  • LHA: Local Highway Authority at Norfolk County Council
  • IDB: Internal Drainage Board, here the East of Ouse, Polver and Nar IDB
  • RMS: Remediation Method Statement, addressing phosphogypsum contamination on the former fertiliser works site
  • NPPF: National Planning Policy Framework
  • EV: Electric Vehicle, referring to EV charging parking bays
  • SuDS: Sustainable Drainage System features such as raised planters and lined tree pits
  • KLIC: King's Lynn Innovation Centre, located south west of the application site
  • KLWNBUG: King's Lynn and West Norfolk Bicycle Users Group, an objector to the application
  • KLACC: King's Lynn Area Consultative Committee, which lodged a holding objection
  • STARS: Norfolk County Council's Sustainable Transport Access and Reach Strategy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPC28:

Resolved

That the applications be determined, as set out at ( i ) – (vii) below, where appropriate to the conditions and reasons or grounds of refusal, set out in the schedules signed by the Chair. (i) 25/01783/FM King’s Lynn: Development site west of Nar Ouse Way: Application for the phased development comprising the change of use of the land to an Active Travel Hub, alongside the construction of a single storey hub building, surface car park, pedestrian infrastructure, access, landscaping and ancillary works: The Borough Council of King’s Lynn and West Norfolk Click here to view a recording of this item on You Tube The case officer introduced the report and reminded the Committee that the application had been deferred from 1 June meeting in order for the proposed development to be further reviewed by the Regeneration and Development Panel and for some further operational detail to be provided. The proposed development was to be considered at the Regeneration and Development Panel meeting due to take place on 22nd July 2026, after the date of the publication of this report. The outcome of the meeting will therefore be reported to Members in late correspondence. In the meantime, the Applicant had submitted a ‘Project Delivery Report’ providing further detail on several points raised at Planning Committee on 1st June 2026, particularly the key objectives of the proposed development, the operational model and financial viability of the scheme and the likely representative user groups. The Applicant had provided clarification on the key objectives of the proposed development, which are set out in the Project Delivery Report as: · Enhance connectivity – Establish a clear and highly visible link between the King’s Lynn Enterprise Park (KLEP), residential communities, and the town centre; · Congestion relief – Reduce peak-hour traffic pressures along the Nar Ouse Way corridor; · Public Health and decarbonisation – Encourage a shift towards active travel and public transport, supporting a cleaner, healthier, and more sustainable town; and · Economic growth and regeneration – Deliver enabling infrastructure, including the western access road, to support the continued development of the KLEP and the wider Nar Ouse Regeneration Area. The case officer explained that the application site related to a parcel of land measuring approx. 1.45 Ha at the King’s Lynn Enterprise Park, located on the western side of Nar Ouse Way, King’s Lynn. Full planning permission was sought for the phased development involving the change of use of the land to an Active Travel Hub, including the construction of a single storey hub building, surface car park, pedestrian infrastructure, access, landscaping and ancillary works. The cycle ‘hub’ building comprised covered and secure cycle parking for 48 regular bicycles, six cycle hoops for adapted cycles and one long cycle hoop for longer cycles. Lockers and a cycle repair ... view the full minutes text for item PC28:
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Planning Committee

Recommendation

APPROVE

THE APPLICATION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25.01783.FM :Report 303 KB DownloadRead as text
PDF
25.01783.FM 5000 :Report 717 KB Download
PDF
26.00366.OM :Report 323 KB Download
PDF
26.00366.OM Map 1 :Plan 459 KB Download
PDF
26.00366.OM Map 2 :Plan 523 KB Download
PDF
Decision on applicationsDecisions 488 KB Download

At this meeting

Whole meeting

Who was there

9 of 36 attended
BA
Councillor Bal AnotaCommittee Member, present
HA
Henry AnthonyCouncil Staff, expected
JA
James ArrandaleCouncil Staff, expected
KB
Kate BlakemoreOfficer, expected
FB
Councillor Francis BoneVice-Chair, expected
EB
Emma BriersSecretary, expected
AB
Councillor Anthony BubbCommittee Member, expected
MC
Martin ChisholmOfficer, expected
SC
Siobhan CleeveCouncil Staff, expected
JC
Julie CookeCouncil Staff, expected
MD
Councillor Michael de WhalleyCommittee Member, present
TD
Councillor Tom de WintonCommittee Member, apologies

All 36 on the meeting page

More from King's Lynn and West Norfolk Planning Committee

All decisions
MeetingDecisionOutcome
5 Oct 2026 PC47That the applications be determined as set out at (i) – (ii) below, where appropriate to the conditions and reasons o... Refused Open
5 Oct 2026 PC48That the report be amended and re-circulated. Decided Open
7 Sep 2026 PC37That the applications be determined as set out at ( i ) – (iv) below, where appropriate to the conditions and reasons... Refused Open
7 Sep 2026 PC38(1) That the report be noted. (2) That a breakdown of enforcement cases showing their start dates be circulated so Me... Noted Open
7 Sep 2026 PC39That the reports be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies