What was decided
The Panel supported the recommendations to Cabinet on the Q1 2026-2027 Performance Management Report.
The Panel added a recommendation that the Car Parking Strategy status be changed from Amber to Red, given the slippage in its target date and links to the King's Lynn and Hunstanton masterplans. Report P49
Why
The Car Parking Strategy target was December 2025 but the project has slipped because King's Lynn and Hunstanton masterplan consultation dates changed, and the panel judged this level of delay warranted a Red rating. Report P49
The report gives an overview of progress and key indicators under the four corporate priorities, so the Panel used it to scrutinise delivery and adjust the status of the Car Parking Strategy. Report 3.1, 3.2, P20
Assistant Directors are responsible for assessing Q1 2026-2027 project status, providing the evidence base for the Panel's review. Report 3.2
What happens next
Cabinet will receive the Panel's supported recommendations and the additional recommendation to reclassify the Car Parking Strategy as Red. Report P15
Officers will continue Q2 actions across the four priorities, with the final King's Lynn and Hunstanton masterplans due for Cabinet in October 2026. Report P58, P59, P60, P61
The money
- £250,000 Overall renewable energy investment from 2025/26 Solar Together programme (29 customers) Report P83
- £5m MHCLG grant to local authorities for Internal Drainage Boards, not yet allocated for 2026/27 Report P110
Options considered
- Chosen: Support the recommendations to Cabinet as drafted
- Chosen: Add a recommendation to reclassify the Car Parking Strategy from Amber to Red. Slippage in target date and dependency on masterplan outcomes Report P49
- Rejected: Take no further action
Implications
- Financial: No direct financial implications; delivered through existing services, programmes and budgets. Report P8
- Legal: No statutory or legal implications identified. Report P9
- Equalities: No direct equality considerations for this report; individual projects have their own Equality Impact Assessments. Report P13
- Climate: The Corporate Strategy includes a priority on protecting the environment and tackling climate change, delivered via the Climate Change Strategy and emerging Local Plan. Report P8
- Risk: Progress with corporate strategy actions feeds into corporate, directorate and project risk registers. Report P14
- Staffing: No HR implications identified at report level. Report P8
- Other: No Local Government Reorganisation implications and no Health and Safety implications identified. Report P10, P11
Who and where
- Cabinet, which will receive the supported recommendations plus the extra Car Parking Strategy recommendation Report P15
- West Norfolk residents across all four corporate priority areas Report 2.1, 2.2
- Assistant Directors and the Corporate Leadership Team who report project status Report 3.2, P12
Timeline
- 23 November 2023: Council approved the Corporate Strategy 2023-2027 Report 2.1
- July 2025: Cabinet adopted the 2025-2027 Action Plan Report 2.1
- Q1 2026-2027: Reporting period for the Performance Management Report Report 3.2, P23
- October 2026: King's Lynn and Hunstanton Masterplans due to be considered at Cabinet Report P58, P59, P60, P61
- 1 April 2028: Vesting day for the new West Norfolk Unitary under Local Government Reorganisation Report P131
Plain English for the jargon
- RAG status: Red, Amber, Green rating showing whether a project has major issues, minor delays, or is on track
- LGR: Local Government Reorganisation, the restructuring creating new unitary councils in Norfolk
- KPI: Key Performance Indicator used to measure service performance
- WNHC: West Norfolk Housing Company, a council-owned housing company
- AQMA / AQAP: Air Quality Management Area and Air Quality Action Plan