RESOLVED that the linkage and timing of the planning obligation projects to the individual developments be as follows A. The improved bus turnaround area shall be available before first use of either the beach or service area. B. The north car park access shall be improved with an interim scheme should the hotel have not been implemented but either the show venue or south car park surfacing has been implemented. C. The full works for the improvement of the north car park access improvements will be completed when the hotel is constructed. D. If the hotel is not built, the full north car park access improvements will be implemented if visitor numbers total 2.8 million over 2 consecutive years (with at least 1.35 million in year 2). E. The south car park access improvements would then be implemented if visitor numbers total 3 million over 2 consecutive years (with at least 1.44 million in year 2). F. The screen landscape planting in the 22 acre field shall take place in the first planting season at or following the commencement of construction of the hotel. (Note: The Tranches and Other Matters remain as approved by Development Control Committee on 1 July 2004.) Reason for Decision To enable the planning obligations relating to the 9 planning applications to be progressed.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
This report describes the progress that has been made in respect of negotiations concerning the planning obligation required in relation to the above planning applications. It also requests agreement to alterations to the linkages and timing of the planning obligation projects previously agreed by Committee on 1 July 2004.
Recommendation
1. It is RECOMMENDED that the linkage and timing of the planning obligation projects to the individual developments be as follows;
A. The improved bus turnaround area shall be available before first use of either the beach or service area.
B. The north car park access shall be improved with an interim scheme should the hotel have not been implemented but either the show venue or south car park surfacing has been implemented.
C. The full works for the improvement of the north car park access will be completed when the hotel is constructed.
D. If the hotel is not built, the full north car park access improvements will be implemented if visitor numbers total 2.8 million over 2 consecutive years (with at least 1.35 million in year 2).
E. The south car park access improvements would then be implemented if visitor numbers total 3 million over 2 consecutive years (with at least 1.44 million in year 2).
F. The screen landscape planting in the 22 acre field shall take place in the first planting season at or following the commencement of construction of the hotel.
(Note. The Tranches and Other Matters remain as approved by Development Control Committee on 1 July 2004.)
REASON FOR RECOMMENDATIONS To enable the planning obligation relating to the 9 planning applications to be progressed.
Background
1. Progress made in respect of negotiations concerning the planning obligation required in relation to the planning applications was reported to Development Control Committee on 24 March 2005 when Members agreed that
1. an extension of time to 30 September 2005 for the completion of the planning obligation be agreed; and
2. consideration of the linkage and timing of the planning obligation projects to the individual developments be deferred pending clarification about the implications of the linkages.
2. Copies of the report to that meeting are enclosed separately for Members of the Committee only, further copies are available on request.
CLARIFICATION
3. The proposed alterations to the linkages and timings from those agreed by Development Control Committee on 1 July 2004 relate solely to the improvements to the north car park and the south car park accesses. There was concern that the new junction at the entrance to the north car park would not be implemented if the hotel is not built. Officers were authorised to negotiate a fall back position.
4. The junction at the access to the south car park has been improved in recent years and works satisfactorily. Officers from Transport for London and this Authority consider that works to the entrance to the north car park are more of a priority than those to the entrance to the south car park. The north car park is the main car park. The south car park is secondary and limited to a maximum use of 100 days a year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.