Maldens and Coombe Neighbourhood approved this item on Wednesday 18 January 2006. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: 1. a “task and finish” group (as set out in paragraph 20 of the report with the terms of reference set out in paragraph 16 of the report) be established to further develop the measures outlined in the report, and members be nominated as follows to serve on the task and finish group: - Councillor Don Jordan - Councillor Howard Jones - Councillor Ian McDonald. 2. in principle approval be given to funding from the Neighbourhood revenue account those recommendations arising out of the review which do not require major expenditure, approximately £2k - £3k. 3. note that a bid of £75,000 has been included in the 2006/2007 Local Capital programme with additional alternative funding sources to be sought to implement more substantial recommendations arising from the review. REASON FOR DECISION To seek the Committee’s approval to develop further measures to improve the functioning and operation of the Home Zone. [Councillors Celia and Derek Osbourne declared a personal and prejudicial interest in this item and withdrew from the room during its consideration.]
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
In August 2003 the road layout in Cavendish Road, Cromwell Avenue, Walton Avenue, Tadworth Avenue, Chatsworth Gardens, and Haddon Close was changed to create a “Home Zone”. The review process included a technical review (the results of which were reported to 2 November 2005 meeting of this Committee) and a consultation review the results of which are reported here.
Recommendations
It is RECOMMENDED that:
1. a “task and finish” group (as set out in paragraph 20 of the report) be established to further develop the measures outlined in the report, and members be nominated as follows to serve on the task and finish group: - one member from the Liberal Democrat Group of the Committee - one member from the Conservative Group of the Committee- - a Co-Chair of the Committee.
2. in principle approval be given to funding from the Neighbourhood revenue account those recommendations arising out of the review which do not require major expenditure, approximately £2k - £3k.
3. note that a bid of £75,000 has been included in the 2006/2007 Local Capital programme with additional alternative funding sources to be sought to implement more substantial recommendations arising from the review.
Reason for recommendations
To seek the Committee’s approval to develop further measures to improve the functioning and operation of the Home Zone.
Background
1. In August 2003 the road layout in Cavendish Road, Cromwell Avenue, Walton Avenue, Tadworth Avenue, Chatsworth Gardens, and Haddon Close was changed to create a “Home Zone”. This was done by Kingston Council in partnership with local residents, who formed a working group with representatives from each road to develop ideas and design the new road layout.
• to turn residential streets into valued public open space, and not just a place for the movement of traffic; • to reduce through traffic speeds and volumes • to improve the safety and security of all road users; • to improve the environmental quality of the street; • to encourage less mobile members of the community, particularly children, older people and the disabled to feel safe and “get out more”.
3. The working group agreed a consultation to seek the views of users, including local residents and people who walk, drive or cycle through the area, on the effectiveness of the new road layout.
REVIEW PROCESS
4. A comprehensive review process of a scheme consists of 2 major elements:
• Technical Review – results detailed in previous report to this Committee in November 2005.
• Consultation Review – seeking the views of: a. Residents Working Group b. Ward Councillors and Committees. c. Public service providers and road user groups –(included in Technical Review) d. Local residents and businesses. e. Non-residential road users.
PUBLIC CONSULTATION
5. The content and format of the consultation letter and questionnaire, a copy is attached at ANNEX 1 (MEMBERS’ AND LIBRARIES’ COPIES AND WEBSITE), were discussed and agreed at a meeting of the Residents Working Group on 17 October 2005.
6. The leaflets were delivered to all households in the Home Zone in November 2005. Copies of the leaflet were also left in the United Reformed Church, the doctor’s surgery and the vets in Burlington Road, these being the prime non-residential users of the Zone primarily for parking.
RESULTS OF CONSULTATION
7. 230 leaflets were delivered to households in the Home Zone and there have been 65 responses (28% of households) received. 150 leaflets were made available to non-residents; there have been 13 responses (8.5%). Attached as ANNEX 2 (MEMBERS’ AND LIBRARIES’ COPIES AND WEBSITE) are copies of the responses received to date in graphical and tabular format, together with a list of all comments. A3
SUMMARY OF CONSULTATION RESULTS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Maldens and Coombe Neighbourhood at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of the Chair and Vice-ChairRESOLVED that Councillor Simon Edwards be appointed Chair and Councillor Lesley Heap be appointed Vice-Chair for the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.