the Borough Neighbourhood Committee agreed this item on Wednesday 25 January 2006. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: 1. Officers enter into discussions with D.C.Leisure regarding adding the facility management and café and hall management to the Leisure contract, and report progress to the Co-Chairs. 2. Officers explore the operation of the crèche in conjunction with the proposed Children’s Centre at Buckland Infant School, and report progress to the Co-Chairs. 3. Officers explore further the operation of the Music Recording Studio and report progress to the Co-Chairs. 4. the operation of the Learning Centre by Kingston Adult Education, in partnership with Kingston Libraries, be agreed to allow the application for external funding to meet the opening date deadline. 5. contract and financial negotiations be undertaken with the advice and notification of Strategic Services and the Finance Directorate. 6. the flexibility of existing resources to provide a presence on the information helpdesks be explored. Reason for Decisions To enable contract negotiations and works associated with each service area to be completed and in place, allowing all areas of the Hook Centre to be operational when the building opens to the public in autumn 2006
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
The Hook Centre is due to open in Autumn 2006. The Centre includes a larger Hook and Chessington Library, a Learning Centre, Music Recording Studio, Citizens Advice Bureau, community areas, crèche, public toilets and café. It is proposed that further council, agency and voluntary services will be offered from the Centre. Residents can hire spaces for meetings and events. Proposals for the operational management of the Centre are set out in the report.
Recommendations
It is RECOMMENDED that:
1. Officers enter into negotiation with D.C.Leisure regarding adding the facility management and café and hall management to the Leisure contract, and report progress to the Co-Chairs.
2. Officers explore the operation of the crèche in conjunction with the proposed Children’s Centre at Buckland Infant School, and report progress to the Co- Chairs.
3. Officers explore further with Kingston College and the Secondary Schools Consortium the operation of the Music Recording Studio and report progress to the Co-Chairs.
4. the operation of the Learning Centre by Kingston Adult Education, in partnership with Kingston Libraries, be agreed to allow the application for external funding to meet the opening date deadline.
5. contract and financial negotiations be undertaken with the advice and notification of Strategic Services and the Finance Directorate
Reason for recommendations
To enable contract negotiations and works associated with each service area to be completed and in place, allowing all areas of the Hook Centre to be operational when the building opens to the public in autumn 2006.
Background
1. In October 2004 the Council awarded capital funding of £2.2 million to match external funding of £950,000 from the Learning and Skills council to build an
innovative community building in South of the Borough neighbourhood, on the site of Hook and Chessington Library and Hook Community Centre. The new Hook Centre is due to open in autumn 2006. During construction a temporary library is available at The King’s Centre, Coppards Gardens.
2. The new building will provide a range of council and community services including a larger public library, Learning Centre and Music Recording Studio, a community hall for meetings, activities and events, a café and a crèche. It is proposed that further council, agency and voluntary services will be offered from the Centre. Residents can hire spaces for meetings and events
3. Public meetings for residents were held in January and July 2005 to both advise on progress and answer questions on the project. A further public meeting will be held at 7.00pm on 13 February 2006 at Southborough School, Hook Road. The meeting will provide a progress report, and question and answer session, and form part of a survey to ascertain the learning courses, children’s activities and events residents wish to see, and would support, in the Centre. This information will allow officers to plan a programme, and organise publicity, for autumn 2006.
BACKGROUND TO THE REPORT
4. At the South of the Borough meeting on 14 September 2005 the Committee considered the South of the Borough (The Hook Centre) Operation of Services Report. It was resolved that officers investigate any increased revenue requirements for the Hook Centre for utilities and running costs and the estimated income target for 2006/07 and that the Director of Finance be notified of the findings. This is being undertaken. It was further resolved that officers investigate the best way in which the day to day operational management of the Centre could be carried out, including the appointment of a Centre Manager, and any revenue or income implications, and reported their findings to the Committee.
INVESTIGATION OF OPERATIONAL MANAGEMENT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.