RESOLVED that 1. the proposed changes to Contract Standing Orders and Financial Regulations set out in this report, together with the consequential changes to officer delegations be endorsed; 2. the revised Contract Standing Orders, Financial Regulations and the consequential changes to officer delegations be referred to Council for approval and inclusion in the Council’s Constitution; and 3. the financial limits set out in Contract Standing Orders and Financial Regulations be reviewed at regular intervals so that the thresholds can be raised if needed. Reason for decision To ensure that the Council’s Contract Standing Orders and Financial Regulations continue to be robust, appropriate and up to date.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
CONTRACT STANDING ORDERS AND FINANCIAL REGULATIONS
Report by Director of Finance and Heads of Strategic Services and Democratic Services Leader of the Council and Executive Member for Improvement and Performance
Purpose To seek approval of a number of revisions to Contract Standing Orders and Financial Regulations, largely consequent upon adoption of the Procurement Framework.
Action proposed by the Leader of the Council and the Executive Member for Improvement and Performance:
The Executive is requested to: 1. endorse the proposed changes to Contract Standing Orders and Financial Regulations set out in this report, together with the consequential changes to officer delegations; and 2. refer the revised Contract Standing Orders, Financial Regulations and the consequential changes to officer delegations to Council for approval and inclusion in the Council’s Constitution. Reason for action proposed To ensure that the Council’s Contract Standing Orders and Financial Regulations continue to be robust, appropriate and up to date.
BACKGROUND 1. Contract Standing Orders and Financial Regulations set out principles of financial control and administration. They were last comprehensively reviewed in 2000, with further subsequent revisions. The Council is responsible for approving changes to Contract Standing Orders and the Constitution whilst the Executive is responsible for approving changes to Financial Regulations.
2. Following the adoption of the new Procurement Framework in December and other changes in circumstances, procedures, legislation and best practice, it is now necessary to make some adjustments. The opportunity is also taken to propose some uplifting of the various financial levels in the light of inflation.
PROCUREMENT FRAMEWORK
3. The Executive approved the Council’s new Procurement Framework in December 2005. The Framework centres round an overarching Procurement Strategy that sets the direction for developing and delivering the aims and objectives of the Council through procurement to ensure the delivery of quality services in the most cost effective and environmentally sustainable way. The Strategy is supported by a new Ethical Procurement Policy and underpinned by practical web based guidance for Members, Officers and suppliers. All these documents are available on the Internet with the Executive agenda and copies are in the Group Rooms and Members’ Room. I-2
4. Key changes introduced by the new Framework are:
a) greater financial control over smaller purchases;
b) improving delegated decision making by removing unhelpful presumption toward lowest cost;
c) using the efficiencies of technology (e.g. e-procurement – tendering, ordering and invoicing);
d) accommodating consortia and framework agreements; and
e) seeking local business/third sector suppliers where possible.
f) “Everyone procures”; some block exemptions have been removed and all procurements are covered by Financial Regulations or Contract Standing Orders.
5. Simple financial thresholds will be replaced with procurement classifications, i.e. a combined assessment of risk and total cost (see Annex 1). The table shows how these classifications offer streamlined and proportionate regulation of:
a) the procurement approach (pre-qualification, “tenders” vs. “proposals” etc.);
b) the contractual relationship that is formed;
c) ethical requirements (diversity, equality, sustainability etc.); and
d) advertising.
Proposed amendments 6. A copy of the proposed revised Contract Standing Orders and Financial Regulations are attached (see Annexes 2 and 3). Contract Standing orders 7. In summary, the key proposed changes to Contract Standing Orders are:
a) Updating of titles of relevant Council officers.
b) Removing throughout the requirement to consult Overview Panel Chairs and opposition spokepersons that was introduced when there was no overall control of the Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.