SOMERSET AVENUE AREA AND CLAYTON ROAD IMPROVEMENT SCHEME
NotedCommittee6 papers
the Borough Neighbourhood Committee noted this item on Wednesday 22 February 2006. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: 1. the work of the Working Group be noted and the members of the Working Group thanked for all their work. 2. the results of the consultation be noted. 3. the phase 1 measures as shown in Annex 1 to these minutes be implemented. 4. a bid be made through the Borough Spending Plan (2007/08) for funding for phase 2 of the scheme. 5. after the implementation of the phase 1 measures, further consultation be carried out before the implementation of phase 2 of the scheme. Reason for Decisions To enable implementation of phase 1 of a scheme to introduce a 20 mph speed limit in the whole area and to enable further consultation to take place with residents before phase 2 of the scheme. Note: Councillors Ian Reid and Mary Reid declared personal interests in this item.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Background In December 2003 you were invited to a public meeting to discuss issues in the Somerset Avenue area. The meeting was well attended by residents and the following objectives were set for the area. 1. Reduce vehicle speeds and the amount of through traffic 2. Carry out maintenance of the footways and carriageways, 3. Consider the influence that other roads have on the area (mainly Clayton Road), 4. Reduce the number of large vehicles, 5. Other objectives (3 issues) • Allow the right turn from Hook Road into Clayton Road. • Enforcement of regulations. • Consider traffic lights at the junction of Hook Road and Somerset Avenue. 6. Improve visual amenity and the environment in the area.
There has been a general issue in Hook and Chessington with regard to emergency vehicle access. The demand for parking in this area is most intense in the lengths of Somerset Avenue nearest to Hook Road. Access has been made more reliable by the introduction of a staggered layout of double yellow lines (no waiting at any time).
The Council bids for the money to carry out traffic management schemes annually from Transport for London (TfL) for projects throughout the Borough. The money is allocated by TfL based on laid down criteria on a project by project basis. There is money to undertake a traffic management scheme in the area. This money will enable Phase 1 of the scheme to be implemented. If residents support the proposals a bid will be made for further funding to implement phase 2.
Highway Maintenance The Council has carried out some highway maintenance works to carriageways and footways in the area. There is funding to complete the kerbing, footway and carriageway works in Somerset Avenue and the kerbing and carriageway works in Selwood Road. The kerbs will be renewed and careful consideration will be given to any implications for tree roots. A letter will be sent to residents where maintenance works are proposed. Residents will have the opportunity to apply for their crossover (driveway) to be widened.
The maintenance and improvement works will be coordinated to minimise disruption.
Possible Schemes to address traffic issues. At the meeting in December 2003, nine residents volunteered to be members of the Somerset Avenue Area Working Group which has met several times. The Group has discussed the identified issues and objectives and considered possible improvements. • Reduce vehicle speeds and the amount of through traffic, • Consider the influence that other roads have on the area, • Reduce the number of large vehicles. The various proposals aim where possible to meet the objectives set at the initial public meeting.
Speed of Traffic. The Working Group has carefully considered options to reduce vehicle speeds. Some Working Group members have discussed the options with their neighbours so that the initial views could inform the Working Group. The regulations will not permit us to lower the speed limit to 20 mph without the installation of physical works at regular intervals along each road in the area. The options considered were • Raised tables (see details A and B overleaf) • Chicanes (see details C overleaf) • Narrowings (see details D overleaf) • Speed cushions (see details E overleaf)
To provide a scheme of chicanes or narrowings there would have to be double yellow line waiting restrictions at each set of features to prevent obstructive parking. To ensure their safe operation they would have to be marked with bollards and road markings.
The majority view of the Working Group was that installing these features would be very detrimental to the character of the roads and would be an unacceptable nuisance to the residents living adjacent to the features.
The preferred scheme is to install raised tables within the Somerset Avenue Area some of which will be at the junctions. The proposed scheme is shown on the plan and in details A and B overleaf. Your views are requested in the questionnaire.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.