RESOLVED that the Development Control Committee be advised that this Committee supports the application subject to the re-instatement of the open space following the redevelopment of the site. Note Councillor Patricia Bamford declared a personal interest in this report Reason – one of her children is a pupil at the College.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
The views of the Committee are requested on planning application 06/10078/FUL for development at Chessington Community College, Garrison Lane, Chessington prior to consideration of the application by Development Control Committee.
The proposal is; Erection of temporary classrooms, offices, toilets and storage accommodation on the playing field to the rear of the site as temporary teaching/admin accommodation during construction of new college buildings.
Recommendation
It is RECOMMENDED that any comments be submitted on the application so that they can be reported to the Development Control Committee when they consider the planning application.
Reason for recommendations
To enable the Neighbourhood’s views to be considered by the Development Control Committee when the application is determined.
INTRODUCTION
1. This application falls to be determined by Development Control Committee. This report represents consultation with South of the Borough Neighbourhood Planning Sub Committee prior to future consideration of the application by Development Control Committee.
SITE
2. This application relates Chessington Community College which occupies a site of approximately 2.7hectares on the north side of Garrison Lane. Ellingham Primary School is situated to the north, Chessington South station and railway line to the east, and residential properties in Harrow Close, Burton Close and Garrison Lane to the west. Barwell Business Park is situated on the south side of the road.
3. As well as the educational buildings the site includes Chessington Sports Centre, the grassed area between the college and Ellingham Primary School and 2 caretaker’s houses. Planning permission has been granted for the installation of 6 B2
all weather tennis courts and associated floodlighting on part of the grassed area, (renewal of planning permission 96/2086) under 02/02007 on 14 March 2002.
Background
4. As part of the Building Schools for the Future programme, the DfES has allocated up to £23m capital grant to Kingston to rebuild Chessington Community College, by September 2008. The objectives include the rebuilding of the school, the transformation of education in the area, with a particular emphasis on vocational courses, increased community use and extended school facilities. The existing Community Sports Centre is to be retained and upgraded. A phased redevelopment of the school is proposed involving a temporary ‘village’ of school accommodation in the interim which is the subject of this planning application. The Director of Learning and Children’s Services intends to submit a full planning application for the new school in May. The applicants have already held a number of public meeting/open forums to explain the proposals to local residents.
PROPOSAL
5. This is a full planning application. It proposes the installation of temporary classrooms and buildings on the playground and grassed area between Chessington Community College and Ellingham Primary School to replace accommodation in two of the school’s teaching blocks which would be demolished this summer. The temporary buildings, currently at Tiffin Girl’s School and St Philips School, would be grouped round the western part of the site with a play area to the east. The temporary village would also include the existing 4 temporary double classrooms sited to the north of the existing school buildings and existing Block C which would be retained in the first phase of building.
6. As well as classrooms, the temporary building would provide accommodation for Learning Support, Library, Staff, offices, toilets and storage. All proposed temporary buildings would be single storey in height and some will include ramped disabled access. It is proposed that one tree would be removed but that all the other trees on site would be retained. CONSULTATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.