Maldens and Coombe Neighbourhood approved this item on Thursday 11 January 2007. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the details of the scheme for the extension of the New Malden High Street scheme from Grafton Road to New Malden Station as outlined in paragraphs 5 and 6 of the report be approved for implementation: construction details of median strip the surfacing details of the entry treatments at Grafton Road and Dukes Avenue footway surfacing new street lighting columns details of the central island for the roundabout. removal of pedestrian guard-railing granite setts set into carriageway on approach from north. type of cycle stand traffic signs (as included in schedule) additional tree planting and soft landscaping. Reason for decision To approve the details of the High Street extension scheme between Grafton Road and New Malden Station prior to implementation.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
At its meeting on 23 November 2006 the Committee resolved that “the proposed works extending the New Malden High Street scheme from Grafton Road to New Malden Station be approved subject to details of implementation being submitted to the Committee meeting in January 2007”.
The details of the proposal between Grafton Road and New Malden Station are outlined in paragraphs 5 and 6 of the report. Details of works and programme for the British Gas mains replacement works are also included for information purposes. The Committee is requested to consider the details submitted in this report and approve their implementation in the New Year.
Recommendation
It is RECOMMENDED that the details of the scheme as outlined in paragraphs 5 and 6 of the report be approved for implementation:
• construction details of median strip • the surfacing details of the entry treatments at Grafton Road and Dukes Avenue • footway surfacing • new street lighting columns • details of the central island for the roundabout. • removal of pedestrian guard-railing • granite setts set into carriageway on approach from north. • type of cycle stand • traffic signs (as included in schedule) • additional tree planting and soft landscaping.
Reason for recommendation
To ensure that Members are aware of and approve the details of the High Street extension scheme between Grafton Road and New Malden Station prior to implementation.
Background
1. The High Street is the centrepiece of New Malden and performs a number of essential roles: it is the district centre, local shopping centre, access to British Rail station, access to local leisure centre, a bus route, and a traffic corridor. E2
2. The main aims of the proposals are to maintain and improve: economic viability of local businesses, environmental amenity, road safety, pedestrian facilities, cycle access, bus facilities, feelings of personal safety and security, reduce congestion and improve the overall efficiency of the corridor. People are to be encouraged to visit the High Street more using transport choices which cause less damage to the environment, at the same time provision will be made for essential vehicles to ensure that local economic and community needs are met.
3. Transport for London consider the High Street scheme an exemplar and have allocated further funding to extend the concept of the High Street to encompass access to New Malden Station (as summarised below), eventually the shopping area in Coombe Road and on residential streets immediately accessing the High Street.
WORKS BETWEEN GRAFTON ROAD AND NEW MALDEN STATION
4. A report outlining the proposed scheme extending the High Street concept between Grafton Road and New Malden Station was discussed at the Committee meeting on 23 November 2006. The Committee resolved that: “the proposed works extending the scheme from Grafton Road to New Malden Station be approved subject to details of implementation being submitted to the Committee meeting in January 2007.”
5. The elements of the scheme are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Maldens and Coombe Neighbourhood at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of the Chair and Vice-ChairRESOLVED that Councillor Simon Edwards be appointed Chair and Councillor Lesley Heap be appointed Vice-Chair for the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.