MANAGING OUR PERFORMANCE – MID YEAR MONITORING 2006/07

Approved Executive 3 papers

Executive approved this item on Tuesday 23 January 2007. Below is the council's own wording, with the papers it was decided on.

Item97

Resolved

RESOLVED that 1. the set of top level Performance Indicators to be monitored in 2006/07 set out in the report be approved, with a view to reviewing arrangements for 2007/08 and beyond; and 2. the mid - year monitoring data for 2006/07 for the top-level indicators set be noted. Reason for decision To ensure that performance management continue to be strengthened as a tool to improve services.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Executive

Background

1. Performance management is a key area where we have worked to strengthen our corporate arrangements over the last few years. The Executive considered a full report at its 7 December 2004 meeting setting out the progress made in implementing and embedding the Council's agreed Performance Framework. These included developments-

• To refine the set of top-level indicators that will be monitored by the Everyone Counts Group and reported on to Executive. • To move to a more pro-active performance monitoring regime, with identification of key improvement indicators and quarterly reviews of performance. • To implement an agreed monitoring cycle with Directorates so that the corporate arrangements flow out of the active monitoring being carried out at Directorate Management Team level.

2. This report proposes changes to the top - level set for 2006/07 in order to reflect the new Policy Programme, and analyses the performance at the six month stage. Colour copies of Annexes 1 and 2 are enclosed for Members of the Executive and Scrutiny Panel.

TOP LEVEL PERFORMANCE INDICATORS 2006/07

3. Following the local elections in May 2006 a new set of indicators has been developed to reflect the twelve Key Objectives in the new Policy Programme and to be used as the basis for top – level monitoring for the remainder of this financial year. D2 4. Annex 1 sets out the proposed top level set to be monitored during 2006/07. The majority of the indicators in the set are annual in nature and so shall not be reported on as part of the mid year monitoring exercise.

5. The set contains many indicators that were used in the previous top level set as well as new indicators to allow the Council to monitor progress against the new policy programme objectives. Those indicators of less relevance to the new key objectives have been removed. 6. The top-level set will be kept under review throughout the year and will be supplemented should it become useful to include additional measures to monitor improvement activities. Such indicators may be drawn from work relating to the Policy Programme, the Local Area Agreement, the Comprehensive Performance Assessment and its successor, or Service and Team planning activity.

7. It is our intention to renew our arrangements for 2007/08 and beyond, to reflect in particular the outcomes of the medium – term service and financial planning exercise that is currently underway.

SIX MONTH MONITORING

8. The top-level set of indicators for monitoring by the Executive and the CDT Everyone Counts Group forms the apex of the pyramid of performance management activity being carried out at different levels of the Council.

9. Annex 2 sets out a range of basic performance data for the period 1st April 2006 to the end of September 2006, covering the top-level indicators, including trends over time and whether performance is on target.

10. It is important to note that the mid year report does not contain the full set of indicators used to measure top level performance. Some indicators do not yield significant outturns at the mid-year point and are only collected on an annual basis.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
D Top level midyear 2006-07 Annex 1Appendix 78 KB Download
PDF
D top level set midyear 06-07 Annex 2Appendix 62 KB Download
PDF
MANAGING OUR PERFORMANCE: MID YEAR MONITORING 2006/07Report 20 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
DO
Councillor Derek OsbourneChair, present
PB
Patricia BamfordMember, present
DR
DAVIES RolsonMember, present
JS
JAMES Simon AlexanderMember, present
IR
Councillor Ian ReidMember, present
LG
Councillor Liz GreenMember, present
SP
SHELTON PennyMember, present
SB
Councillor Sue BakerPublic, in attendance
IG
Councillor Ian GeorgePublic, in attendance
PJ
Councillor Paul JohnstonPublic, in attendance
NK
Councillor Nick KilbyPublic, in attendance
RT
Councillor Robert-John TaskerPublic, in attendance

All 13 on the meeting page

On this subject at Kingston upon Thames

Search all
  1. MANAGING OUR PERFORMANCE – MID YEAR MONITORING 2006/07This decision
  2. Managing our performance - comprehensive performance assessment 2007 - nine month monitoring 2007/08Noted

More from Kingston upon Thames Executive

All decisions
MeetingDecisionOutcome
27 Mar 2012 MINUTESRESOLVED that the minutes of the meeting held on 20 March 2012 are confirmed as a correct record. Decided Open
27 Mar 2012 Decisions of the policy and resources committee to be ratifiedRESOLVED that the following decisions of the Policy and Resources Committee on 27 March 2012 are ratified. Decided Open
27 Mar 2012 Grants to voluntary organisations: project grants 2012/13Agreed that 1. the amounts of Project Grant aid to be offered to the voluntary organisations for 2012/13 as set out i... Agreed Open
27 Mar 2012 One kingstonAgreed that the progress report concerning the One Kingston Programme is noted and reports continue to be submitted a... Agreed Open
27 Mar 2012 Capital programme 2012/13Agreed that 1. the forecast capital outturn for 2011/12 is noted 2. the proposed approach to developing and reporting... Agreed Open