the Borough Neighbourhood Committee noted this item on Wednesday 30 January 2008. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: 1. the progress on schemes to date be noted. 2. Priority for funding be allocated to the schemes at Bidmead Court, York Way/Garrison Lane ( Paving works at 2 blocks - to be identified) and Chessington Court; the costs to be reduced by the Neighbourhood Building Maintenance Ranger undertaking some of the work. Reason for decision To enable the Housing Improvement Budget to be fully allocated and committed by the end of the financial year.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
At its meeting of 6 June 2007, the Committee allocated resources from a Housing Improvement Budget to schemes for the improvement of the estates. This report updates members on the progress to date and requests the Committee to prioritise the available expenditure.
Recommendations
It is RECOMMENDED that
1. The Committee note the contents of this report and progress on schemes to date. 2. Prioritises schemes to allow expenditure to be restricted to the available budget.
REASON FOR RECCOMMENDATIONS
To enable the Housing Improvement Budget to be fully allocated and committed by the end of the financial year.
Background
1. At its 6 June meeting the Committee considered a report requesting that they allocate £30,600 of Housing Revenue Account funds to schemes to contribute to the improvement of the Council’s Housing stock in their neighbourhood.
2. Attached at Annex 1 is a list of the schemes to which funds were allocated along with the progress of the works to date and options for further schemes as requested by members at the November meeting of the Committee.
REPORT
3. Progress has been made on a number of schemes although there remain several outstanding. In particular areas of resurfacing are delayed as these works are allocated to RJ Dance, the Council’s highways contractor in order to give better value for money. However as the housing work is of a small scale and are not in the overall programme the work is carried out on an as and when basis. If progress has not been achieved by the end of January the work will instead be allocated to Mears to progress. It is hoped that this will have only a marginal impact on costs. C2
4. Members will be aware that several schemes have proved to be more costly than were originally estimated. As such they have requested that a further report be brought back setting out the options for these schemes and for further schemes to be bought forward for consideration.
5. Annex 1 lists all schemes either approved or where members have requested that proposals be brought forward. Members will wish to note the following:
a) Bidmead Court – The original cost of the scheme was estimated at £3,000. However further investigation shows that this will not be sufficient to deal with the full extent of the problems with the paths and walls around the block. The new estimated cost for all the work is £17,500 and this has not been approved by the Committee. However a site meeting has been held with members to prioritise the works to be done. The cost of the works to the paving alone, along with marking the nosings of external steps is £8,000. This does not allow for the repairs to walls, but officers will examine which of these can be carried out within existing HRA resources. b) York Way – the total cost of the works to the external steps is in excess of £42,000 against an allocated budget of £14,000. Members met with officers to allocate resources on a worst first basis and have prioritised blocks 43-67 and 134-144. This will use the allocated budget. Further blocks could be improved at a cost of approximately £7,000 each. c) Members requested that costings be obtained for the repairs and replacement of gates to the rear of properties on the Chessington Court Estate. These have not had the approval of the Committee. The cost of these works is £2,000. d) Members requested costings on landscape improvements for Chaffinch Close, including the replacement of the ball to the top of the entrance pier. The estimated cost of this work is £1,500. This has not been approved by committee.
6. The total budget available to the Committee is £30,600. The total cost of approved and non approved schemes amounts to £38,304. There is therefore an over commitment of £7,704. Non- approved schemes at Chessington Court and Chaffinch Close total £3,500 and the scheme at Bidmead Court is £5,000 over approved costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.