RESOLVED that: 1. subject to the results of consultations with the local community, to be considered by the Service Director in consultation with the Co Chairs and Ward Councillors, the following proposals be approved · a zebra crossing in Buckland Road outside the School pedestrian access · the widening of the footway outside 26/28 Buckland Road · the extension of the parking bay outside nos 2 and 4 Buckland Road · the extension of the double yellow line beside no. 97 Moor Lane to the start of the parking nay at no. 2 Buckland Road 2. the changes to the operational times of the school keep clear markings in Buckland Road previously approved be implemented separately from those at other schools in the Borough subject to the traffic management order process. Reason for decision To improve highway safety in the vicinity of Castle Hill Primary School.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
This report seeks approval to implement highway improvements in the vicinity of Castle Hill Primary School in Buckland Road and Moor Lane. As part of the process to determine the preferred site for Castle Hill Primary School a Working Group was formed to consider the implications of a larger school on one site. The recommendations in this report have been endorsed by the Working Group.
Recommendations
It is RECOMMENDED that:
1. the following schemes as shown in Annex 2 be approved for implementation subject to the results of consultations with the local community. • a zebra crossing in Buckland Road outside the School pedestrian access • the widening of the footway outside 26/28 Buckland Road • the extension of the parking bay outside nos 2 and 4 Buckland Road • the extension of the double yellow line beside no. 97 Moor Lane to the start of the parking nay at no. 2 Buckland Road
2. the results of the consultation be considered by the Service Director in consultation with the Co Chairs and Ward Councillors so that the way forward can be agreed.
3. the extension of the double yellow line outside no. 93 Moor Lane as shown in Annex 2 be implemented subject to the traffic management order process.
4. the changes to the operational times of the school keep clear markings in Buckland Road previously approved by Committee be implemented separately from those at other schools in the Borough subject to the traffic management order process.
5. the short lengths of double yellow line by no. 33 Buckland Road as shown in Annex 2 previously approved by the Committee be implemented subject to the traffic management order process.
Reason for recommendations
To improve highway safety in the vicinity of Castle Hill Primary School. E2
Background
1. Castle Hill Primary School was formed last summer from the amalgamation of Buckland Infant and Nursery School and Moor Lane Junior School. Following consultations with the local community in the autumn, the Council determined that the new school should be sited from September 2008 on the Buckland Road site. As part of this process a Working Group was established to consider the highway issues associated with the new school on one site in Buckland Road and to bring forward proposals for improvements. The Working Group is made up of local residents, school Governors, school staff, representatives from organisations that use the school premises, a local business, local Councillors and Officers.
2. The Working Group has met on two occasions, on 28 November 2007 and 26 February 2008. The first meeting agreed the issues and possible solutions/improvements and these are shown in Annex 1. The School has to produce a School Travel Plan which must seek ways to reduce car dependency for school related trips by particularly encouraging walking and cycling. This is nearing completion. To encourage more walking to and from school there is the opportunity to open a new pedestrian access at Mount Road where the school has a boundary with the road near Four Oaks. This proposal was discussed by the Working Group and it was agreed that it would be put to a meeting of the School Governors for their consideration. Officers prepared a plan showing a possible zebra crossing in Mount Road to provide a safe crossing point. The Governors decided that a decision on this option should be deferred until the new building proposals for the School are known. The construction site access will be at Mount Road and there was concern about conflicts with pedestrians during the works.
3. Between the two Working Group meetings Officers prepared schemes to address the identified issues. These are shown in Annex 2 and were considered by the Working Group on 26 February.
PROPOSALS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.