RESOLVED that the approach taken to manage risk on the One School Pathfinder project to rebuild Chessington Community College be noted. Reason for the decision To provide the Audit Committee with assurance that a high corporate risk is being managed effectively.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
At its meeting of 5 December 2007 Audit Committee received a Review of Corporate Risks which includes the project to rebuild Chessington Community College as being of high risk for the Council. The report sets out the variety of risks and processes involved in a complex phased high cost rebuild project and the actions taken to minimise all risks. The experience should be helpful to Council in management of other large building projects, including the Primary Capital and Building Schools for the Future programmes.
Recommendation
It is RECOMMENDED that Committee note the approach taken to manage risk on the One School Pathfinder project to rebuild Chessington Community College.
Reason for recommendation
To provide the Audit Committee with assurance that a high corporate risk is being managed effectively
Background
1. The national Building Schools for the Future (BSF) programme was launched by central government in 2004, with the intention of rebuilding every secondary school in England over the following 15 years. Authorities were prioritised according to relative need (based on levels of deprivation and educational standards). This resulted in Kingston, along with the other Authorities of south-west London, being placed towards the end of the programme.
2. Kingston is currently anticipated to join the Building School for the Future programme from 2014 and to benefit from the Primary Capital Programme (PCP) from 2009. The substantial investment available through these programmes will provide the Local Authority with a key lever to transform the way in which children and young people learn and develop in the future.
3. In November 2005 the Government announced the intention that all Authorities (including those in later waves such as Kingston) would be provided with the opportunity to benefit from the BSF programme through participation in a One School Pathfinder rebuild project. The capital grant was made available on condition that: A2
(i) the Authority could rebuild a single school within exceptionally tight timescales, enabling the rebuilt school to open by September 2008, and
(ii) the new design must achieve at least a very good rating under a BREEAM (Building Research Establishment Environmental Assessment Method) assessment.
RISK MANAGEMENT IN THE PRE-CONSTRUCTION PHASE
4. In January 2006 the Executive confirmed the selection of Chessington Community College as the school for redevelopment, with associated investment at Tolworth Girls’ and Southborough High Schools to enable a more collaborative approach to 14-19 learning in the South of the Borough. The scheme was to be funded using a £23m 100% DfES capital grant. The Authority submitted a detailed proposal of the scheme to DfES in April 2006 and received confirmation of the capital grant in May 2006.
5. In order to achieve the deadline of September 2008 rapid progress was required to expedite the design and procurement process. It was essential that the optimum procurement route be selected, and therefore that different forms of contract be considered. Three main forms of contract were considered: • single stage selective tendering (which involves the preparation of measured bills of quantities after the design has been completed), • two-stage tender (selecting a single contractor for early involvement in the design and negotiating a contract sum) or, • design & build (where the contractor is fully responsible for the appointment and co-ordination of design consultants in addition to the construction work itself).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.