RESOLVED that the following reports be noted: 1. New Malden High Street – Carriageway construction 2. Coombe Estate barrier - outcome of court case 3. Dickerage Road petition update 4. Coombe Lane West traffic safety update 5. Malden Manor parking petition update 6. Clarence Avenue / Darley Drive / Elm Road 7. Potential forthcoming business 8. Traffic Scheme Update
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
1. New Malden High Street – Carriageway construction 2. Coombe Estate barrier - outcome of court case 3. Dickerage Road petition update 4. Coombe Lane West traffic safety update 5. Malden Manor parking petition update 6. Clarence Avenue / Darley Drive / Elm Road 7. Potential forthcoming business 8. Traffic Scheme Update
1. NEW MALDEN HIGH STREET - CARRIAGEWAY CONSTRUCTION
1. In the summer of 2005, the High Street was the subject of an extensive scheme to remodel its layout in order to provide a more pleasant and usable environment for all its users. The main elements of the scheme were:
§ introduction of centre islands in the carriageway as a design feature and facilitate street lighting units § a virtual central space along the road to allow safer movement of pedestrians and reduce traffic speed § realignment of the kerb line to encourage a reduction in parking § reconstruction of the footways using new surface materials § provision of new street furniture § additional footway lighting § improved pedestrian crossing points § entry treatments to side road to aid pedestrian movements and reduce traffic speed § introduction of granite setts in the carriageway as a design feature and to calm traffic speed
2. In arriving at the final design, and securing sufficient funding from TfL, consideration needed to be given to balancing the various, and sometimes competing demands, of the High Street users and other stakeholders. These were prioritised, in line with the Borough’s Local Implementation Plan (LIP), as follows:
§ Pedestrians (with attention to equal access arrangements) § Cyclists § Public Transport (Buses) § Freight/delivery vehicles § Other motor vehicles
The wishes and the commercial interests of the shopkeepers and the business community were also been uppermost in considering the options and decisions taken to undertake the scheme. Potential disruption and reduction in trading conditions were factored in to the scheme design. F2
Carriageway Problems
3. Shortly after completing the works, localised failure of some carriageway areas became apparent, especially where granite setts had been installed. These problems were investigated and remedial works, to stem the failures, were undertaken.
4. Shortly before the start of these remedial works, it became known that the gas mains and associated connections in the northern part of the High Street were included on Southern Gas Networks’ (SGN) replacement programme. It was therefore considered necessary to arrange with SGN for their works to be co- ordinated with those of the Council. Unfortunately SGN’s original proposals required a redesign, thus delaying the completion of their mains replacement. It was therefore necessary for the resurfacing of the northern section of the High Street to be undertaken as part of the previously agreed scheme extension, otherwise known as the Phase 2 works.
5. Between the completion of the SGN works and the start of the Phase 2 improvement scheme, signs of further carriageway failure occurred. These were located between Sussex Road and Dukes Avenue and have occurred on the north and south bound carriageways. In evaluating the situation, it was apparent that the failures were progressive and affecting the full depth of construction. The extent and seriousness of the deformation (dips, cracking and wheel tracking) meant that remedial repairs to the surface would not be sufficient to restore the carriageway to a suitably stable condition.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Maldens and Coombe Neighbourhood at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of the Chair and Vice-ChairRESOLVED that Councillor Simon Edwards be appointed Chair and Councillor Lesley Heap be appointed Vice-Chair for the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.