RESOLVED that: the current budgetary position be noted, and the proposed spending freeze on Community Environmental projects and Neighbourhood equipment be endorsed. 2. the Proposed Revenue Budget for 2009/2010 be noted, with the following comments reported to Budget Council: a. The marketing of facilities at the Devon Way Centre be reviewed, with particular consideration given to how to attract a higher level of lettings income. b. Consideration be given to the control of operating costs at the Hook Centre. Reason for decision To manage the current year’s budget and submit the views of the Committee on the proposed 2009/10 Neighbourhood budget to Budget Council.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
In addition to receiving its regular budget monitoring information, the Committee is asked to consider the South of the Borough Neighbourhood Committee’s Proposed Revenue Budget for 2009/10 as part of the budget setting process.
The Council’s Medium Term Service and Financial Plan 2009 - 2012, entitled “Changing Kingston Choosing Our Future – Destination Kingston”, has been published and sets out the Council’s three-year strategy, together with the Executive’s detailed proposals for the 2009/10 budget and council tax. These proposals will be reviewed by the Scrutiny Panel, after which the Executive will consider its final budget proposals and make recommendations to full Council. The Council will set the Budget and Council Tax for 2009/10 on 3 March 2009.
Recommendations
It is RECOMMENDED that:
1. the latest 2008/09 estimated expenditure as at month 9 be noted; and
2. the Proposed Revenue Budget for 2009/2010 be noted and any comments be reported to the Budget Council meeting on 3 March 2009 for consideration.
Reason for recommendations
To manage the current year’s revenue budgets and to submit the Committee’s Proposed Revenue Budgets for the next financial year to the Executive for approval.
Background
1. The Council’s revenue budget for the current financial year was approved on 27 February 2008. This report sets out the proposed revenue budget for 2009/2010 for this Committee and the latest 2008/2009 budget monitoring exercise up to month 9. - C2 -
BUDGET MONITORING 2008/2009
2. The latest estimated outturn for 2008/09 is shown in Annex 1. This budget has been amended to reflect: - underspends carried forward, - allocations from the discretionary budget, - any over/underspendings identified during the current year, - inter committee adjustments.
3. The following paragraphs update the position from that reported previously.
LEARNING & CHILDREN’S SERVICES
Hook Centre – total £20,800 overspend
4. The new gas contract has enabled officers to review the projected expenditure and the cost for the year can be assumed at a slightly lower level than allowed for in Month 6. Water consumption has also fallen fractionally and produced a small budget saving. However, supplies and services budget is overspent, mainly due to higher than expected cost for signs (including safety ones) onsite. A new café contract has been negotiated and Maverick Catering Ltd will become the contractor from 13 January 2009 for an initial period of 12 months. Some rental income can now be built into the forecast.
5. The Library branch is continuing to show an improved position from the last report. The appointment to the temporary vacancy has been delayed and another month’s salary can be assumed. To compensate for the persistent decline in book fines and DVD rentals and bolster income, income streams have broadened to encompass sale of items such as small gifts and notebooks, which are proving popular with library visitors – current forecast shows income at £2,700 better than budgeted.
Hook Recording Studio – Nil variation
6. No variation to report as the budget is a contribution towards the running cost of the Studio, which is managed by the Kingston Music and Arts Service for the benefit of all Kingston young people and schools
Devon Way Centre (Youth Service) – Nil variation
7. Officers continue to believe that additional lettings income can be generated to sufficiently neutralise the effect of rising energy prices.
OVERALL POSITION FOR 2008/2009
8. The overall position for this committee is summarised as follows:
Neighbourhood Improvements Fund £12,900 Balance from 07/08 brought forward £18,405 £31,305 - C3 -
Less over/underspend identified during year £12,105 Less total allocations £30,620
Forecasted Overspend £11,420
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.