Resolved
It was AGREED to 1. note the completion of site specific studies; and 2. approve the release of these studies to bidders. Reason for decision To enable bidders to use the information in their bids.
South London Waste Partnership Joint Committee agreed this item on Wednesday 29 April 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
It was AGREED to 1. note the completion of site specific studies; and 2. approve the release of these studies to bidders. Reason for decision To enable bidders to use the information in their bids.
As part of the work of the OBC and procurement and in minimising pre-application planning delay and the associated costs, preliminary site studies reports have been completed on the Reference Project sites.
This work is a necessary follow up to the work we described in the OBC and on that basis it draws upon the Reference Project technologies, referring to both mechanical and thermal processes. As the partnership is going out to open procurement for any of a range of technologies available, we must again emphasise that these studies are generic and not an attempt to match a given technology to a given site. Where specific treatment solutions are mentioned, this is purely by way of an example and as a sensible and more cost effective alternative to assessing every conceivable technology on every site.
The Joint Waste Committee is asked to:
1. note the completion of site specific studies; and
2. approve the release of these studies to bidders.
INTRODUCTION
1. As part of the due process of the procurement and in mitigation of the risks associated with planning, the Management Group commissioned Entec to undertake preliminary studies at each of the three Reference Project sites.
2. These studies set out to determine that the sites are capable of providing residual waste treatment, as we have asserted in our OBC. The studies set out to identify technical constraints to the development of each site, which could lead to delays, additional costs or otherwise affect the ability to deliver waste treatment facilities.
3. The studies also examine and suggest potential mitigation measures, where constraints are identified.
4. The studies provide important information on utilities availability, visual impacts, transport impacts, air quality and emissions, flood risk, and impacts on the local environment with reference to conservation areas.
5. The studies found no barriers to offering these sites to bidders and confirm that we can have a good deal of confidence as to their viability.
6. These reports will be valuable in lowering the commercial risks that bidders will face on these sites. This will aid the partnership in attracting a strong field to bid for the contract and will lower the risk premium that bidders place on planning in the absence of such information. Agenda Item 3 2
7. Further investigations will be required on these sites, particularly in the event of bidders choosing to use them. For example, a full Environmental Impact Assessment, will be needed on each of the sites.
8. Release of these reports with the procurement documentation will enable bidders to make important commercial decisions. The timely release of these reports demonstrates the partnership’s awareness around a key risk area, namely planning.
Further investigations of the sites
9. A key obstacle to use of the sites is the re-routing of power lines at both Factory Lane and Garth Road. Initial estimates suggest this could have up to a 2% capital cost impact on the currently modelled costs (approximately £2m at each site). It is worth remembering that the Partnership has modelled up to a 30% sensitivity on capex within the financial model. However, Entec readily admit this estimate needs further investigation and officers are following up on this with the power companies to have a more precise idea of the likely costs.
10. There is a statutory need for site specific Flood Risk Assessments but none are considered by Entec’s planning consultants to be prohibitive and are quantified as low probability flood risks on all sites.
11. An EIA scoping report and full EIA will need to be completed.
Authors: Frank Smith and Emma Smyth
Background papers – Nil
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
OBC REFERENCE PROJECT SITES REPORTSReport | 56 KB | DownloadRead as text |
Follow South London Waste Partnership Joint Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2025 | Election of new Chair and Deputy Chair of the committeeRESOLVED that Councillor Christopher Woolmer be elected as Chair for the 2025/26 year. Carried Election of Vice Chair... | Decided | Open |
| 17 Dec 2020 | MinutesThat the minutes of the previous meeting held on 9 September 2020 be confirmed and approved as the correct record. Vo... | Approved | Open |
| 17 Dec 2020 | Partnership Budget Update - Month 6To note the contents of the report. Voting: Unanimous | Noted | Open |
| 17 Dec 2020 | Partnership Budget 2021/22To agree the proposed budget for the core activities of the Partnership. Voting: Unanimous | Agreed | Open |
| 17 Dec 2020 | Communications UpdateTo note the contents of the report. Voting: Unanimous | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.